Supplementary written evidence submitted by FTI Consulting (GRI0126)

    1. On 7 February 2024, I served as a public witness to the Energy Security and Net Zero Committee (“ESNZ”) on the topic of “a flexible grid for the future”. My evidence was partly based on our independent assessment on behalf of Ofgem of the impact of locational wholesale electricity pricing in GB, published in October 2023.[1] In this long-standing engagement, which I led in my capacity as Head of EMEA Energy Transition at FTI Consulting, we found the following:
  1. £28 billion to £51 billion of consumer benefits in GB between 2025 and 2040 in a nodal market design, and £15 billion to £41 billion in a zonal market design.
  2. Consumers in each GB region benefitting, although the size of benefits differs across GB due to variation in wholesale electricity prices between different regions.
  3. £13 billion to £24 billion of societal benefits in GB, which includes changes to generator revenues, in a nodal market design, and £6 billion to £15 billion in a zonal market design.
  4. Improved utilisation of flexibility assets in dispatch, meaning lower spend on managing constraints and potential very significant savings in transmission investment.
  5. 65 to 100 MtCO2 of reduced emissions in GB between 2025 and 2040 in a nodal market design, equivalent to £12 billion to £18 billion of additional benefits.
  6. Significant changes to asset revenues leading to “winners and losers” among different stakeholders.
    1. As a follow-up to that session, I have been asked to provide supplementary evidence on two specific topics. These are:
  1. a further explanation of examples of other jurisdictions that have implemented a form of locational wholesale electricity pricing; and
  2. in the GB context, how existing Contracts-for-Difference (“CfD”) subsidy schemes for renewables would be affected if locational wholesale electricity pricing was introduced, and the implications for consumers.
    1. I discuss each of the two topics requested in turn.
    2. I also note that one of the other witnesses at the Committee, Mr Gowdy, has submitted an extensive report to the Committee, since the hearing by way of a follow-up. I comment briefly on this, noting that I disagree with nearly all of the points made in Mr Gowdy’s submission.

 

 

 

A. Further explanation of the experience of other markets

    1. One of the requests following my oral evidence to the Select Committee was to explain the experience of other locational pricing markets further.
    2. Locational wholesale electricity pricing is a well-established feature of electricity markets since the wave of liberalisation in the 1980s and 1990s. Unlike GB and some European countries such as France and Germany, many other markets have adopted two broad approaches to locational pricing, often expressed as “zonal pricing” or “nodal pricing”.
    3. At the outset, I highlight that locational pricing is becoming a more common feature in liberalised electricity markets worldwide. This is shown in Figure 1 below, which summarises the evolution of installed generation capacity in liberalised OECD markets, and the split of those markets between national, zonal and nodal market designs.

Figure 1: Evolution of installed capacity under different market design options across the OECD countries with liberalised electricity markets

    1. We make the following observations:

Table 1: Relevant statistics from selected electricity markets

Energy market

Market type

(transition date)

Total installed capacity, 2022

Wind, solar and batteries installed capacity, 2022

Wind and solar generation, 2022

GB[2]

National

112GW

44GW

114TWh (38%)

ERCOT, Texas[3]

Nodal since 2010

131GW

53GW

131TWh (31%)

CAISO, California[4]

Nodal since 2009

77GW

25GW

59TWh (26%)

PJM (Northeast US)[5],[6]

Nodal since 1998

198GW

17GW

53TWh (7%)

SPP (Partly Midwest and South US)[7]

Nodal since 2007

99GW

32GW

109TWh (37%)

MISO (Midwest, US)[8],[9]

Nodal since 2005

200GW

43GW

111TWh (17%)

Sweden[10]

Zonal since 2011

47GW

17GW

35TWh (21%)

New Zealand[11]

Nodal since 1996

9GW

1GW

3TWh (7%)

Note: Some jurisdictions, such as CAISO, Sweden and New Zealand, have significant renewable resources such as hydropower and geothermal not included in the two right-hand side columns.

    1. As such, I provide a brief overview for selected jurisdictions from the above, explaining their rationale for transitioning to locational pricing, recent observable trends in the market, and key implications for the GB electricity market. I cover the following markets:
  1. ERCOT, Texas
  2. CAISO, California
  3. Svenska Kraftnat (“SvK”), Sweden
  4. New Zealand

a. ERCOT, Texas

    1. The electricity market in Texas, often referred to as the Electric Reliability Council of Texas (“ERCOT”) (the system operator), is similar to the GB electricity market in some ways. We set out a few key comparisons:[12],[13]

Figure 2: ERCOT average annual real-time energy market price by zone, USD/MWh

    1. While some stakeholders argue that locational pricing reforms in GB would be detrimental to generation investments, and in turn, progress towards Net Zero, the experience in ERCOT suggests otherwise. We set out the annual installed capacity additions in ERCOT below in Figure 3, and Wind installed capacity by ERCOT zone as of end-2022 in Figure 4.[20] Figure 5 shows the location of wind turbines in Texas.[21]

Figure 3: Additional installed capacity per annum by generation technology in ERCOT, GW

Figure 4: Wind installed capacity by ERCOT zone as of end-2022, GW

Note: Figure 4 above shows wind generation capacity by ERCOT zones based on several sources. As the ERCOT grid does not cover the entire state, the Panhandle in Northwest Texas is mostly part of the Southwest Power Pool (“SPP”) grid, and so we use Potomac Economics: 2022 State of the Market Report to reflect installed capacity in the ‘North’.

Figure 5: Location of wind turbines in Texas by capacity

    1. We make the following observations.

b. CAISO, California

    1. The electricity market in California, often referred to as the California Independent System Operator (“CAISO”) (as the system operator), transitioned from a zonal market, established in 1998, to a nodal market in 2009. CAISO’s peak load is over 50GW, slightly smaller than GB’s peak load of around 60GW.
    2. While there are several insights from the history of CAISO, such as its energy crisis of 2000-2001 which was driven by poor market design leading to rampant market manipulation and ineffective treatment of congestion, the key recent lessons for GB relate to its successful roll-out of renewables – mostly solar and batteries.
    3. In the past six years (2017 to 2023), 8GW of solar, 1.5GW of wind, 6.5GW of battery and 1GW of renewable-battery hybrid were installed. This is shown in Figure 6 below.[27]

Figure 6: Additions to CAISO market participation by fuel type

    1. As shown in Figure 6 above, most of the new battery capacity investments have been made since 2021, to store energy from high solar generation when it is sunny to serve demand in other parts of the day, such as the evening.
    2. More recently, electricity markets adjacent to CAISO have joined CAISO’s real-time nodal market, known as the Western Energy Imbalance Market (“WEIM”). This is shown in Figure 7 below.[28] The initiative has been widely regarded as a success, with estimated benefits of c.$1.7 billion in 2023.[29] Further expansion of the nodal CAISO market is anticipated in the forthcoming period. [30]

Figure 7: Active participants in the WEIM

c. Svenska Kraftnät, Sweden

    1. In 2011, SvK, the Swedish transmission owner and system operator, divided the Swedish electricity market into four zones, as shown in Figure 8 below.[31] The boundaries of the zones were defined by where the main “bottlenecks” on the grid were located.

              Figure 8: Map of Swedish electricity market, and Nordic and Baltic bidding zones in 2022

    1. In some ways, the Swedish energy landscape is analogous to GB. The north of Sweden is marked by rich renewable resources (with some heavy manufacturing industries), while most of the population is located in southern Sweden. Transmission capacity to connect northern and southern Sweden is limited, which risks shortfalls in generation in southern Sweden.
    2. The reform followed a European Commission (“EC”) finding that SvK abused its dominant position by “curtailing capacity on the Swedish interconnectors when it anticipated internal congestion within the Swedish transmission system”, particularly to Denmark.[32] This arose in periods when southern Sweden had excess demand, but limited transmission capacity to convey generation from northern Sweden. In some of these periods, due to a low single uniform price across the country, interconnectors from south Sweden were scheduled to export which would exacerbate congestion within Sweden, and in particular north-south flows of electricity.[33]
    3. After the EC’s judgment, Sweden decided to implement four zones where each zone would have its own locational wholesale price. The southern zone, which often has excess demand, typically has a higher locational wholesale price, improving how the interconnectors would be scheduled (i.e. importing more often to Sweden when there is congestion between north and south Sweden).
    4. In GB, because the wholesale market does not account for transmission constraints when scheduling supply to meet demand, interconnectors to France are often scheduled to export from GB to France when, the physical reality of the system is such that they should instead be importing to meet excess demand in south GB. In our modelling for Ofgem, we found that interconnector flows were expected to be scheduled the “wrong way” up to 30% time in 2030.[34] In these hours, the GB energy system is essentially scheduled as a highway, paid by consumers, to convey imported power from Norway and renewables generation in Scotland to France – but frequently without the necessary transmission infrastructure to actually deliver these flows.[35]
    5. In Sweden, following the wholesale market reform, prices between the four zones have increasingly diverged, particularly since 2020. In 2022, the average annual zonal price in the northernmost zone in Sweden was 0.63 SEK/kWh, but 1.62 SEK/kWh in the southernmost zone.[36] Figure 9 shows weekly prices across the Swedish zones in 2022.[37]

Figure 9: Average annual wholesale prices in Sweden in 2022 and 2023 by price zone, SEK/kWh

    1. Additionally, in recent years, SvK has received significant congestion rents (c.SEK 49 billion in 2022) which arises due to price differentials across two zones (revenues collected exceed payments to generators across two zones where there is insufficient transmission capacity and a price differential). This congestion rent is typically used to reduce transmission charges, and so constitutes an additional benefit to Swedish consumers of the move to locational pricing.
    2. There is also evidence that locational wholesale prices in Sweden have affected the location decisions of new generation and energy-intensive industrial consumers. For example:


d. New Zealand

    1. The electricity market in New Zealand is considered to be the first nodal market, beginning trading in October 1996.
    2. The electricity market in New Zealand has some similarities to GB with rich renewable resources in one part of the country (the South Island) but with most of demand in another (the North Island).
    3. Hydropower makes up over half of New Zealand’s electricity generation, and is generally plentiful from Spring onwards as melting snow fills the reservoirs. This is correlated with lower demand, and can lead to excess generation in summer and excess demand in winter.
    4. Alongside this, New Zealand’s transmission grid faces some particular issues; it consists of a long “backbone” along the length of the two islands, with few alternative paths between generators and demand. There is also significant distance between generation and demand, which can lead to large electrical losses. Finally, the North and South Islands have limited interconnection. In this context, locational pricing was seen as essential to manage potentially very differing supply and demand conditions that arise simultaneously at different locations across the system and to manage efficiently flows across the New Zealand transmission network.
    5. Wind and solar penetration has increased in recent years in New Zealand; in 2010, wind and solar made up around 6% of installed capacity, and by 2022 it was around 14%.[41] Geothermal, wind and solar generation have made up the bulk of the transition away from coal generation in New Zealand.
    6. Figures 10 and 11 below show a map of each region in New Zealand and the average nodal electricity price in these regions in 2022.[42] Consistent with theory, prices on the Lower South Island, where low-marginal cost hydro generation is more plentiful, are lower; prices in the North, particularly the Upper North Island, are generally higher, as the electricity is often supplied by more expensive gas generation.

Figure 10: Map of New Zealand Regions

Figure 11: Average nodal prices in each region of New Zealand in 2022, NZD/MWh

 


B. Existing generators with CfDs in a locational market

    1. I have also been requested to provide a note about the impact of locational prices on existing wind generation investments backed by renewable support schemes, and the resulting implications for consumers.[43] As most concerns relate to projects backed by the so-called CfD regime, I focus on the impact to wind generators under these CfD contracts.[44]
    2. The CfD regime is currently GB’s primary mechanism to support new renewable investment, particularly offshore wind investments.[45] It works by providing the CfD contract holder with a fixed guaranteed electricity price (known as the “strike price”) over 15 years.[46] This means that if the prevailing market wholesale electricity price (known as the “reference price”) is lower than the strike price, wind generators receive a support payment to top up the price to the level of the strike price. Likewise, when the reference price is above the strike price, wind generators pay the difference between these two prices.[47] Consumers pay for any top-ups, and receive payments from generators when the reference price is above the strike price.
    3. CfD generators are guaranteed the strike price for their output, but do not receive it when they are not generating. However, these generators have firm transmission access under the current market design – which means they are entitled to be paid constrained-off payments when they are scheduled to run but are instructed by the ESO to be curtailed due to transmission congestion. These payments are ultimately borne by consumers.[48]
    4. In our assessment of GB transitioning to a locational market, we have assumed throughout that all existing CfD contracts and planned CfD contracts would be maintained and honoured (often termed as “grandfathering”).[49] This means that CfD generators would continue receiving the prevailing strike price over the term of the CfD contract irrespective of the locational wholesale price.
    5. As most of the existing and planned CfD wind generators are located in Scotland and northern England, locational pricing will likely, in aggregate, increase the cost of funding these CfD schemes to maintain the prevailing strike prices. This is because wholesale electricity prices in northern GB are likely to be lower due to limited transmission capacity to export excess renewable generation in certain periods, thereby increasing the support payment to maintain the prevailing CfD strike prices. As such, in a locational market, CfD investors would be no worse-off in periods of generation, and by extension, consumers would also be no better-off in these periods.[50] Overall, this reduces the benefits to consumers of transitioning to a locational pricing market despite lower wholesale electricity prices in northern GB.
    6. The impact to consumers and generators from maintaining existing and planned CfD contracts can be shown in Figure 12 below:[51],[52]

Figure 12: Cost-benefit assessment for a nodal market design relative to a national market design (2025-2040) – LtW (NOA7)

    1. As shown in Figure 12 above, maintaining existing and planned CfDs would constitute a cost to consumers. In one of our scenarios, we estimate a £12 billion cost to consumers over the modelling period, which negates some of the consumer benefits (though these remain highly positive, at £51 billion). Conversely, however, producers would benefit through the CfD prices – the £12 billion represents a transfer from consumers to generators. Overall, this reflects the assumption that all existing and planned CfDs are grandfathered in a transition to a locational pricing market.
    2. Overall, we would expect the CfD regime to provide very significant confidence to investors in revenues from low-carbon generation. However, I highlight here some of the changes generators might face in a locational pricing market:

C. Response to Mr Gowdy’s supplementary evidence to the ESNZ Select Committee

    1. Since the public session on 7 February, I note that one of the other witnesses at the Committee, Mr Gowdy, has submitted supplementary evidence to the Committee. I provide a short response in this section.
    2. Mr Gowdy’s response is some 32 pages in length. I disagree with the majority of points he raises in his note, but I will spare the committee a full breakdown and highlight seven key points Mr Gowdy makes that are either factually incorrect, unevidenced assertions, or are presented in a distortive manner in favour of maintenance of the status quo.
    3. Point 1: Role of FTI Consulting. In Section 1.3 Mr Gowdy states that “studies commissioned by the ESO and Ofgem have used the same consultants (FTI) who have essentially used the same model using the same scenario assumptions”. This is incorrect. Our work for ESO was one of four phases of work commissioned by the ESO to assist it in its consideration of market reform as GB transitions to Net Zero. FTI Consulting were selected to assist in the third phase of ESO’s work, and our outputs were shared with the industry in a series of workshops.[55] In phases 1, 2 and 4 of its work, ESO used consultants KPMG, Frontier Economics/LCP and Baringa respectively.[56] Furthermore our work for ESO was not quantitative in nature – there is no “same” model used in our work for ESO that has been published to date.[57]
    4. Point 2: Choice of scenarios used in modelling. Many of those opposed to locational pricing have sought to undermine the credibility of our modelling work for Ofgem by arguing that we should have assumed different scenarios of the transition pathway to Net Zero from those that we used in our work. Indeed, Mr Gowdy spends many pages on the topic in his submission. I have three simple points in response:

Figure 13: Overall Cost Benefit Assessment for a nodal market design relative to a national market design (2025-2040) – LtW (NOA7)

    1. As shown in Figure 13 above, the chart itself makes very clear the £12.7 billion figure (the light blue column) cited by Mr Gowdy is more than offset by the £48.8 billion reduction in payment by consumers in constraint management costs (the red column). Essentially the £12.7 billion cost arises as some of the costs that are saved in the red column (specifically constrained-on payments to southern based generators) still need to be incurred under a locational market design, but now manifest themselves in the light blue column.[68] The difference between the height of these two columns therefore represents one of the potential benefits of a shift to locational pricing.
    2. A further £27.1 billion is earned by congestion rents (the green column) which would normally accrue to consumers.[69] The key point to note is that all of the costs must be considered in their totality to conduct a comprehensive and meaningful Cost Benefit Assessment. Hence to cite one figure in isolation is highly misleading.
    3. Point 5: Mr Gowdy’s repeated references to other LMP markets – notably Texas – are entirely incorrect. I am very fortunate to lead a global team of energy market economists and work extensively both in GB-style non-locational markets as well as locational markets. For example, in recent years I have led work and filed expert reports in the LMP markets of New Zealand[70] and Texas[71], led a large team assisting the regulators on market design issues in the zonal market of Australia,[72] and supported colleagues in FTI Consulting’s work in the Mid-West of the US. As such, I am familiar with the workings of such markets as well as our own market here in GB.
    4. As I have discussed earlier in this paper, Mr Gowdy appears to have a very distorted view of LMP markets such as Texas. Statements such as “many developers […] could decide to delay their projects until they have revenue security and a guarantee that network capacity will be available. [That] is what has happened in other LMP markets, such as Texas”[73] are simply untrue and not borne out by the facts. For example, as I noted earlier in this paper, Teas has had a very significant roll out of generation in a variety of different locations since 2022. Indeed, Texas increased its wind capacity in 2023 by 4GW alone - 40% more than Britain over the same period.
    5. Point 6: Mr Gowdy presents a very distorted view of the cost to customers for constrained-off payments. A frequent assertion by Mr Gowdy is that the “largest portion of constraint costs is not the payments to generators to turn down, but is in fact the payments to generators […] to turn up to replace the constrained generation”.[74] I note that Mr Gowdy also made a similar point in his presentation to the Select Committee on 17th January when he states that “Around 70-80% of constraint costs are to Turn UP energy!”. [75]
    6. In my view, this constitutes a very serious and significant misrepresentation of the costs to GB consumers of constraint costs and also of the amount of money paid to constrained-off generators (which are typically wind generators in the north of the country).
    7. Mr Gowdy is indeed correct to note that a large portion of constraint costs incurred by the ESO are to turn up generators – typically gas fired plant in the south of the country. The smaller portion is those costs paid to renewables generators as compensation for being curtailed. These transactions are undertaken by the ESO in the balancing mechanism – with the costs being recovered from consumers.[76]
    8. However, in all of his citations, Mr Gowdy at no point refers to the fact that in nearly all cases, renewables generators that are constrained-off have also been paid in the wholesale market. Hence, constrained-off generators are the recipient of two payment flows from consumers – one payment in the balancing mechanism (paid by ESO and recovered from consumers) and one payment in the wholesale market (paid by retailers and ultimately recovered from consumers). But Mr Gowdy only refers to one payment flow to constrained-off generators. Figure 14 below provides a simple schematic diagram of the payment flows associated with constraining on and off wind generators under the current market design.

 

 

 

Figure 14: Payment flows associated with constraint costs under current market design

    1. The key point to note is that, under typical market conditions, the largest proportion of money paid by consumers to constrained-off wind generators is not through the payments by the ESO but rather through the wholesale market.[77]
    2. Because of the way the current market works – with the split between the non-locational wholesale market and the locational balancing mechanism, combined with the opaque nature of the contracts market - it is very difficult to assess the revenue constrained-off generators earn for not actually generating. However, through our modelling for Ofgem, we have estimated payments to wind generators sited in Scotland that they would earn over the period 2025 to 2040.
    3. Our, very conservative, estimate is that Scottish wind generators would receive payments from consumers of £11 billion in the period 2025 to 2040 for not actually generating.[78] This comes in two forms – payments in the balancing mechanism of £1 billion (the payments referred to by Mr Gowdy) and payments in the wholesale market of £10 billion (the payments ignored by Mr Gowdy).
    4. Given the large quantum of customer money that would, under the current regime, be paid to wind generators in Scotland for, quite literally, nothing, a full understanding of the financial implications of the current regime therefore needs to take account of both types of payment. I would discount entirely the view put forward by Mr Gowdy that the vast majority of costs to customers to resolve constraint costs are incurred by plant to “turn up” which, in my view, is a very serious mischaracterisation of the true impact on consumers of the current market design.
    5. Point 7: Mr Gowdy’s list of “[o]pportunities to reduce the occurrence and cost of constraints”[79] represents a compendium of “Heath Robinson” style sticking plasters on the GB electricity market. In his submission to the Select Committee, Mr Gowdy provides “good news” in the form of a long list of reforms that might be adopted in lieu of locational pricing. I will resist the temptation to explain why each one of them will either be hugely costly to consumers – simply noting that they would retain the current approach of wealth transfers from GB consumers to constrained-off generators – ineffective, or both.
    6. Instead, I will simply requote my statement at the Hearing that “[f]irstly some of those proposals are entirely untested relative to locational pricing, which has been in operation in many parts of the world for over 20 years. Secondly, under that regime, the constraint payments that generators in the north of the country continue to receive, which is money literally for nothing, would continue.”[80]

April 2024


[1]                             FTI Consulting and Energy Systems Catapult: Assessment of locational wholesale electricity market design options in GB (link).

[2]                             National Grid ESO: FES 2023 Data Workbook (link): tab ‘ES1’.

[3]                             Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link): Figure A10 (capacity); Figure 15 (generation).

[4]                             CAISO: 2022 Annual Report on Market Issues & Performance (link): Figure 1.31 (capacity); Figure 1.10 (generation).

[5]                             Monitoring Analytics: 2022 State of the Market Report for PJM (link): Table 12-1 (capacity).

[6]                             Monitoring Analytics: MARKET MONITOR FINDS PJM WHOLESALE ELECTRICITY MARKETS COMPETITIVE (link): 88,884MWh x 8,760hrs x 6.8% = 53TWh (generation).

[7]                             SPP: State of the Market 2022 (link): Figure 2-13 (capacity); Figure 2-26 (generation, wind only, based on 39% real-time capacity factor).

[8]                             Potomac Economics: 2022 State of the Market Report for the MISO Electricity Markets (link): Figure 11.

[9]              MISO: Historical generation fuel mix, 2022 (link): See historical_gen_fuel_mix_2022.

[10]              Svenska Kraftnät: Kraftbalansen på den svenska elmarknaden, rapport 2023 (link): Table 2.

[11]              MBIE: Data tables for electricity (link): See Data tables for electricity: tab ‘7 – Plant type (MW)’ (capacity); tab ’2 – Annual GWh’ (generation).

[12] National Grid ESO: FES 2023 Data Workbook (link).

[13] Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link).

[14] Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link): Page 76 to 90.

[15] We note that ERCOT is, however, considering introducing a type of capacity mechanism. See UtilityDive, Texas slows development of annual $1B performance credit mechanism designed to boost grid, dated 8 March 2024 (link).

[16] ERCOT: Fact sheet, February 2024 (link).

[17] ERCOT: Annual Report on ERCOT Demand Response (link).

[18] Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link): Page 36.

[19] Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link): Page 44.

[20] ERCOT: December 2023 Capacity Demand and Reserves Report (link); and Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link).

[21] US Wind Turbine Database (link).

[22] Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link): Executive Summary, Page ii.

[23] Potomac Economics: 2022 State of the Market Report for the ERCOT Electricity Markets (link).

[24] National Grid ESO: FES 2023 Data Workbook (link).

[25] National Grid ESO: FES 2019 Data Workbook (link).

[26] For challenges faces the ERCOT, see the following article for examples. Bloomberg, Why the Texas Power Grid Is Still Facing Challenges, dated 16 January 2024 (link).

[27] CAISO: 2022 Annual Report on Market Issues & Performance (link): Figure 1.32.

[28]               WEIM: About (link).

[29]               WEIM: Benefits (link).

[30] WEIM: Extended Day-Ahead Market Forum set in Las Vegas (link).

[31] Sveriges Riksbank: The Swedish electricity market – today and in the future (link).

[32] Commission Decision in Case 39351 – Swedish Interconnectors (link).

[33] Commission Decision in Case 39351 – Swedish Interconnectors (link).

[34] Jason Mann, Joe Perkins and Dan Roberts: Transmission investment, flexibility and locational pricing (link).

[35] The same issues exist for batteries and emerging forms of smart technology such as smart EV charging and smart heat pumps.

[36] Holmberg and Tangerås (2023): The Swedish electricity market – today and in the future (link).

[37] Nord Pool: Day-ahead prices (link).

[38] Lundin: Geographic price granularity and investments in wind power: Evidence from a Swedish electricity market splitting reform, 2022 (link).

[39] H2 Green Steel website (link).

[40] ESNZ committee: Oral evidence: A flexible grid for the future, 2024 (link): See Q322 to Q327.

[41] MBIE: Data tables for electricity (link).

[42] EMI: Wholesale price map (link).

[43] I do not consider in this note how the CfD regime could be adapted for future generators in a locational price regime. This is covered briefly in 2.114 of our report.

[44] Currently, the Renewables Obligation (“RO”) scheme is still the largest form of renewable support in Great Britain (link). The RO scheme works by requiring suppliers to procure a certain number of RO certificates, whilst eligible renewable generators are issued certificates for the volume of electricity generated. This provides an additional revenue stream to generators with RO certificates, acting as a “top up” to wholesale revenues. A transition to locational pricing, which might affect wholesale revenues, would not affect this additional revenue stream through the RO scheme. The RO scheme for new investment applications had ended in 2017, and will end for existing assets by 2037.

[45] CfD contracts are also used to support other generation technologies by fixing electricity prices received, including for nuclear, biomass, and more recently new hydrogen production.

[46] CfD contracts are awarded through a competitive auction, with a maximum strike price set by the government. In the upcoming AR6 auctions, the maximum strike price for offshore wind was £73/MWh (2012 prices). Strike prices are indexed for inflation. Allocation Round 6: Allocation Framework, 2024 (link).

[47] In 2022, this was quite common, as the Ukraine crisis led to sustained high electricity wholesale prices above the strike price of generators. Low Carbon Contracts Company: Actual CfD Generation and avoided GHG emissions (link).

[48] Payments to CfD wind generators to be curtailed can be sizeable. There are two components, the direct constrained-off payments made by the ESO, and the portion of wholesale revenues received when they are scheduled to run (which is set irrespective of network congestion), but do not do so when curtailed.

[49] We have also assumed that the grandfathering principle would apply to other prevailing contracts between investors and Government, including the Cap & Floor regime for interconnectors, ROs for wind and solar, CfD contracts for other technology types (such as solar and Hinkley Point C).

[50] While this applies to the CfD scheme in aggregate, the precise impact differs by technology and location. For example, in our assessment, Hinkley Point C located in the south of the country would receive £1 billion less in CfD support payments over the forecast period under a nodal market as a result of an increase of c.£ 1billion in wholesale revenues. Overall, the plant’s revenues do not change over the forecast period, as it continues to receive revenue in line with the agreed strike prices.

[51] FTI Consulting and Energy Systems Catapult: Assessment of locational wholesale electricity market design options in GB (link).

[52] The grey bars shown in Figure 12 reflect the following impacts. “Impacts on consumers (other)”: Reductions in the cost of congestion management, Wholesale costs faced by GB consumers, Intra-GB congestion rents between nodes, and one-off implementation costs; and “Impacts on producer (other)”: Lost wholesale and balancing market revenues earned by generators.

[53] We assume that all future offshore wind projects, and 50% of onshore wind and solar projects, receive a CfD contract. Therefore, Mr Gowdy’s statement that “FTI has assumed that only 50% of future renewable capacity will be under a CfD” is incorrect (Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Footnote 17).

[54] While these policies are equal and opposite transfers in the short-term, they could lead to inefficient outcomes or unintended consequences in the longer-term. For example, inefficient generators that in practice increase system costs by continuing to operate might be incentivised not to close.

[55]               We conducted five industry-wide workshops attended by a total of over 500 industry stakeholders, as discussed in our report. FTI Consulting and Energy Systems Catapult: Assessment of locational wholesale electricity market design options in GB (link): Paragraph 1.18.

[56] KPMG: ESO Networks Stakeholder Group, 2020 (link); Frontier Economics/LCP: Net Zero Market Reform, 2021 (link); Baringa: Final Report - options and packages assessment for market design and policy reform, 2023 (link).

[57] In the interests of full transparency, we should note that we are currently working on two assignments for the ESO which are quantitative in nature and do indeed use the some of the features of the modelling exercise that we undertook for Ofgem. However, these are not publicly available (as yet) and nor have we made external stakeholders aware of our work. Hence, Mr Gowdy cannot be referring to these studies in his submission to the Select Committee as he cannot have been aware of them.

[58] For example, the ESO have recently announced their “Beyond 2030” plan, which outlines an ambitious £58 billion investment plan in GB’s electricity grid to meet growing demand and facilitate decarbonisation. See ESO, Beyond 2030, 2024 (link).

[59]               Subsequent to our work for Ofgem, we have undertaken a similar exercise with refreshed scenarios.

[60]               See Ofgem, Initial Project Assessment of the Third Cap and Floor Window for Electricity Interconnectors, 2024 (link): Paragraph 3.37.

[61] Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Page 9.

[62]               The HND scenario is a “high transmission scenario” that is adopted on top of a high wind scenario (known as “Leading the Way”), which assumes a very large roll-out of wind generation – much of which is sited in the north of the country. The HND scenario of high transmission is not, from the ESO’s perspective consistent with the System Transformation scenario (which envisages a greater reliance on nuclear generation located in the south of the country). See (link) .

[63] Mr Gowdy states: “FTI modelling is based on the current national market having a single marginal clearing price. This is not a true representation of the current market and may have inflated the occurrence of infra-marginal profits as it ignores the value transfer potential of long-term PPA contracts”. Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Page 10.

[64] Energy Security and Net Zero Committee: Oral evidence: A flexible grid for the future (link).

[65] The actual real time price is known as the imbalance price.

[66] Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Page 11.

[67] FTI Consulting and Energy Systems Catapult: Assessment of locational wholesale electricity market design options in GB (link): Figure ES-7.

[68]               This cost is the often the cost of gas plants operating in the south of the country and is needed to resolve transmission constraints. In the current national market design, this cost manifests itself in the congestion costs (the red column). A move to locational pricing does not absolve the need for these plants to operate at certain times (as the capability of the transmission system is unchanged). However, the costs of operating these plants are now recovered through the wholesale market (the blue column).

[69] This is funds recovered in the settlement process and arises because of locational differences in the prices at which the electricity market is settled. An oft cited view by some stakeholders is that these revenues (as represented in the green column) should be used (either in whole or in part) to compensate those market participants that lose out in a move to locational pricing (which would be mainly northern based wind generators).

[70] High Court of New Zealand: Judgement of Palmer J, 2022 (link).

[71]               Public Utility Commission of Texas: Review of Wholesale Electric Market Design, 2022 (link).

[72]               FTI Consulting: Resource Adequacy Mechanisms in the National Electricity Market – A Report for the Energy Security Board (ESB), 2020 (link).

[73] Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Page 18.

[74] Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Page 27.

[75]               Johnny Gowdy & Ellie Brundrett: Select Committee Briefing Managing Network Constraints (link): Page 11.

[76]               The mechanism for recovering this charge is the so called Balancing and Use of System charge (BSUoS) and is smeared per MWh levy charged on all customers.

[77] Constrained-off payments to wind generators by the ESO are one of the more idiosyncratic features of the current market design. The market design is such that generators sell power in the wholesale market and, if required to be constrained-off, the generator buys back the power in the balancing mechanism that it has sold earlier in the wholesale market, so that the aggregate commitment of that generator to generate is now zero. This has the effect of reducing generation in parts of the network where there is a surplus of electricity. The original design of the GB market envisaged that thermal generators would be willing to pay the ESO to buy back the power in the balancing mechanism so that the payment flows would constitute a payment by generators to the ESO. The assumption was that a thermal generator would be indifferent between paying to buy back the electricity it had sold in the wholesale market (and not generate) or the fuel cost that it would incur to meet its commitment. In this way the generator still managed to retain the profit between the price it earned for selling its power in the wholesale market and the costs incurred in meeting its commitment regardless of whether it actually generated. A windfarm operating under a CfD scheme would sell its power in the wholesale market (as per the thermal generator). However, if required to be constrained-off, a wind generator would offer to buy back – but only, typically, at a negative price. It would do this as, if it does not generate, it would not be able to receive the top up payment under terms of the CfD scheme. Hence, to be willing not to generate the wind generator requires additional compensation to reflect the fact that it would not earn the top up payment of the CfD. The exception to this is if the wholesale price clears above the strike price of the CfD – in these cases the wind generator would be willing to pay the ESO not to generate (as it would need to pay back the surplus market revenues to the government under the CfD rules).

[78]               This estimate is conservative, because at the time we forecast these payments, the cost of new renewables wind generation was expected to be much lower than the results of the recent auction round for offshore wind suggest is likely in the future.

[79] Regen: Supplementary Evidence for 7th Feb ESNZ Hearing (link): Figure 3.

[80] Energy Security and Net Zero Committee: Oral evidence: A flexible grid for the future (link): Q339.