Written evidence from AES UK & Ireland (EEE0024)
AES Kilroot Power Limited (KPL) in the competitive Single Electricity Market (SEM) since 2010
Over the past 3 years on average K1 and K2 have run in excess of 6,400 hours they generated 86% of the time they were available.
Kilroot Units K1 & K2 running hours
It is worth noting that no generation plant in the system is used to full capacity, as even the cheaper plant are run at lower loads either to provide operational reserve or when the wind is blowing and demand is low.
Trend over last three years
In 2017, on our figures, the Kilroot Coal Units K1 and K2 supplied approx. 15% (1.32TWh) of the Total Energy Requirement (TER) for Northern Ireland (9.07 TWh). It is worth noting that 2017 was a very windy year and there were adverse commodity movements impacting Kilroot dispatch, so we look back over the past three years to capture the trends including commodity volatility.
Running hours 2015, 2016 and 2017
As mentioned above 2017 was a high wind generation year, and in which commodity prices moved significantly negatively impacting Kilroot coal units. Due to this the running hours for Kilroot Coal units were less than previous years as outlined in the table below.
| 2015 | 2016 | 2017 | 3 year Average |
K1 and K2 Running Hours (% of hours available) | 13,241 (98%) | 14,769 (93%) | 10,634 (68%) | 12,882 (86%) |
K1 and K2 Generated TWh | 2.02 (22% of NI TER) | 2.03 (22% of NI TER) | 1.327 (15% of NI TER) | 1.8 (20% of NI TER) |
Average Capacity Factor % for K1 and K2 on Coal |
66% |
66% |
43% |
58% |
This year’s running hours from 1st Jan 2018 to 22nd March 2018
Time Horizon | K1 MG |
| K2 M |
| |
3888 | Periods | 228326 | MWhr | 164741 | MWhr |
1944 | Hours | 228.3 | GWhr | 164.7 | GWhr |
81 | Days | 11% | Of NI Demand |
| Of NI Demand |
Kilroot’s generation and revenue profile
Essentially K1 and K2 run baseload for most of the Winter (October to March) so “surplus” is negligible. In the summer, each unit run as “mid-Merit” units within the economic merit stack and are also dispatched to address NI system constraints.
Any assessment of generator profitability should include an understanding of the risks borne by a Generation Licensee within the market and regulatory conditions
Whilst capacity payments are not intended to cover all fixed costs of all generator classes, the predictability and relative certainty of the payments are vital to ensure many generators are financially viable. We do not view regulatory approved capacity payments as a ‘nice little earner’.
Our profit margin has been steadily eroding since 2013 on the back of commodity and market pressures. The challenges of the market and a significant impairment in 2015 have meant AES Kilroot Power Limited has not paid a dividend to the AES Corporation since 2013. However, we have continued to invest significantly in new technology (such as Energy Storage) on a merchant basis and to invest to comply with environmental legislation to ensure extended life of the assets.
We would draw your attention to the most recent Regulator Commissioned “Generator Financial Performance in the Single Electricity Market (SEM)” Report published in November 2016 by Cambridge Economics that showed
Northern Ireland is operating only a limited PPA market: under a PPA you have a lower cost of capital – higher operational risk but lower commercial risk. Today, and since 2010, we have operational risk plus commodity risk, which is exacerbated by the lack of liquidity in the market and the less manageable volatility in the market.
The last PPA in Northern Ireland is between Viridian’s Power NI Power Procurement Business (PPB) and the AES Ballylumford C Station. In 2015, the Utility Regulator had the opportunity to terminate this PPA, but instead determined that at the point of evaluation the contract remained in the interest of consumers. The Utility Regulator can terminate this PPA with six months’ notice, and given their on the record comments in relation to PPAs it is surprising that the termination powers have not been exercised.
Innovation and investment at Kilroot
AES has a long history of innovation globally and locally. As well as continued environmental and efficiency investments, AES Kilroot Power Ltd tested the potential for the co-firing of wood pellets in the early 2000s before many other generators had started to explore biomass opportunities.
While this particular approach was not sustainable at Kilroot, AES Kilroot Power Ltd has invested in deploying world leading low emissions technology at the site. Since 5 January 2016, the Advancion Array has been operating as a fully commercial project within the system operator’s existing Harmonised Ancillary Services system, without any form of customer subsidy. The array provides 10 MW of interconnected energy storage, equivalent to 20 MW of flexible resource.
It is a complete, battery-based alternative to traditional peaking power plants and pumped hydroelectric storage projects that provides a dependable, smart and cost-competitive means to support a reliable, low carbon electricity system for the Northern Ireland economy.
Additionally, Innovate UK provided Energy Catalyst funding for Queen’s University Belfast to investigate the full potential of energy storage to benefit the UK and Ireland electricity systems by analysing the impact of this array.
Other planned innovation included significant investment in SUFA (Secondary Under Fired Air technology) to provide emissions compliant generation 2020-2023 with no reduction in running hours and avoided cost to consumers of new generation before required. The Utility Regulator disallowed recovery of this investment during the USPC process.
The bid process
In relation to assertions that ‘a lot of the decisions about what AES has done were not taken by Ian Luney and his team at Kilroot”. This assertion is baseless and without any foundation. The Directors of AES Kilroot Power Ltd have obligations with respect to Financial, HS&E, Company and Energy legislation and the business is managed at a local level within the Northern Ireland energy market. Furthermore, it is the local Directors who carry all liability associated with complying with our Licence and other contractual obligations.
In relation to being able to “plan for not securing capacity payments” we would re-emphasise the point the each of the Kilroot coal units had statutory maintenance periods through the 2018/19 period which were required to ensure that the units could run. If this work was not undertaken then the units would not be in a position to operate.
AES Kilroot Power Ltd bid price for the coal units was subject to regulatory oversight by the Utility Regulator (UR) and its consultants in line with the prescribed auction process rules and did not include any buffer for margin or risk contingency:
The capacity revenue for the Ballylumford 536 MW CCGT was awarded to Viridian Group’s Power NI PPB business who bid this into the capacity market auction, not AES.
The derogation process
Much has been made of this by the regulator and the system operator but this would have required KPL to apply for a binding derogation for a new market that hadn’t been developed yet based on figures and costs that no one could predict.
Every Generator without a derogation in place had a mandatory obligation to bid into the first T-1 Capacity Auction.
In order to comply with the 36-month notice period, it would have been necessary for AES to apply for the binding derogation in May 2015. This is 6 months in advance of the 36-month rule being added to the Grid Code, in order to ensure it could opt out of the Capacity Auction.
While the broad principles and parameters of the market were outlined by the regulatory authorities, very little was known of the details, rules, tariffs and timelines for each pf the three markets of Energy, Capacity and DS3, and indeed much still remains unclear (as the regulator alluded to) and subject to change.
This is reflected in the most recent delay to DS3 Volume Capped Auction for High Availability Units, which is the part of the market the AES Kilroot Advancion® Energy Storage Array is expected to operate in. When AES last gave evidence to the Select Committee the DS3 market was set to come into effect in late 2016/early 2017.
In any event the 36-month Grid Code notice obligation has been contentious from the outset. AES Kilroot Power Ltd, AES Ballylumford Ltd and other Generator Participants including ESB objected to this Grid Code modification in Northern Ireland as it was inconsistent with the proposed T-1 capacity auctions. Generator’s tabled an NI Grid Code modification in relation to the 36month notice period but neither SONI nor the Utility Regulator took any action to address these concerns.
In addition, the issue was raised multiple times at Regulatory ISEM Senior Stakeholder Meetings and whilst the issue was acknowledged it was never addressed. In the CRU paper Regulatory Approach to Maintaining Local Security of Supply in Electricity it is acknowledged that the 36month Grid Code notice obligation could cause issues with the results of annual T-1 Capacity Auctions and a process was put in place to provide clarity on how this could be addressed with an explicit acceptance that Licencee’s had to be able to finance their activities during the transition period to the first T-4 delivery date (2022/2023).
The UR has produced no similar paper and for the avoidance of doubt KPL are of the view that no Licencee can be obliged to operate for 36-months if it is not financially or economically viable to do so.
Material Changes in the Market
As well as changes to the auction timelines, there were two material changes in the market:
• 15th December 2017 SONI Operational Constraint Document published continues to include operational constraint for one Kilroot Unit to be run if NI demand was above 1,400MW and two Kilroot Units to run if demand was above 1,550MW.
• 15th December 2017 - T-1 Capacity Auction closed
• 18th December 2017 – RoI Regulatory Authority (RA) published paper on Regulatory Approach to Maintaining Security of Supply in Electricity (there is no equivalent document for NI)
• 20th December 2017 - provisional auction results issued to AES
• 20th December 2017 - EirGrid/SONI (the TSOs) jointly published a Generation Plant Closure Process document
• 12th January 2018 - SONI (NI TSO) provide to UREGNI (NI RA) requested assessment of capacity and NI system stability based on provisional T-1 auction results for May 2018 to September 2019 period
• 19th January 2018 - SONI issues revised Operational Constraints Update which removes the previous October 2017 Updates reference to requiring one or two Kilroot coal unit(s) when demand in Northern Ireland exceeds 1,400MW and 1,550MW respectively
• 25th January 2018 - final T-1 capacity auction results confirmed
• 13th December 2018 - subject to 6 months’ notice, the second T-1 auction will take place, for period Oct 19 to Sep 2020
• March 2019 - Subject to almost a year’s advance notice, the first T-4 capacity auction will take place, for the period Oct 2022 to Sept 2023
Claim this shows competition working
The outcome of the auction
Interconnectors
In the SEM market from 2007 to date:
In the I-SEM Market much is expected to change
Not all megawatts are the same
Orderly and fair transition
We would draw your attention to the article by Professor John Barry about the result of the Capacity Auction entitled “Closure of Kilroot – or how NOT to manage a ‘just transition’ to a low carbon energy economy”, where he states
“Energy transitions are decade long processes that need to be manged, mapped and based on clarity, openness and transparency. The shift from one energy system to another is not as simply as switching from one fuel or source to another.”
He asserts that the outworking of the auction undermines ability of an energy company to deliver a fair and orderly closure of a coal plant replacing it with no and low emissions technology.
Will NI be reduced to more of the same old-style CCGT gas plants, continuing our ‘carbon lock-in?
Northern Ireland as a constrained area
It is AES’ understanding that Northern Ireland in its entirety is deemed a “constrained area” by the CRM rules.
Coal Plant Closures
Unlike the coal units at Kilroot, Eggborough is not subjected to the 36-month derogation notice period and can close in an orderly fashion.
16 April 2018