Written evidence submitted by Dr Gareth Davies, Aquatera Ltd (RES0036)

 

Introduction to Orkney

Orkney is a special and unique place when it comes to energy.  The are some aspects of energy in Orkney that are different and distinctive from other places in the UK and globally.  But what is especially special and unique is the breadth and diversity of energy features that are exhibited within and around Orkney at a scale and in a stage of progression that many other parts of the UK and the wider world can see, experience and learn from.  Orkney is more than an energy island, it is an energy archipelago, it is a hub of imagination, invention and innovation and it is a community of vision, ambition and foresight. 

 

Some key points are listed below

 

Record breaking achievements

Major energy infrastructure

World leading experience and expertise

 

Orkney is not just the end of a grid spur it is a strategically important location for Scotland, for the UK and for the wider worldOrkney has been a major energy hub for the last 40 years through the operation of the Flotta Oil TerminalOrkney is the gateway to significant renewables generation capacity – there is at least 5GW of generation potential around (within 12 miles) of the islands (possibly as much as 10GW).  Further offshore Orkney shares the potential for over 100 GW of offshore wind potential along with Shetland and the Outer HebridesOrkney has also been the site of numerous technological breakthroughs, the base for introducing many pioneering ways of managing energy supply, an exemplar of how energy awareness within a community can lead to transformational changes in customer behaviour and a leading example of how engaging local investment and involvement can help energy developments progress ay unparalleled rates and scales.

SPOTLIGHT: Orkney and renewable electricity

 

Some key milestone dates for electricity generation from renewables:

 

2002                            First calls for new transmission grid connection

2002                            Active network management scheme suggested by OREF in discussions with SSE

2003                            First transmission grid application made by local renewables developer

July 2008              First net export month

2012              SSEN close down grid for new generation above G83 capacity (unilaterally/without consultation)

2013              Grid Action Group established – 28 possible action points identified – only 1 taken forward by SSEN

2013                            First net export year

April 2015              Last net import month

April 2017              New export record of 5,000MWh

April 2019              ReFLEX project kicked off – ground-breaking integrated energy systems projects

Ongoing              Regulatory and network management obstacles placed in the way of rolling out ReFLEX approach             

 

 

 


How has Orkney earned this opportunity?

          Vision - Oil 1970s; wind 1980’s; marine 1990’s, efficiency 2000’s, hydrogen and storage 2010’s, integrated energy solutions 2020s, large scale developments 2020s & 30s

          Commitment - People, money, sites, demand, ideas

          Knowledge and expertise - Unrivalled experience, facilities and cluster of experts and specialists

          Willingness to share know-how and success

 

 


Issues with the needs case process

SSEN failings

Ofgem failings

  • Needs case focussed on transmission level service and ignored distribution level synergies
  • Needs case ignored offshore wind capacity
  • Needs case ignored non-firm existing capacity
  • Needs case ignored future increases in demand as decarbonisation takes place
  • Needs case ignored options for considering storage and balancing capacity with the system
  •  
  •     
  • The process fails to recognise value and service to the local customer base despite them being asked for decades to pay in for wider socialised system improvement which have no local consequence
  • The wider social and economic benefits were ignored
  • The system balancing benefits of distributed generation were ignored
  • The effects of system losses were ignored
  • The carbon and linked monetary cost of supporting ongoing carbon sourced electricity in preference to renewables were ignored
  • The views and needs of the community were disrespected
  • The strategic R&D importance of Orkney for the UK was ignored
  • The level of strategic upfront investment required of the development community was not appreciated or accounted for
  • The past use of every MWh of the available system was not taken into account
  • The capacity target and associated timing set were too inflexible and demanding (subsequent timing relaxation due to COVID is however appreciated)

 


Who pays for works involved

Preparing the needs case

[A much better solution would have been for SSEN to commission the local community and local generators to develop an initial needs case which they could then add their own network understanding to, perhaps a £50k funded local process would have been appropriate]

 

Meeting needs case conditions

Task

Amount

Management

200k

Feasibility and site finding

30k

1st stage grid application

10k

2nd stage grid application

50k

Technical investigations

50k

PPA negotiations

50k

Public consultation

40k

Landowner access and wayleves

30k

Legal documentation and processes

40k

Baseline surveys

200k

Preparing EIA documentation

200k

Submittal and review of application

50k

Sub-total

950k

Participation in any planning enquiry

200k

Contingency

100k

Total

1250k

 

There are 7 to 10 developments underpinning the needs case, this means that the Orkney community, the supply chain and local project developers have been required to invest, at total risk, some £10 million against the Needs Case process.

 


What advantages would the grid connection provide?

 


Transmission charging regime

 

The transmission cash cow

The present transmission charging regime places excessive and uncertain costs on development activity.  The basis for the locational premise of the charging regime has changed.  In the old model generation capacity based upon coal and hydrocarbons was encouraged to be built close to urban and industrial demand centres.  Given the co-location of coal and urban development in the UK and the southern abundance of gas resources the established north/south and west/east high/low charging gradients may have held some logic.  In today’s and tomorrow’s worlds with an imperative for decarbonisation the availability and suitability of resources is reversed with northern and western areas holding critical and over time absolutely critical resources upon which the UK will be reliant to achieve Net Zero and wider decarbonisation.

 

The present zoning structure is therefore likely to need to be changed and the charging philosophy needs a total overhaul.

 

Development needs to be encouraged in areas where there are sufficient resources, that can be delivered acceptably at an affordable cost.

 

To show the effect that transmission charges can have, the following calculation, based upon information currently available, estimates the TENUoS costs for the cluster of wind farms currently being developed in Orkney.

 

Key assumptions:

 

Total revenue = £487M+£395M+£443M = £1325M - £1490M over 40 years

 

CAPEX – £264M x 2 = £484M

OPEX - £7.9/yr = £317M over 40 years

TENUoS @ £100/kW - £280M+£227M+£255M  = £762M

 

Total project cost = £1,563

 

Compared to the estimated revenue this estimated TENUoS would make the development not profitable given the £73 million estimated deficit

 

Applying actual total connection cost of say £500M makes the scheme profitable with a surplus of around £189M over 40 years.

 

Obviously the actual TENUoS charge level is not known to any developer and under the present system are not known until the works are completed by the network operator.  There is a history of cost overruns for such works particularly in the Isles.


People closer to generation pay less – apparently an Ofgem proposition – is that true?

There are many factors linked to what we pay for energy which affect customers in different parts of the country to different extents.

 

 

Part of the bills we pay for energy are directed into system investment – each customer in Orkney pays 12.5% of their bill for socialised network upgrades – because Orkney pays more for its energy Orkney customers pay more towards the grid – but Orkney never gets its turn at socialised grid investment, instead local developers and shouldered with the bill and the associated reduced profitability.

 

Where do energy customers come from?  It is obvious within Orkney, and important to remember, that energy makes our society.  Energy investors, energy employees and energy service users are also energy customers/consumers.  Without investment, jobs and services there is no society and there are no customers or consumers for Ofgem to ‘safeguard’Unsustainable consumer safeguarding will lead to unsustainable communities and society!!

 


Targets – are they useful?

 

 

Local perspectives

 


How do targets affect jobs?

The works to prepare for and meet targets have been very helpful to a place like Orkney that has committed itself to making a contribution to this endeavour

 

 

Type of activity

Numbers of people

Planning and permitting

30

Technology development

30

Project development

10

Technical services

30

Testing

20

Marine services

60

Insurance and finance

5

Regulation and enterprise

3

Research

40

Teaching and training

10

Students

35

Total

273

 

Monetary value of works connected to renewables in Orkney undertaken between 2000 and 2019:

 

 


What is local opinion about targets?

 

Why Orkney supports renewable energy – for Orkney renewables means money and jobs

 

Orkney understands energy as generators, as distributors and as consumers

Grid connection to major parts of Orkney was only achieved in the late 1970’s, we appreciate the benefits of connectivity in a very tangible way

Orcadian’s use more energy than any other part of the UK due to strong winds, cool temperatures, drafty housing, big sea and air journeys

Orcadian’s pay more for energy due to the amounts of energy used and due also to the excessive locational tariffs added to fuel and electricity delivery

The quality of supply can be poor with many winter wind induced faults

Over 270 people currently employed in renewables sector and a further 150-200 in the oil sector, so 420 to 470 people are currently employed in the energy sector across Orkney

A huge part of Orkney’s success has been/is willingness to invest collectively and individually in its own energy future

That local investment of over £170M, is at risk of becoming a stranded investment due to the ongoing delay in delivering a new grid connection to Orkney

 

 

 

 

 

 

 

 

 

Exportability of experience, technology and knowhow – how does that work?

 

 

 

 

 

 

 

 

 

 

 

 

 


Orkney energy hub and prioritising internal UK connection

Looking forward and taking into account Orkney’s unique geographical position, its unique and rich energy resources and its unique strategic industrial and energy role will likely lead to many other follow-on connections to OrkneyThese connections may be through other cables, pipelines, shipping etcThe key point is that in every other respect that the grid, Orkney is a strategic hub not a marginal spurGrid connectivity is now limiting the wider role that Orkney can play and therefore limiting the development potential of the UK at a time when the country needs every opportunity it can find

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Benefits of UK intra-connectors

 

          The image previously graphically shows the large number of continental interconnectors that have been considered and their length – which is roughly equivalent to their cost

          None of these interconnectors exploit UK resources, none create UK jobs, none support UK technology, none will pay UK tax on generation and none provide national energy security – especially at a time when we are reducing reliance on European systems

          The Orkney “interconnector” is a fraction of the length and despite its relatively low capacity a fraction of the costs of these other interconnectors.

          The Orkney connection will use UK resources and will create UK jobs, technology, taxes and security

          Far better to invest in the UK as a priority

          Also noteworthy that however these wider connections are initially funded their costs will eventually be borne by the UK consumer

 

July 2021