Written evidence submitted by Wates

 

Background on Wates Group

Wates Group is a family owned, construction focused business in its 118th year of operation. Wates works nationally from 16 regional offices and has an annual turnover of around £1bn. Education is a core sector for the business and represents 40% of Wates Construction’s turnover. We built our first school in 1961, and each year we typically deliver around £200m of education projects benefitting 13,500 students annually.

Our recent relevant experience in school construction includes:

 

Building Schools for the Future

 

Priority School Building Programme

 

Purpose of this paper

We have been asked to reflect on our experiences on the Priority School Building Programme and other education projects; this paper provides our point of view on the following key issues as requested:

  1. How the allocation of funding under the Priority School Building Programme has affected schools, including those who were due to receive funding under the Building Schools for the Future programme
  2. The impact on schools in need of repair or rebuilding that have not received funding
  3. The experiences of schools who received funding under Phase 1 of the programme
  4. The value for money of the PSBP compared to Building Schools for the Future

 

 

 

 


  1. How the allocation of funding under the Priority School Building Programme has affected schools, including those who were due to receive funding under the Building Schools for the Future programme:

Because of the varying criteria used on each programme to determine the priority of which schools to fund, their allocations affected different school types. Table 1 highlights the main allocation criteria of each programme and the outcome they had for different school types.

 

Table 1 – funding selection criteria by education programme, showing who benefitted and who didn’t

Programme

Assessment level

Assessment criteria

Outcome on which schools got funding

BSF

Local Authority average

 

A weighted mix of the following measurements averaged out over the entire LA:

Pupil performance (attainment)

Deprivation level (Free School Meals)

Entire LA education estates were allocated funding for a mix of new build and refurbishment.

Good for:

  • LAs with low attainment and high deprivation irrespective of the condition of individual schools

Bad for:

  • LAs/schools delivering excellent attainment despite the poor conditions of their schools
  • Schools in really bad condition but in LAs that averaged better attainment and/or lower deprivation

PSBP 1

Individual Schools

The condition of each area of the school was assessed on a scale, with the overall school condition being averaged out on a percentage basis

Good for:

  • Schools considered to be in the worst condition overall

Bad for:

  • Schools in mostly poor condition, with some new or refurbished areas, which took them above the average qualifying criteria
  • Schools in mostly good condition but with some areas in terrible condition

PSBP 2

Individual Buildings

Condition of individual blocks/buildings

Property Data Survey performed by independent consultants based on criteria set by the EFA

Good for:

  • Schools considered to be in the worst condition overall
  • Schools with areas in terrible condition irrespective of the condition of the rest of the school

Bad for:

  • Schools that just missed out on PSBP 1 potentially will not haut which no longer qualify under PSBP 2 due to the change in assessment criteria
  • Schools that did not apply

 

With the cancellation of the BSF programme, all follow on schools and in some cases sample schools that had not achieved financial close were stopped mid-way through the process. Following an extended period with no policy to replace BSF, many of the cancelled schools have ultimately gone on to be delivered as part of the 261 schools on PSBP 1.

However, for some cancelled BSF schools, the change in funding allocation criteria under PSBP 1 may have essentially sent them to the back of the queue as they no longer qualify as a ‘priority’. This is not necessarily a bad thing as it means money is spent where it is needed most but for the schools affected it must be devastating. 

The Priority School Building Programme essentially ‘does what it says on the tin’ in that it targets the schools in the worst condition. The criteria have been refined on PSBP 2 to ensure schools with significantly sub-standard blocks/buildings are not disqualified as a result of recent improvements elsewhere on the same campus.

From our experience visiting many of the schools that have received allocations under PSBP, we would support the allocation methodology. Each school’s definition of ‘poor condition’ and ‘priority’ will vary greatly, as it is subjective. Many are dealing with on-going maintenance issues and aging campuses which they consider a ‘priority’ but compared to other schools they are far better off. PSBP is targeting the schools that are in a truly terrible state and need immediate attention.

 

  1. The impact on schools in need of repair or rebuilding that have not received funding

In early February 2015, the 277 PSBP 2 schools were announced, we understand that the approved schools do not yet know how much budget and for what scope they have been approved for, but at least they know their condition will be addressed.

The schools that have yet to get any PSBP funding allocation appear to face a long wait with PSBP 1 set to finish in 2017 and PSBP 2 in 2021 it is unclear when the next programme will come along. Recent history could suggest nothing until 2019.

The absence of any longer term commitment means that unapproved schools are frustrated and face years of uncertainty, scratching around for funding from their local authorities to keep their schools running via the School Condition Allocations.

Meanwhile many of them are being required to accommodate pupil rolls in excess of their capacity and/or are being forced to compete with new nearby Free Schools that receive capital funding to ensure their facilities are fit for purpose.

 

  1. The experiences of schools who received funding under Phase 1 of the programme

We believe that the experiences of the schools that have received funding under Phase 1 of PSBP can be summarised as follows:

PSBP 1 is delivering 261 schools including many of the cancelled BSF schools. The programme set significantly reduced budgets contrasted against a backdrop of BSF level-expectations.  These aspirations came from:

This has resulted in frustrations around a two-tier estate and a perceived effect on a PSBP school’s attractiveness to new pupils and staff compared to BSF and Academy programme schools. But the main issue was the stakeholder expectations in what their school should look like, how it should be designed and how much they influenced the process.

The EFA have developed baseline school designs and related funding levels which they feel essentially determines what makes a good school design and what it should cost.

This means that the EFA does not need as much input from the school; they only really need the school’s buy-in on a high-level plan of how the spaces are arranged internally and externally and aesthetic finishes such as colours, furniture etc. As a result compared to BSF, the school representatives are far less involved on PSBP.

BSF procurements typically took up to 18 months including six to eight, 3½ hour meetings led by the local authority or school to discuss and develop the design. They also participated in separate ICT and FM related meetings that further influenced the design.

Under PSBP, which typically takes 28 weeks, they attend six one-hour engagements with both contractors to agree the design including ICT plus a maximum of five further one-hour meetings with the successful bidder to input into the completion of design information and discuss and agree phasing, working arrangements and safeguarding during delivery.

Our experience is that schools feel like they are being kept at arm’s length and find the process quite demanding. They are non-construction professionals expected to participate in multiple engagement sessions; FF&E, colour and RDD meetings, legacy decant studies etc. all while continuing to do their day job.

Some express frustration at not being able to change things and feel that they receive a lot less guidance and support under PSBP than was provided on BSF, which combined with the quicker timescale of PSBP leaves them feeling somewhat rushed into making decisions on things they do not feel totally comfortable with.

The school representatives are education professionals that will probably only go through the process once, what they think is good school design will be based on their own experience teaching in their current and previous schools. The schools we are building under PSBP will out-last all current staff and most of the teaching methods so while it is important to take on board their point of view it is important to maintain the future proofing of the school as much as possible. Therefore a balanced amount of school involvement is required to get the decisions needed but needs to be carefully managed as this can be a source of frustration and friction between the school, EFA, the local authority and the contractor.

What this requires is strong alignment between the EFA and contractor to manage the school’s expectations within budget and within the agreed timelines.

Overall while some schools may be frustrated that they do not get as much under PSBP as nearby schools may have received under BSF, they acknowledge that they are better off than those still waiting for funding.

Once they move into their new good quality fit for purpose PSBP School and consider the conditions they were operating in previously, our experience is that in the whole they are absolutely delighted.

 

  1. The value for money of the PSBP compared to Building Schools for the Future

It is difficult to compare the true value for money of both programmes as they represent the delivery of two different ideologies:

To highlight the major differences between the programmes Table compares our experience of the major elements of each:

 

Table 2 - a high levlel comparison of BSF and PSBP

 

Building Schools for the Future

Priority School Building Programme

Underlying ethos

“Inspirational learning environments, delivering educational transformation”

“Functional, fit for purpose buildings”

Design principles

Bespoke exemplar architecture

BB99 plus ‘extras’, BREEAM Very Good to Excellent

Standardised/component based design

BB99 less 15%, Facilities Output Specification

Dedicated specialist spaces

Dedicated rooms for music, music practice, dance, theatre etc

Multi-use performance spaces

 

Dining and kitchens

Bespoke design, full school dining capacity, separate dining areas for older year groups

Formulaic dining areas sized to require staggered timetable, kitchen sizes do not easily facilitate religious dietary requirements e.g. halal

SEN in mainstream schools

Design reflective of SEN need in community demographics

Set formulaic allowance irrespective of community demographics/need

New school location/ externals/sports facilities

Wide spread use of temporary accommodation to allow the optimum building location

Masterplanned campus developments with welcoming designs, all new sports provision and mature landscaping

 

Temporary accommodation is considered a waste of money, which significantly restricts where the new school can go, thereby preventing the optimum building location

Buildings located to cause minimal impact, facilitating the maximum re-use of existing external areas/infrastructure, landscaping to grow into, compromised campus layouts

ICT provision

Completely new ICT infrastructure, all new ICT equipment and managed ICT services

New infrastructure but with re-use of legacy active equipment where possible, no new equipment, no centralised managed service

Furniture, fixtures and equipment

All new fixed and loose FF&E including multiple breakout areas etc

Minimum provision possible. New fixed FF&E but re-use of legacy wherever possible, no budget for new loose FF&E unless school is expanding

Impact of facilities management risk profile

Because FM risk sat with the contractor they tended to over-design specific components, to reduce the risk of unavailability reductions e.g. boiler capacity

FM risk sits with school/LA therefore contractors design only to meet the specification requirement

Building life

60 years

60 years

 

In order to give an opinion on Value for money we have compared both programmes on the following issues:

 

Construction Costs

To make a comparison on build costs we have compared a BSF school that we have the data on and demonstrated what the PSBP equivalent would be based on the current design and funding criteria.

 

Table 3 - secondary school comparison BSF vs PSBP

 

Building Schools for the Future Secondary School

Priority School Building Programme Equivalent

PSBP reduction            vs BSF

Number of pupils

964

964

n/a

School area

9,292m2

7,124m2

-30%

Construction budget

£23.5m

£12.96m

-81%

Cost per m2

£2,529/m2

£1,819/m2

-39%

 

Clearly PSBP is delivering ‘compliant’ schools for significantly less money than BSF did, but it must be remembered that BSF schools answered a different question on compliance. While much of the savings result from a more efficient use of space and a streamlined process, some compromises (including some of those shown in Table 2) have been accepted in meeting the reduced funding parameters. Whether these compromises are acceptable depends on which programme’s ethos you agree with.

In BSF competitions there were typically no extra marks for being under the affordability level, so to win contractors tried to incorporate the most ‘extras’ to score higher marks. This took many forms including extra floor area, grander entrances with triple storey heart spaces, community use areas, wider corridors, multiple breakout spaces, responses to specific client requests and enhanced externals. While the school benefitted from the ‘extras’, ultimately the local authority was left with an unfunded but increased long term maintenance expense and the ‘extras’ were paid for with money that could have gone back into the public coffers.

Our opinion is that PSBP delivers better value in this regard. To get appointed to the framework contractors competitively bid against the EFA’s prescribed expectations which they have predetermined to be the minimum requirement. This has resulted in significantly lower building areas and cost per m2.

Furthermore, on each project contractors still bid in competition and must deliver compliant designs against the EFA requirements, with efficient designs and where possible deliver savings against the budget to score added marks.

The EFA uses a formulaic funding allocation to budget projects. One challenge that this approach poses is that all budgets are set using allowances of 12% for external works and 5% for project abnormals irrespective of project specifics.

What this essentially means is you get the same budget for the same sized school, irrespective of the project challenges and schools with less challenging sites may get better schools whereas schools with challenging project issues will have to accept compromises. Budgets should be set using an independent cost expert’s assessment of the external and abnormal costs following the feasibility study rather than fixed with a formula before the project is even looked at. This is the main issue with PSBP project budgets.

A lesser issue is that the furniture, fixtures and equipment allowances in the formula are fixed and neither adjusted for project location or inflation which means that currently:

 

Added Value initiatives

In addition to the ‘extras’ above, which are often referred to as added value, BSF programmes also included a wide range of specific added value and partnering initiatives, which were designed to benefit the wider community and local economy, not just the school. In comparison PSBP delivers added value limited to the project under its KPIs and with the exception of apprenticeships does not explicitly promote the local agenda. There are no more requirements under PSBP to deliver wider added value commitments.

Procurement process and bid costs

On BSF procurements, local authorities spent 12 months developing their BSF Outline Business Case, including fully designed schools as part of the feasibility studies, and then typically took at least twelve months to select a preferred bidder.

Following an initial stage where up to six bidders developed outline proposals, two bidders were selected for the final stage of competition. Both were required to develop detailed plans on how a Local Education Partnership would be established and operate with the local authority as well as developing complete designs and delivery strategies for two schools.

Once appointed it then took the preferred bidder a further six months to reach financial close and commence construction work on site. 

For the two bidders that got through to the competition stage this meant risking between £2.5 to 3m in bid costs to secure two sample projects averaging £50m and exclusivity over a further £150 to £200m of construction turnover.

In addition to the contractor’s costs the process caused both the local authority and the central body (Partnership for Schools at the time) to incur significant costs. They had a large team that spent a year developing the OBC and essentially man marked the contractors’ teams on all aspects of the project attending multiple meetings with both bidders for each of the work streams (including design, FM, ICT, financial, commercial/legal and partnering).

By contrast PSBP follows a process which is a lot more efficient.

The EFA expects their feasibility study and approvals to be achieved within ten weeks, allowing projects to get to market much quicker. All nine framework contractors are invited to tender and are given one week to submit an initial response. Typically two to four respond incurring costs of circa £15k each; the EFA team then shortlists two bidders who engage in six weeks of design engagements before submitting their bids, typically incurring further costs of around £200k each. The selected bidder then spends around 16 to 20 more weeks finalising the design and achieving financial close before commencing on site.

Overall at an average of 38 weeks in total, PSBP projects take under 30% of the time BSF procurements took at 130 weeks. They also require contractors to bear a risk to reward ratio that is about one third of what it was under BSF.

Not only are PSBP timelines shorter, but the project teams on both contractor and authority sides are also much leaner, thereby reducing the costs associated with the procurement further. This ultimately means that more money is spent on bricks and mortar rather than being diverted into delivery costs that provide no benefit to the education of children.

 

Conclusion

While Wates is not best placed to comment on which of the two ideologies behind the programmes is right and/or more effective, in terms of the built environment elements we consider that PSBP delivers significantly better value for the taxpayer’s pound.

While the programme’s funding and timeline principles were initially met with a sense of disbelief, contractors have been challenged to develop better, more efficient ways of working and procuring construction work. We believe that the principles of PSBP are sound and it not only correctly targets the schools in most need, but causes contractors to focus the spend on exactly where it is needed.

This opinion is demonstrated by our on-going commitment to the education sector in general and specifically the centrally funded schools programmes.

However we do feel that the PSBP programme needs to be refined to reflect the changes in the construction marketplace that have developed since the programme was introduced.

The programme faces challenges from the re-emergence of the construction economy within the UK meaning EFA projects are competing for resource and bid budgets against more attractive projects that offer far more beneficial risk/reward profiles to contractors.

With the success of the programme and the ever increasing number of projects the EFA faces the challenge of ensuring sufficient resource and funding is available to invest in developing robust project feasibility studies to set accurate budgets and achievable timescales and while facilitating the successful management of the programme.

We trust that this paper has been informative and provides you with a different viewpoint to that of your own. We are very proud of the work we do in education and are committed to supporting the EFA in their continuing efforts to deal with our aging education estate and the growing demand for pupil places.

 

 

 

March 2015