Transport Committee

Oral evidence: Delivering East West Rail, HC 755

Tuesday 3 November 2026

Ordered by the House of Commons to be published on 3 November 2026.

Watch the meeting

Members present: Ruth Cadbury (Chair); Steff Aquarone; Dr Scott Arthur; Samantha Dixon; Daniel Francis; Olly Glover; Alex Mayer; Joe Morris.

Questions 45–115

Witnesses

 

II: David Hughes, Chief Executive Officer, East West Railway Co.; Ben Rule, Railway Operations Director, East West Railway Co.; Christian Irwin OBE, Capital Delivery Director, North West & Central, Network Rail; Rosemary Hopkins, Interim Director of East West Rail Sponsorship and Senior Responsible Owner (SRO) for East West Rail Key Outputs 2 to 5, Department for Transport; Jodie Lofthouse, Programme Director for East West Rail and SRO for East West Rail Key Output 1, Department for Transport.

 


Examination of witnesses

Witnesses: David Hughes, Ben Rule, Christian Irwin, Rosemary Hopkins and Jodie Lofthouse.

  1.             Chair: Welcome to our second panel, which is covering the wider issues of accountability, delivery and governance of East West Rail. Could I ask you each to introduce yourselves, starting off with Ben?

Ben Rule: Hello. I am the railway operations director in East West Rail Company.

David Hughes: I am the chief executive, East West Rail.

Jodie Lofthouse: I am programme director for East West Rail in DFT and SRO for the first phase of delivery.

Rosemary Hopkins: I am interim director of East West Rail at DFT and senior responsible owner for phases 2 to 5 of the scheme.

Christian Irwin: Good morning. I am the capital delivery director for Network Rail.

  1.             Chair: Welcome. In the previous panel, we heard about the ongoing dispute that has resulted in no passenger services running on the first stage of East West Rail since the line opened 744 days ago. What impact has the dispute had on the delivery timetable, costs and the planning assumptions for subsequent phases of the East West Rail project? You probably do not all need to answer all the questions, given you are from similar organisations. Who wants to kick off on that?

David Hughes: The material impact of the delay in passenger services on the first phase is probably limited in terms of planning of future phases. I do not underestimate the reputational damage the delay has had for East West Rail as a programme, but in terms of material consequences on cost and schedule for future phases, there are not any. The key thing for us is learning lessons from all the discussions you had in the first panel to ask, how do we do things differently to ensure that we are not in this situation again when we get to opening up future phases of the railway?

  1.             Chair: Is it impacting on expected revenues?

David Hughes: Clearly, now it is. The loss of the revenue today is a matter for Chiltern and the Department. In terms of the overall delivery costs of the programme, it does not have an impact. The big impact for us as East West Rail Ltd, being responsible for delivering the programme, is the reputational damage it has, which is significant. It is also very important not to lose sight of the real-life impact this has on communities along the line of route. We have recruited a lot of people in recent years. Many in my team have moved into the area, bought houses in places such as Winslow, expecting to be able to travel to work by train, and they cannot.

  1.             Chair: I realise Chiltern Railways is not here, but do you have a figure for the revenue loss?

David Hughes: No. Jodie might be able to get that for you.

Jodie Lofthouse: I can potentially send to you something in writing around the revenue loss. We have been very cost conscious in the development and delivery of the railway. When the Secretary of State came to the Committee back in June of this year, she talked about bearing down on the costs and recognising that it was not driving revenue at the moment. Being cost conscious, we have delivered the infrastructure for this part of the railway both on time and under budget. The overarching funding envelope for that first phase is £1.2 billion; I continue to drive delivery within that funding estimate. It is not a case of creating significant additional costs for the taxpayer; in fact, we look to continually minimise those and bring this part of the railway in under budget wherever possible.

  1.             Chair: For those who did not answer the first question, has this dispute had impact on the delivery timetable, infrastructure costs or planning assumptions for subsequent phases of the project?

Jodie Lofthouse: Going back to the lessons learned, I would say it has had a positive impact on planning and how we set the project up for success. The whole point about learning from this first phase is that you can enhance the delivery of the future phases. That is one of the reasons for splitting up major projects, so you can roll over that learning and make sure you address it in the future phases. I would expect all the things that we have experienced on this first phase to be addressed in how we set up the company and the programme for those future phases.

  1.             Chair: Christian, has it had an impact on Network Rail?

Christian Irwin: As Jodie made reference to, we delivered the infrastructure on time and ahead of budget, which we are really proud of. Obviously, we are equally disappointed that we do not have passenger services on the railway. We have a well-established maintenance and operations team that look after the railway, keeping it in good condition. On the line, we have regular freight services and charter services and, as we speak, a very intense driver training programme, which almost simulates an hourly service. We are comfortable that we are ready to go; the infrastructure is there and is being utilised for the start of service.

  1.             Dr Arthur: Hopefully, the Secretary of State is bearing down on the dispute as much as she is bearing down on costs. It is quite disheartening—I do not know how you feel sitting there—but the people on the other side of you are saying, “Well, we’ve done our bit of the job; it is not our fault;” whereas, the taxpayer wants all five of you here to work together to resolve this. David comes along—I am not being critical—and says, “Well, the lost revenue is lost revenue; that is not my problem, it is someone else’s,” but taxpayers want this to be a team effort.

As regards lost revenue and the costs of the dispute—I know you cannot put a number on it just now—in terms of the scale, how does it compare to the cost of settling the dispute and giving the trade unions exactly what they want? They said it would cost £150,000 a year. Surely the lost revenue must far exceed that. David has also talked about the impact on communities. It affects wellbeing but also has an economic impact. What is the quantum of the dispute, the impact in terms of communities and the loss in terms of revenue? How do those numbers compare? I think we can guess how the comparison is going.

Jodie Lofthouse: It is a system we are talking about here. There is a wider network, and it is about delivering this part of it. Consideration of cost is something that Ministers regularly do.

  1.             Dr Arthur: He gets advice from you, Jodie, I am sure. You must have these numbers.

Jodie Lofthouse: I do not have the numbers in front of me. This is not just about a cost over here; this is about the operating model that we have based the infrastructure and the plans on. When you make changes, it has consequences that would require further consideration and judgment by our Ministers. It is not as simple as, “Just make this happen and it will work tomorrow.” As a system, it is more complex than that. I will see what I can provide you in terms of following information in writing, if that gives you a bit more help in understanding that.

  1.             Dr Arthur: That is interesting. Thank you. The project has moved from a connection model to being delivered in phases. What does this mean? What is the difference there? As somebody who might want to use the network, what difference will that make to me?

David Hughes: It is partly a change in terminology, but it is more than that. It is probably one that is best for Ben to answer.

Ben Rule: As David said, to some extent it is just terminology. In moving from the connection stages to key outputs, we have done two things: first, we had to react to the fact that the Universal attraction that is to be built at Stewartby was proposed. We needed a plan that dealt with the arrival of that theme park. We had to adjust what we were doing to provide services in line as far as possible with the arrival of the theme park. That was the first thing.

  1.             Dr Arthur: What drove you to do that then? Were you told you had to do that, or did you just think this would be a good thing to do? Did you see it as an opportunity to raise revenue?

David Hughes: It was all of the above.

Ben Rule:. It is a big investment in the country. The East West rail route runs right alongside it. It is absolutely right to provide a transport link to that as well as to the Midland Main Line. We had to react to that; the key output approach serves to do that. The key outputs have also allowed us to make sure that we deliver benefits to customers as early as possible.

  1.             Dr Arthur: Why would you not have done that anyway right from the start?

Ben Rule: That is a good question. We are making sure that the schedule we are now working to delivers as many benefits as early as possible. Our key output stages deliver four trains an hour to Stewartby station earlier than you would have had under the connection stage approach. It is about bringing forward as many benefits as we can.

David Hughes: The intent of the original approach was to open this in three phases. It is not revolutionary what we have done; we have just broken it down into slightly more phases. In part, that is learning lessons from previous projects that told us that, the more that you can break down the delivery and introduce services gradually, the more that derisks the project. It is good practice to break it down into bite-sized chunks. There was also a very clear steer from Government in early 2025, when it was clear that Universal was going to go ahead. They asked us, “How can you adapt that opening schedule to get as much service into the park as quickly as possible? Alongside that, what else can you do as part of the overall economic growth agenda? How can you bring forward benefits in Cambridge, in Bedford? How can you sequence delivery of the railway to ensure that we get as much of the benefit as soon as possible?”

All those elements came together to drive what is not a massive change. It was always intended to open in phases; we just broke it down into slightly more phases with the intent of bringing forward benefits, in particular, as Ben says, trying to get as much of a service to the park as soon as we can. The park is huge. It will be the UK’s biggest tourist attraction, and it is literally 100 metres from one of our stations. We were going to have to adapt the design of the railway to cater for that.

  1.             Dr Arthur: I do not want to reopen the debate, but it is interesting that there is a focus on delivering economic benefit as early as possible. It would be interesting to see the benefit of changing your plans compared to the impact of the dispute. Let us not reopen that.

David Hughes: If I may, Dr Arthur, just close out, we have talked already about learning lessons. No one is happy with the position we are in on phase 1. The key thing for Rosemary, Jodie, myself and Ben is how we make sure, when we get to these future phases, that we are not in the same position. The first key lesson that we have taken away is about clarity of accountability. You heard witnesses in the previous session refer to the fact that accountability was not as clear as it should be.

In the first phase of the railway, Oxford to Bletchley, where we do not have services running, accountabilities were split—there is a lot of history around that—between what the Department was responsible for and what East West Rail was responsible for. For the first phase, East West Rail had a responsibility for the infrastructure but not for the introduction of services. Going forward, it is clear now that East West Rail Ltd holds accountability for the whole system. For future phases, Ben and I do not have direct control of everything, but we are the conductor of the orchestra. Our job is to make sure that, when we get to these future phases, we have not just delivered the infrastructure, important though that is, but all those other elements are in place that are necessary to bring passenger services into operation. That is the first lesson: clarity of accountability.

The second—again there was reference to this in the previous session—is getting ahead of the issues early. When I came in as chief executive just over two years ago, one of the first things I did was to bring in Ben, someone with a huge amount of rail operations experience, in order to tackle the sorts of issues that delayed us on the first phase now, several years in advance. You heard the union reps saying, “We didn’t get into consultation on these issues until relatively late in the day.” One of the big lessons from large rail projects is there is a risk of focusing on the infrastructure in the early days. You need to focus on the whole system from the get-go, and that is what we are trying to do to ensure that there is no repeat of where we are now when it comes to opening up future phases of the railway.

  1.             Dr Arthur: That is good. In this place, I have to keep reminding myself that the world does not end at Oxford and Cambridge. Is there scope for the line to go beyond these places at some point? Is that a possibility? Is there a business case there?

David Hughes: I cannot answer the question on business case. Ben might want to comment. There is nothing to preclude running services beyond Oxford and Cambridge. This will be part of the integrated rail network. By the time it is delivered, GBR will be fully up and running and will be that single controlling mind. It is not a self-contained railway that can only run from Oxford to Cambridge. You could run from Penzance to Ipswich if you chose, but that is an operational choice to be made by GBR as it plans the overall network. There is nothing we are doing that precludes running services beyond.

Ben Rule: It is part of the network and connected in many places to its wider parts. For example, freight will use East West Rail to connect ports and depots across the network. That is already happening. We are speaking with the operators at either end of the line as well. We have good conversations with Greater Anglia and GWR about the opportunities to run longer distance services. It is entirely possible with the network.

Dr Arthur: Can I squeeze in a question about freight?

Chair: Yes, please do. You are very welcome.

  1.             Dr Arthur: In your consultation in 2026, you said there will be up to one freight train per hour between Oxford and Bletchley. What does that mean, up to one train? Is that a guarantee that one train could run, or does it mean that possibly one train could run?

Chair: How does that fit into the 70% freight increase target?

Ben Rule: The network is designed with sufficient capacity to run the passenger trains that we are instructed to provide for, and there is additional capacity built in to allow for freight traffic as well.

Dr Arthur: If my wife says to me we are going to have up to one holiday this year, I would read that as that might mean no holidays.

Ben Rule: There is capacity on the network to run an hourly freight service.

  1.             Dr Arthur: So, that is there?

Ben Rule: That is there.

  1.             Chair: But no more?

Ben Rule: It does not always mean that you will have a freight train in every hour because it depends partly on demand.

  1.             Dr Arthur: That average of one per hour is over a day; those trains could be overnight.

Ben Rule: We will provide the capacity. Freight companies can then choose whether they would like to use it, depending on the demand they are trying to meet, the contracts they have and so on. But the capacity is there. It is also worth saying that, while we provide capacity for one freight train an hour along the line of route, other investments would be required elsewhere on the network to make it something that freight companies would definitely want to take up.

Chair: Ely-Haughley.

Ben Rule: That is a good example.

  1.             Dr Arthur: It is one per hour between Oxford and Bletchley, one every two hours between Bletchley and Bedford, and around two freight trains each direction east of Bedford. Is there a strategy here for freight?

Ben Rule: There absolutely is.

  1.             Dr Arthur: Do these numbers make sense?

David Hughes: They absolutely do. Ben will explain why.

Ben Rule: There is a strategy. The wording as you have described is, “The railway that we will upgrade and build has capacity for an hourly service along the line of route.” Whether that is taken up or not depends on other investments. The wording you have read out there reflects the expected demand without that further investment. We are providing capacity for a freight train every hour along the line of route.

David Hughes: To build on that, the strategy is driven partly by constraints on existing network, but largely by what the demand flows are. We can provide capacity for a train an hour on that section between Oxford and Bletchley, and have done that already, but it also reflects the demand flow. If you think about the geography of the country, it means going from Southampton through up to Oxford, using that line from Oxford to Bletchley to join the west coast main line, and then head north to the west midlands and to Trafford. That is the flow. The logical freight flow from the other side of the country would be from the east coast ports, Felixstowe in particular, coming through Cambridge, joining our infrastructure, and then turning right on to the west coast main line at Milton Keynes.

There are two problems there and these are the constraints that Ben talks about: there are bottlenecks before you get to Cambridge that the industry would have to invest significant amounts of money into; and there is no right turn from our infrastructure on to the west coast main line to head north at Bletchley. That would also be a very significant piece of infrastructure. If you look at the numbers cold, it does not make a lot of sense, but it reflects both the demand flows and the underlying capacity in the network.

  1.             Dr Arthur: Basically, you do not want there to be a constraint in the future.

David Hughes: No. If those constraints were unlocked in the future, it would be relatively easy to make sure that the East West Rail infrastructure could accommodate that increase in freight.

  1.             Chair: While we have a freight target increase, the Secretary of State confirmed to me in orals last week that there will not be a specific freight strategy; it will be incorporated into the rail investment strategy. Do we have any timescale for that?

Rosemary Hopkins: In terms of the freight strategy, I am not sure. It is probably one we need to take away, check out and come back to you on. No, as you say, there will not be a freight strategy.

Chair: There will not be a standalone freight strategy, as she confirmed to me last week.

Rosemary Hopkins: It will be rolled into the wider strategy for rail investment. This is work we are undertaking alongside preparing for the stand-up of GBR, in readiness for which we need to have that vision and prioritisation in place.

  1.             Chair: Am I right in saying that is about investment in hardware, whereas the last set of questions focused on things such as train paths in among passengers, logistics infrastructure beside the line and that sort of thing? Is a freight strategy somewhat different to a rail investment strategy? Maybe I am missing something.

Rosemary Hopkins: As a whole, one of the great advantages of standing up GBR is being able to think about the system, the policy intent, and our ambition for delivering outcomes for passengers and freight, and the infrastructure, services, operations, depots and rolling stock we need to support those outcomes. We are building bits of the jigsaw together, and I feel really confident that we will get there. The team here today in particular is leading on a piece of the infrastructure within that wider system.

Chair: As you say, it is much easier in the context of GBR, so thank you.

  1.             Olly Glover: East West Rail has been a bit of a journey in terms of the delivery timescales it has been working to. In 2019, the aspiration was to do Oxford to Milton Keynes by 2024, which we have discussed in some detail, and a limited service using the existing infrastructure Oxford to Bedford in 2025, and the whole thing to Cambridge in 2028. Now, East West Rail is saying mid to late 2030s for the Cambridge bit. I must admit I am not quite clear what the current Bedford-Bletchley thing is; maybe you can tell me. How confident are you that the current key timescales that you are working to are deliverable on schedule and will not slip further?

David Hughes: I question whether those original timescales were ever plausible. At the moment, if everything goes to plan, the earliest we would get our development consent order is late 2028, early 2029. For the bulk of the work that we have to deliver, we cannot get started until late 2029. Whatever the history before—that takes you into a whole debate about how long it takes to get planning consent for big infrastructure, which would need a different committee to look at that—the reality is, the earliest we are going to start our main works and really get going on the bulk of the project will be sometime in 2029-30. At this stage, we are still at a relatively high level of design as we head into the DCO.

Over the course of the next 12 months, we have to inform Government’s decisions about the project in terms of whether they want to commit to funding it. Over the next year, my team need to develop a very clear understanding of the likely cost envelope and delivery schedule. Our best estimate is that we will complete the project in mid to late 2030s. That is where we are at the moment. As with cost envelope and schedule, I do not want to overstate. It would be wrong of me to say I am absolutely confident because we are just too early in the process for that. That is our best understanding of where we are. Those are the timescales we are trying to meet.

As we work through the detail of what the cost and schedule will look like and present that to Government when we get to OBC next year, my job is to give the most accurate view of what we think that will be. That is clearly one of the key lessons from HS2 and other projects. At this stage, do not succumb to optimism bias; do not try to meet artificial deadlines or cost envelopes. We will spend the time between now and DCO submission, which we plan to do this time next year, bottoming out what we think the cost envelope and schedule ranges are for this project. At the moment, our best estimate is it is mid to late 2030s.

  1.             Olly Glover: I understand your point about looking to the future and not dwelling in the past. Those timescales I mentioned are something that East West Rail did a very extensive non-statutory consultation about in 2019 and 2020. That is partly why I, and lots of other people, ask what is going to be different this time. You have given your view on that.

Also, what stage has each section of the project reached? You mentioned DCO submission this time next year. Is business case approval ready to move to that phase in terms of FBC or OBC?

David Hughes: We present our OBC to the Department—I will use a season—in the summer; we are thinking around June/July.

Olly Glover: Go for a month rather than a season. That is a point to you.

David Hughes: We will go for a month. Around June or July of next year we will present to Government our outline business case and our draft DCO submission. That is a key decision point for the Government. We use the jargon—it is review point 2. We went through a review point 12 months ago. Review point 2 will be in June or July next year. Two big decisions for Government are the OBC that we present, and we will be in front of Government saying, “We think we’re good to go with our DCO submission.” The plan is to submit that around this time next year.

  1.             Olly Glover: Forgive my ignorance; at what point does FBC happen?

David Hughes: That would happen after the DCO award, and so we plan for that to be late 2028.

  1.             Olly Glover: I have a final question for you, Mr Hughes. Over the summer, I read a book, “The Delivery Gap” by Jonathan Simcock. In relation to your time as chair of the Crossrail sponsor board, you said to him, “I put my hand up to the failure of the assurance. I need to say that up front I am on the list of the guilty.” You have said a little about what you think can be learned from previous projects. What else do you take from that time, and maybe HS2, as to how East West Rail will be different and how we can learn positively from those projects?

David Hughes: I could talk for hours on that. In terms of where we are now with the project, the key lesson that my team hear me banging on about all the time is making the right judgment about cost envelope and schedule. I talk about it a lot with Mark Wild, chief executive of HS2; he and I worked on Crossrail together. We want to set an ambitious cost envelope and an ambitious schedule. We want to drive the project hard so we get the most efficient delivery and can realise benefit as quickly as possible; but at the same time, we have to guard against the over-optimism that so many projects have fallen prey to. I do not want to be guilty of coming to Government next year with too rosy a picture on cost and schedule in order to secure the funding. What we need to do—and this is a lesson from HS2—is flush out now our best possible view of that cost and schedule to inform the Government’s decision about whether they want to commit to this scheme. Flush that out now, not after the event, not after you have let your main works contracts. Give your best possible judgment of that cost and schedule range.

  1.             Alex Mayer: We had consultations in 2019, 2021, 2024 and 2026. Is that it?

David Hughes: We are not planning on any further route-wide consultations. That is it; but that does not mean it is the end of engagement with communities and stakeholders along the line of route.

  1.             Alex Mayer: For anyone who wants to answer—Christian was nodding away—will the next time that the public participate be in examining that application for the DCO?

David Hughes: In a route-wide sense, yes. We are in Buckinghamshire this morning; we were in Bedfordshire last night; we are in Lidlington tomorrow. It is quite an important point for us. The Chancellor made the point that there had been four consultations. The Planning and Infrastructure Act changed that process. If it had been on the statute book several years ago, our whole approach would have been different. By the time it came on to the statute book last December—it makes significant changes to the pre-application process for the DCO—we had already done three route-wide consultations and we were just gearing up to go out with our fourth. The new Act will change how this is done in the future.

I would make two points. First, the consultations have been hugely valuable in refining our design. The feedback we get from the public has resulted in some quite significant changes to our design. Secondly, there is a danger that people think the Planning and Infrastructure Act changes mean we are not going to consult any more. When I answer your question saying we do not have any more planned consultations, that does not mean we are not talking to the public. The new legislation enables us to have much better and much more iterative engagement, such as we are having this week, with communities on the issues that matter to them.

The thing about the route-wide consultations is they are big, set-piece events. Before you even get out of the door, doing a three-month route-wide consultation puts six to nine months into your programme. The big win going forward is the Act enables you to engage in a much more iterative way with communities on the things that matter to them. For example, in terms of Bicester, the main thing they want to talk about is what we are doing with their level crossing. It is not the only thing they want to talk about, but they are not really interested in what we are doing in Cambridge East. Moving away from these route-wide consultations opens up the opportunity for us to engage in a much better way and at the same time speed up the process.

  1.             Alex Mayer: There are still decisions to be made. You mentioned Cambridge East. Is there any possibility that you will feel the need to consult there again ahead of next year?

David Hughes: We do not have plans to do so at the moment. I think I am right in saying it is not unusual in a DCO process to have targeted consultations if changes emerge. We have another year to go before we submit the DCO application. We do not anticipate significant changes to the scope of the scheme at this stage; we certainly do not anticipate running any route-wide consultations. It is possible that we need to do some targeted engagement if there were to be any significant changes at a local level in the route design. That might happen, but it is not part of our plan.

  1.             Alex Mayer: You mentioned that, had the legislation been in place earlier, it potentially would have changed the way you did those first four consultations. Are you making any changes going forward because the legislation is now in place?

David Hughes: The biggest impact of the Planning and Infrastructure Act is on the pre-application process. Believe it or not, it will enable us to get to the point of DCO submission this time next year more quickly than would otherwise have been the case. It has limited impact on what happens when you get into the examination stage, and the Government are now looking at this more broadly. It comes back to Mr Glover’s point. If you step back, East West Rail was initiated in 2017, and the earliest we will have spades in the ground is 2029/2030, i.e. 12, 13 years. There are all sorts of reasons for that, but it is not on a lower Thames crossing sort of timescale. It is part of a much bigger debate about how long it takes to get major infrastructure spades in the ground. We are part of that debate. The new legislation has definitely helped. We have mainly captured the benefit of it in the pre-application phase. It does not change the bar very much in terms of what we have to demonstrate in the examination itself.

  1.             Alex Mayer: Does anyone else want to say anything?

Jodie Lofthouse: The only thing I would add to that is, on this project, we have been engaged on the Planning and Infrastructure Act and the opportunities that it afforded very early on. We worked really closely and set up governance across Whitehall to make sure that we take on board and utilise opportunities wherever possible. David talked about a number of those. There is always more to do and more to consider. Utilising opportunities for East West Rail also allows us to identify and demonstrate other opportunities we can draw out of that so that we can leave more of a legacy from this project to support other major projects that are coming up behind us.

  1.             Samantha Dixon: Mr Irwin, how has the East West Rail project affected the delivery of Network Rail projects across the region?

Christian Irwin: The East West Rail project was set up by us in 2015 under an alliance with some brilliant delivery partners. There has been a standalone alliance team in existence for nearly 11 years that has worked in full collaboration with East West Rail Company, our operators and the Department for Transport, but also on discharging the Transport and Works Act order and engaging with communities through the delivery of the programme. Given the standalone nature of the alliance, we had a very lean team to manage delivery, the equivalent of 10 full-time staff, so it is a very cost-effective way for us to deliver our infrastructure projects.

In terms of the project itself, while we and all our colleagues are very disappointed not to have passenger services running right now, if you look at how this was delivered using a modern form of NEC contract, using the Government construction playbook in how we collaborate and build target costs; during the life of the alliance, through the design stage we were able to reduce the cost by nearly £300 million. Through the delivery stage, we saved £60 million and handed that back to the Department for reinvestment into future stages of East West Rail. During the construction period, which was very challenging through Covid-19—construction phases started at the back end of 2019 into 2020—we managed to offset nearly £300 million-worth of headwinds that impacted the project. From a delivery front, we are really proud about what we have been able to learn through the life of this project.

If you look at our future investment projects, certainly big programmes such as the midlands rail hub, the west coast main line modernisation, TransPennine route upgrade, there are a phenomenal amount of good lessons that will also affect future delivery. You made the point earlier: we need to act and operate collectively as an industry. It cannot be that one part delivers its bit and the other parts say. We are a railway and we need to deliver outcomes. Over the last 10 years, rail investment has been on a journey of shifting from being infrastructure-focused to being very much outcome-focused. The reality is, the East West Rail line will deliver phenomenal transportation outcomes. Let us not forget that the outcomes go far beyond transportation in terms of connectivity, access to jobs, employment, education and gross domestic product growth. That is what we need to focus on and why it is so important to have a fully integrated team under David’s stewardship, with Network Rail, operators and East West Rail Company, DFT, all aligned on the outcome. That is the lesson we take going forward.

  1.             Dr Arthur: Christian, of course, the 10 FTE lean team would sound a lot better if the project was running better, would it not? Yes? You said you have learned valuable lessons from the project. Were the problems the project has been beset with inevitable? If Network Rail had been delivering it, would some things not have happened?

Christian Irwin: I will just replay the point I just made. We as an industry are accountable. We work with our partners over in East West Rail Company. We are an arm’s-length body of the Department for Transport. While we were brilliant at specifying the infrastructure—"Great, we can crack on and build that, we know how to do that"—what we got wrong at the start of this programme was we did not specify the operation, the end outcome, how the rail system was going to come together. The railway system is very complicated. It is not just about the hard and soft infrastructure, operations and maintenance. You heard this morning; it is about how we operate the trains, dispatch and make sure passengers get where they need to be.

  1.             Dr Arthur: Are you saying these problems would have happened if Network Rail had delivered the project?

Christian Irwin: As I said, the journey that the industry has been on over the last five to 10 years has been flipping our investment approach from infrastructure very much into outcomes. We learned those lessons on Network Rail’s self-delivered projects as well as those delivered by other people. The reality is that it is a learning approach. We are very much focused on the end user, the end outcome, the passenger. Previously, our investment projects were very much focused on the infrastructure side, and that is a huge lesson we take going forward across all our rail investment schemes.

David Hughes: It comes back to that key lesson from the first phases. It is at the heart of the thinking behind GBR and how we set up delivery of future phases of East West Rail. Do not think about the railway in a fragmented way in terms of infrastructure, trains, rolling stock, people; it is a whole system; you have to manage it as a whole system. It does not really matter who was in charge in previous phases; the structure was fragmented. The whole thinking behind GBR is to try to put that right; and I think it will. In the meantime, in planning future phases of East West Rail, we are putting it right by making sure the accountability is with us.

Dr Arthur: You are so on message, David; I like this.

David Hughes: Well, it is because I believe it. Honestly, it is not being on message. My background is rail delivery in London Underground, which is a vertically integrated rail system. How can you run the railway in any other way than as a whole system?

Ben Rule: I agree with what has been said. A lot of projects failed to deliver benefits because there was no alignment between things that needed to be perfectly aligned at the end of the programme. You need an infrastructure that matches the rolling stock, that matches the competence and the training of the staff that you have recruited and the authorisation you get from the regulator, as well a number of other things. When any of those things are out of line with the others, you end up failing to deliver your benefits.

One of the mistakes we have repeatedly made is that some things to do with operating the railway rather than building the infrastructure are seen as things that you can consider towards the end of the process, and they are not. You have to think about them earlier. During the period that the railway has been privatised, we tended to equate the word operations with the appointment of a train operator through its franchise; and this made things worse. Operating a railway is not just about appointment of a train operator through a franchise; it is about speaking to operators that know how a railway is to be built and making sure their voice is heard early enough in the process that people can take it into account.

Since I arrived about 15 months or so ago, my job has been to make certain that the collective voice of operators is heard in the programme early enough that issues can be identified and people can make choices about how to avoid problems as we go forward. I have got together the various train operators involved in this. There are a number of them because it is not just Chiltern; it is Great Western, West Midlands, Greater Anglia and GTR. We are already speaking to them and to their rail operating people, so that we have a common plan and we can flag to the project things that need to be considered early. That will make it more likely that key outputs you talked about earlier are delivered successfully in the end.

  1.             Dr Arthur: Do you involve the unions in those conversations as well?

Ben Rule: We talk to train operators and Network Rail. They obviously have the relationship with the trade unions as they employ the people who work there. We want to make sure we take all issues into account.

  1.             Daniel Francis: Jodie, in 2023, the National Audit Office assessed the East West Rail project as offering poor value for money. What is your current assessment of the project’s value for money?

Rosemary Hopkins: That is probably one for me to pick up. It is piece of work that we are taking forward with East West Rail in co-operation with the outline business case, which, as David says, will be available early next year as part of the decision-making ahead of DCO’s mission. It is fair to recognise that East West Rail is the backbone of the Government’s growth strategy for the Oxford to Cambridge corridor. It is the enabler for potentially as many as 100,000 houses. It is going to be the feeder for potentially two new towns that are in MHCLG’s strategy. It is feeding the biggest visitor attraction in Europe. We estimate it could deliver as much as £6.7 billion of GVA to the local economy by 2050.

We need to recognise those strategic benefits and the impact that East West Rail can have on growth, on connecting people to jobs, opportunities and housing in the area through the business case. We are collectively working to ensure that we quantify where we can in terms of transport and growth, but that we also recognise the wider strategic opportunity and value that the scheme adds and capture that in the business case. As SRO for subsequent parts of the schemes, we need to set up both governance and partnering arrangements across Whitehall to ensure that the benefits from East West Rail are fully utilised through delivery and the incremental investment that will be needed around, as I say, new towns and other enabling infrastructure in order to maximise that economic case.

David Hughes: I agree with all that Rosemary said. I am often asked, “Are you confident in the business case for East West Rail?” I am wholly confident. I am on message on this as well because I believe it. I am wholly confident in the business case for East West Rail, but it comprises a number of elements. The key one is the strategic case, which has been backed by successive Governments, including this one. The railway makes a reality of the Oxford-Cambridge corridor, where growth is critical to the future prosperity of the UK. That is the strategic case, about housing development at large scale, hundreds of thousands of homes, connectivity, connecting to high-productivity jobs in the kinds of industries that will be critical to the UK’s future prosperity. It is a really strong strategic case.

People confuse business case with benefit-cost ratios and the intricacies of transport appraisal guidance. My personal view is that the business case methodology that drives the BCR is poor at capturing the benefits of schemes such as East West Rail. It is not a railway transport project; it is one for economic growth. I sometimes say it is a housing project with a railway attached. The methodology is really poor at capturing that, which is not unusual for this sort of project. If you look at the Borders Railway, no one who would say that is anything other than an outstanding success. It had a poor BCR when it was committed to by Government. When asked about the business case, I say, “We’ve got a really strong business case.” It is compelling. It is about making a reality of that Oxford-Cambridge corridor. BCR, I do not expect, will be very good. The report of the NAO before my time does not surprise me. I do not think on the standard methodology we will score well on BCR. That is not the basis on which we make the case for investment in this railway.

  1.             Daniel Francis: If the National Audit Office compiled a report today, would it say the same based on the BCR analysis?

Rosemary Hopkins: There are two elements to this. There is making sure that we quantify all the benefits we can as part of the benefit-cost ratio for the scheme; then it is important to recognise the wider strategic case and opportunity that the project represents beyond what is quantifiable in a BCR when providing advice to Ministers for them to make a decision on whether this is the best use of public funds for delivering infrastructure that can enable growth. As SRO working with David, it is really important that we set out a narrow transport case in well-quantified in economic terms, but also that we take a place-based approach to exploit the opportunity to demonstrate the value this project provides to the growth corridor and to the wider economy. This is not typically captured well in a transport economic appraisal. The decision will be taken in the round on the basis of all the cases, strategic and economic, for the scheme.

  1.             Daniel Francis: Back in 2033, DFT was expected to spend between £5.7 billion and £6.6 billion on the project. What is your current assessment of how much it is projected to spend?

Rosemary Hopkins: I am going to pass that on to David in the first case because you are doing the numbers for my business case.

David Hughes: It comes back in part to the answer I gave to Mr Glover earlier. The current estimate in the public domain is from 2023-24 of £6 billion to £7 billion, and that is in 2021 prices. As I explained, over the next six to nine months, as we head to that OBC submission to Government in the summer of next year, we are working out our revised view of the schedule and the cost envelope required to deliver the scope of the railway that we now have. The scope has changed significantly since 2024; to a large extent that is driven by Universal. We are delivering more benefits, longer trains and more frequent services to make sure we can accommodate the additional demand from Universal, which is a good thing in terms of revenue and so on. Having the UK’s biggest tourist attraction on your doorstep is a good thing, but we had to make changes.

As I said to Alex earlier, we have pretty much locked down the scope now to take into the DCO. We need to cost that design. This is about making the best possible judgment about what our cost envelope will be to deliver the scope we have now agreed with the Department. That will take us through until the review point 2 moment in June/July next year when we will set out a revised cost envelope. The design has changed, and of course the previous estimate is in 2021 prices, so everyone can do the maths around that.

  1.             Daniel Francis: Can you tell us how much has been spent today and break that down?

David Hughes: I cannot, and I would not want to because to do a running commentary on what I might think at any one point in time is not the right way to do this. We have committed to Government that we will set out our best view for all the reasons I said earlier. Do that now before the point of commitment. Get the judgment right in terms of being ambitious about efficiency, but do not lose a grip on reality; do not succumb to optimism bias. These are really difficult judgments that I need to make with my leadership team and with the East West Rail board. We will present the outcome of that at review point 2 as part of our OBC submission to Government.

  1.             Daniel Francis: I heard what you said earlier, obviously on experience from elsewhere, but is there anything else you want to add on how you are going to ensure that costs do not exceed estimates along the way?

David Hughes: To repeat the same point, there are lots of reasons why rail projects go over their initial estimates. One is you get the initial estimate wrong. To refer to the book by Jonathan Simcock that Mr Glover mentioned earlier—it is well worth a read, not just because I am quoted in—about dangers in Government-sponsored projects in particular, in terms of the temptation to lowball estimates at this point in the process, not in a Machiavellian way but the way the system works, there is a risk, and we see it time and again, that the initial estimate is wrong. You get the funding commitment and then you are fighting a battle after that because your costs exceed the estimate.

The challenge ahead for my team and board over the next six to nine months is to get that cost envelope and give our best possible view of what the Government will have to invest to deliver the scope that we have now arrived at.

Rosemary Hopkins: Could I come in on the Department’s role in this as well? As SRO, my responsibility is very much about setting the strategic direction of the project, which we have talked about as the backbone for growth in the Oxford-Cambridge corridor, to set out the sponsor requirements of what we want for an operational railway, ensure that we have the governance to oversee that effectively and hold the programme to account for delivery. At the moment, as David says, we are working up that cost envelope and schedule. It is about building confidence in that cost envelope and schedule, getting the right balance between what is minimum viable product and what is the best value for the taxpayer in terms of what we can deliver, but also balancing that with confidence that it is deliverable.

We talked a little already about lessons learned from HS2 and other major projects, where large infrastructure schemes sponsored by Government have gone wrong previously. Common themes are around under-specifying or underestimating the cost and then watching it creep up over time. I was keen to agree with David that we need to take time to work thoroughly through both the schedule and what is achievable and the cost envelope required to deliver that, being as lean and responsible as possible with public funds. Then we need to put in place the governance to ensure that David has the objectives and incentives to deliver but also the resources to do the project well.

I look forward to working up the business case so that a ministerial decision can be taken as to whether this is right investment choice. The scope looks down at the point when DCO is submitted and Government decide whether to make the funding available to take this project forward. Changing the specification, hitting affordability problems and taking projects to market when they are insufficiently mature is what drives uncertainty, delay and the cost growth that we have seen on other projects. That is where we take the learning on board, taking the time to get it right, scope it well and cost it properly at the outset.

  1.             Chair: How much has been spent on the project to date?

David Hughes: There is the phase 1.

Chair: Yes, by phase.

Jodie Lofthouse: The overarching funding envelope for phase 1 is £1.2 billion. We expect to come within or under that budget.

David Hughes: I would have to write to the Committee to confirm. There is delivery of the phase 1 infrastructure. East West Rail Ltd has been in existence for nine years. For most of that time, the annual spend has been relatively small. We are ramping up now. We put our accounts in Parliament last Monday. In terms of design development, we spent £190 million in the last financial year. Our budget for the current financial year is around £275 million. We are ramping up. The bulk of that spend now is on design development. Again, a key lesson from HS2: get your design to the level of maturity that you need to make informed judgments about cost envelope. The lion’s share of our spend at the moment is on design development. We also have a very extensive survey programme. If you are out in the area, particularly between Bedford and Cambridge, you will see a lot of folk in orange jackets doing ground investigations, environmental surveys and so on. That is again a key lesson from previous projects: you invest in your design maturity and spend as much as you can on understanding the ground conditions in which you are going to deliver the project.

Chair: We get that from HS2. Thank you; that is helpful.

  1.             Olly Glover: East West Rail is proposing discontinuous electrification with battery electric trains for the next phase of the project. The Campaign to Electrify Britain’s Railways has argued that the case for discontinuous electrification on a railway such as East West Rail has not been adequately demonstrated. How would you respond to that criticism?

Ben Rule: You need to start by remembering the purpose that East West Rail has, which is to provide connectivity along the OxCam Corridor to drive economic growth. That is what we are tasked with doing. To do that you need some trains, so there will need to be a procurement of trains to run the service from Oxford to Cambridge. DFTO are the procuring authority for that; we are working with DFTO to make sure that those trains are available. DFTO has recently published the rolling stock and infrastructure strategy that sets out how DFTO intend to deliver new trains for the country, of course, which has made it very clear that moving away from diesel rolling stock is their policy. That means that you will end up with fleets of electrically powered trains; that is the direction of travel.

The question then becomes to what extent is that driven by full electrification or discontinuous electrification? Discontinuous electrification is a way in which we can reduce the capital cost of delivering the infrastructure. The rolling stock strategy sets out that that is the preferred direction of travel for discontinuous electrification battery EMUs. There is a clear direction from the Department that we are expected to deliver our benefits by the best possible capital cost. We are incentivised to try to do that as efficiently as possible on this project and battery EMUs with discontinuous electrification allow us to do that.

It is worth just giving an example of why discontinuous electrification can save us a significant amount of money. Quite a lot of the national grid power lines in the country actually run north-south; our railway runs east to west, which means that there are a number of points at which our railway crosses those grid lines. For us to put overhead line on the railway in some of those locations would require those national grid lines to either be lifted or buried. That is a significant cost, and if you can avoid that it keeps the cost down; it will also incidentally reduce schedule risk because national grid and other power companies are under quite a lot of pressure with the amount of work they have to do. Avoiding those is good from a schedule risk point of view, as well. Our proposal is for discontinuous electrification battery EMUs because we believe that will deliver the benefits at the best capital cost for the programme.

  1.             Olly Glover: There is quite a bit to pick at there. Let us start with what you said about the right overall rolling stock approach; you cited the rolling stock strategy, but my recollection of reading that document is that it very clearly says in there that for railways that are intending to have freight as well, then full electrification might be justified. You have cited earlier in your evidence today that there is a case for using freight on East West Rail. Would discontinuous electrification and battery trains enable electric freight, in your view?

Ben Rule: We talked earlier about the fact that we are providing the capacity to allow freight trains to operate; we talked about freight train per hour. Doing discontinuous electrification does not prevent freight trains from operating along the line of route. We are tasked with providing that connectivity between Oxford and Cambridge, driving that economic growth. We believe that by doing discontinuous electrification we can deliver those benefits we are tasked with delivering for the best capital cost for the programme. That is why we have proposed discontinuous.

David Hughes: Mr Glover, Ben is much closer to the detail, but a reflection from me is that when I came into this role in June 2024, the assumption that the project was working to was that the end-state rolling stock would be diesel: the assumption was that this would be a diesel-traction railway. Two things became very clear to me very quickly. First, that was never going to be acceptable to stakeholders on the line of route, who could not get their heads around why you were building a new railway with the intention of it being diesel-operated in the 2030s. Secondly, we would never get the money for full electrification of this railway from the Department, and particularly from the Treasury.

  1.             Olly Glover: Why is that?

David Hughes: I will not speak for the Department. I will give you a view, not really so much from my position as chief executive of East West Rail, but my experience generally. The Treasury looks at the amount it needs to spend on decarbonisation across the UK as a whole, not by sector. It looks at rail as a form of transport that actually is, relative to other forms of transport, relatively carbon friendly. From a Treasury perspective, and I am sure Rosemary and Christian will have views as well, one of the difficulties that the rail industry has had in arguing for more investment in electrification is the Treasury thinks actually in terms of bang for buck in meeting the UK decarbonisation target, rail is not where it wants to put its buck, it wants to spend it in other areas. I just think that is a general context that we have.

The way that felt to me coming in is that I came in and said that delivering a brand-new railway on the basis of diesel traction is not going to be acceptable in the mid-to-late 2030s. I can see why it was a real bone of contention for stakeholders and communities along the line of route and the upfront capital cost difference is in hundreds of millions. The discontinuous route allowed us to decarbonise the end-state traction solution that was hugely well-received along the line of route, and it did so at a cost that was going to be acceptable to Government.

In a world where money was no object that might not be the solution you arrive at, but that is not the world in which we live. We have ended up with a solution that allows us to have a decarbonised railway at a cost that is acceptable to Government and using a technology that is now going to become increasingly the norm in line with the national strategies, actually not just in this country but in Europe as well. The route to decarbonising the railway is not going to be putting wires up across the whole of the network.

  1.             Olly Glover: Yet all across Europe they continue to do so. Countries in Europe have a vastly higher percentage of electrified lines than we do on average. Are you aware of any other 100 mph high-frequency railways that are being proposed for discontinuous electrification, and not full?

Ben Rule: We are not aware that there is an identical railway that is set up in that way. There are a number of railways around Europe that are being set up as discontinuous electrification; I do not think there is an exact match.

  1.             Olly Glover: Are there any new ones that do not come with the same burden of structure clearance?

Ben Rule: I am not aware of one that matches that in Europe. That does not mean to say that we cannot use discontinuous electrification on our railway to provide a decarbonised railway that delivers the benefits that we are tasked with delivering.

Olly Glover: I have two more, Chair; I do not want to hog it for too much longer.

Chair: No, go on because it is quite important.

  1.             Olly Glover: Thank you for your forbearance, Chair, and indeed everybody else. Okay, there is still a bit more I want to probe about that. You mentioned that the cost savings are in the hundreds of millions. What is the cost per standard track kilometre you are assuming for electrifying your railway?

David Hughes: I will have to write you on it; I do not have that to hand.

  1.             Olly Glover: Please do write. That would be great because, given that it is a relatively small distance you are not proposing to electrify, that cost is very surprising given that as a result of its rolling programme Scotland has the cost per standard track kilometre down to about £2 million. Forgive my rough maths, there is about 30 km—20 miles—you are not planning to electrify, so 60 km times £2 million for the track, so it does not necessarily get to hundreds of millions that quickly. Of course, that is a new railway without structures to clear, which is some of the cost, but that is my very rough maths.

Ben Rule: We will write to you on that. It is worth going back to the point I made earlier on that it is not just about the pure cost per kilometre. There are those other specific costs around things such as utility diversions that you have to take into account to get the total cost.

  1.             Olly Glover: Yes, I wanted to come back to that. There has been another east-to-west railway that has been electrified in recent times, admittedly with problems; that is the Great Western mainline electrification. Reading the National Audit Office report there is no mention of the costs resulting from national grid power line diversions as a factor. From having looked into the Midland mainline business case, the information I have been given from conversations I have had is that that accounted for about 0.2% of the cost. What is different here? Have you looked at the costs of that particular element in previous electrifications?

Ben Rule: I was the operations director for Great Western Railway at the time when the thinking was being done on electrifying Great Western Main Line. I can recall that there was great concern in the programme at the time about the fact that the diversions that needed to be done, at least one of which is in your constituency, I think, were potentially going to put the programme at risk because of the length of time it would take. There was a lot of concern at the time about it. The electrification of Great Western main line obviously took longer than expected and was more expensive than expected, but I am pretty clear that there was concern in the programme about the scale of work required to do that. I do not know the exact cost numbers, but I can recall there being a quite significant concern about the scale of that.

  1.             Olly Glover: Perhaps you could write to us about that as well.

Ben Rule: If we have those numbers, we can write to you.

  1.             Olly Glover: Hopefully you do because you are citing it as a big reason for your decision.

Ben Rule: We definitely have the numbers for the cost of the diversions that we would require to do on our railway. Whether we have the numbers for the diversion specifically on Great Western is a different matter.

Olly Glover: Just two more, Chair, and then I promise I will stop.

Chair: I think Christian wants to come in as well.

  1.             Olly Glover: Sorry, right. Just on that, have you had your assumptions about electrification costs and rolling stock capability and costs peer reviewed?

Ben Rule: We have a number of expert panels inside East West Rail that give us independent advice from experts on a number of different topics. We have had electrification expert advice; they have looked at our proposals and made some observations on them, so yes, we have had external advice on what we are proposing to do.

  1.             Olly Glover: Just one more question, Chair, I apologise. In terms of the assumption that it is cheaper. Mr Hughes, you keep referring to optimism bias, which is a very important thing to think about. Does the fact that the cost of 29 five-car trains for TransPennine Express with batteries is £1 billion—£6.9 million per vehicle, which I am pretty sure is one of the most expensive rolling stock orders ever—support the assertion that indeed it is necessarily cheaper to do discontinuous and batteries?

Ben Rule: Our assessment of the business case for discontinuous electrification has assumed a range of lease costs for rolling stock. The way in which we have done it is by assessing the lease cost of the rolling stock. We have taken a range, and that assessment has included a range for the lease cost of battery EMUs, which is higher than the lease cost for a plain EMU. Our assessment has included a higher lease cost for battery EMUs already. That is the way in which the business case work has reflected the risk of battery EMUs being a more expensive train.

Christian Irwin: The conversation has moved on a little but just on the point about benchmarking electrification costs, there has been a phenomenal amount of lessons that have been learned since the Great Western electrification. We held a challenge panel internally to the industry on reducing the cost of electrification with our chief executive only three weeks ago, and with the amount of innovations that have come through in terms of how long we can put between stanchions and voltage control clearances, we have been able to really drive down some of the costs of electrification. Scotland particularly has done a wonderful job in terms of that, and you quoted its benchmark rate of £2 million per kilometre.

Where the challenge on electrification comes is in highly congested urban areas. We are still really struggling to find a way to drive the cost down below £5 million or £4 million in those highly congested areas, with complex utilities, bridges and structures. Wigan to Bolton delivered about £4.5 million per SDK. I recently spent some time with Transport for Wales colleagues on its Core Valley lines, which has recently delivered its partial electrification, saving nearly £300 million. Its narrative was very clear around where it is complex and disproportionate to deliver electrification, the efficiency of being able to have that battery on board enables the railway to be very successful, and its batteries never dip below 90%.

There is innovation to drive the SDK rate down, and that is really important, but there are certain parts of the infrastructure where it is disproportionately expensive. The cost of putting in what we now have—an automatic pantograph changeover with leads on the ground that allows the pantograph to drop, to run into an alternative mode and then to pick up. That efficiency in terms of pure infrastructure is significant, and we are talking hundreds of millions of pounds. Certainly the conclusion we drew from our industry challenge panel electrification cost is that, where it is appropriate to do so, that has to be a fundamental part of our strategy going forward.

Yes, we need to prove that the technology is suitable and robust. Yes, you need to demonstrate that rolling stock is affordable to buy that, but we are starting to see through our procurement in TransPennine, what we are doing in Liverpool and the Core Valley lines, and we are going to be going out with colleagues in Italy, France and Germany looking at some of their partially decarbonised routes.

  1.             Olly Glover: Yes, but I will just come back to the point about 100 mph operation, which is definitely not what happens in the valley lines in south Wales. There are some differences that I hope are going to be looked at.

Rosemary Hopkins: Just in conclusion, I wonder whether it is worth coming back to the Government policy on this. We already talked about the wider rolling stock and infrastructure strategy that is supporting the increasing use of standardised battery electric fleets. In making that policy recommendation the Department has confidence that it will deliver a net zero passenger railway at significantly less infrastructure and lower upfront costs than full electrification. That is certainly what the numbers are suggesting on East West Rail. We have considered full electrification, but the analysis suggests that the infrastructure costs are higher, while delivering a similar passenger outcome. The important thing to note here is that both the final traction and the fleet solution still remain subject to that business case approval, and that will be part of the decisions taken at the ABC stage.

  1.             Samantha Dixon: Can we have an update on the work of the East West Rail economic growth board? What work has it been carrying out and are there any conclusions and recommendations that it has made?

David Hughes: The economic growth board was reworked after the 2024 election and is now the Oxford to Cambridge growth corridor unit in Treasury under the leadership of Lord Patrick Vallance. That replaced the economic growth board and continues to play a really important role in convening business, academia, local authorities and the stakeholders along the line of route to drive the agenda for economic growth in the corridor. Rosemary and Jodie will probably want to comment on that. East West Rail Ltd was really pleased to see Lord Vallance confirmed continuing in that role as chair of the growth corridor following the recent change in Prime Minister, because he is a very powerful advocate for the importance of the corridor and the importance of East West Rail in making a reality of the corridor.

  1.        Samantha Dixon: There was some criticism in 2024 that the board was quite isolated in terms of local perspectives. Was that the response to it?

Rosemary Hopkins: Certainly my experience does not align with that. My attendance at the ministerial delivery group has included sessions with England’s Economic Heartland, actually providing that joined up approach across the corridor to look at the opportunity as a whole. The delivery board has been just hugely helpful in terms of convening all the parts of Government who have an opportunity to influence the success of this project together, both to unlock barriers to successful delivery and really bring some momentum and focus to what needs to happen to make this work well.

There is a cross-Whitehall piece there, driven by Ministers, to set the ambition and to unlock the impediments to success. In learning the lessons from HS2 and other major projects we have been able to refresh our own governance and oversight of the project to ensure that we are also replicating that cross-Whitehall influence and focus in our own governance. On the back of the James Stewart review and the recommendations for HS2, we have looked at our own sponsorship and governance arrangements, and we are about to step up a new programme board for the programme as a whole that will include the cross-Whitehall attendance from MHCLG, Treasury and other colleagues, to really set that expectation for a whole of Whitehall collaborative endeavour to maximise the benefit that the enabling infrastructure can have in terms of growth.

  1.        Joe Morris: We are familiar with the reporting from Rail Magazine at the end of 2025 that there was strong reporting, consideration and support for taking East West Rail in-house to Network Rail. David, is that still being considered?

David Hughes: It is really important to start from an understanding that East West Rail Ltd and Network Rail are not two completely separate beings. We are both arms-length bodies of the Department for Transport. East West Rail Ltd sits in Network Rail offices. My leadership team comprises a number of NR secondees, so we are working hand in glove with Network Rail. That is really important, and actually around half of the spend on the programme will be delivered by Network Rail on its infrastructure. About half of it is the new-build stuff between Bedford and Cambridge, and half of it is upgrading existing rail infrastructure. The success of this project is critically dependent on East West Rail Ltd and Network Rail working hand in glove.

One of the questions that I raised when I came into the role—I do not have a selfish agenda in maintaining an independent East West Rail Ltd—with Government and with Andrew Haines, the then chief executive of Network Rail, was about whether it still made sense for East West Rail Ltd to be a separate arms-length body set up for the delivery and design of the railway. There is a lot of history here. When East West Rail was first set up back in 2017, there was a very different vision about what its role would be and how the future operation of the railway would look. We are very clear now that our role is as systems integrator, as we have touched on already. Our job is to co-ordinate inputs from across the industry to make sure we bring together all those elements that are required for successful delivery of railway services. That is the outcome that we need. We specifically raised whether keeping East West Rail as a separate arms-length body was the right thing to do, in the context of the James Stewart review into HS2 governance. Off the back of the James Stewart review the Department and East West Rail jointly commissioned a follow-on review of East West Rail governance that included James himself, actually, as part of the review team. One of the questions that we posed to that review was, “Would it make sense to move East West Rail Ltd into NR, or in fact GBR, from day one?” The conclusion that was reached by that review, which was endorsed by Ministers, was that for the time being at least there is actually merit in retaining East West Rail Ltd as a separate arms-length body.

Why is that? Partly just where we are in the programme, having a single-purpose vehicle focused on securing the DCO, developing the design, getting the project to the point of main works delivery, it makes sense to keep East West Rail Ltd as a separate body and, in the meantime, allow GBR stand up to take place.

It is fair to say, although it is probably not written down anywhere, there is an expectation that in a few years’ time—maybe 2029/2030—all being well we will have secured our DCO and full funding for the railway, will be at the point of starting main works delivery and, in parallel, GBR will have been stood up in a more steady state. There is an expectation that whoever is in Government at that time would probably want to consider whether we should revisit the question of whether East West Rail should remain as a separate entity, at that stage. That question was looked at very carefully in the light of the James Stewart review into HS2. There were pros and cons around it but the decision reached was that to try to incorporate East West Rail into GBR at the point of stand up would, for the time being, probably import a bit of a risk in terms of distraction from all the other changes going on. It makes sense to remain as we are for the time being.

The point I would stress is that we are not two separate organisations in the way that perhaps we were when East West Rail was first established back in 2017. That was very much the original vision for East West Rail when it was set up by the then Secretary of State, Chris Grayling. That is not where we are in today’s world. As I say, we work hand in glove with Network Rail; that is the trajectory that we are on.

Chair: Do keep the answers quite short because we are short for time now.

Ben Rule: To add a little to that, David has talked about the question as to whether East West Rail should become part of Network Rail, Great British Rail. It is also worth thinking that Network Rail is a series of routes, though. I talked about north-south power lines earlier on, but actually a lot of Network Rail’s routes run north-south as well. Those routes will become business units in GBR. East West Rail’s route actually cut across seven of those GBR business unit routes. Regardless of whether East West Rail is inside Network Rail, GBR or not, it is important to have a group of people who are focused on bringing the East West Rail project to a successful conclusion.

  1.        Chair: It is quite important that the relationship between East West Rail and Network Rail is effective. Do you think it is working to date?

Christian Irwin: As Ben just described, this is about how we integrate and how our relationships work to deliver this together. Whether in Network Rail, outside Network Rail, in GBR, it is about how we structure ourselves in terms of the governance, the assurance, and how we set the system up for success. We have recently made some significant changes in how we integrate together. David has appointed one of our major programme directors to sit on his leadership board and Kayleigh, who fills that role, represents the broader Network Rail and the six or seven routes that it crosses. We interface with five main line timetables. That integration is absolutely fundamental, but having a clear, guiding mind focused on the outcome is really important and David’s team can provide that.

What we can provide in terms of that integration is making sure that while we are building the new, we keep the existing railway operational during construction and post construction. That interface—playing the best athletes in their roles—is really important. We have really established that clear governance. Yes, we still have work to do in terms of how we move into the next delivery phase, but we are pleased with the direction of travel and the integration we have together.

David Hughes: If I may add a very brief comment to Christian’s point, Chair, we have mentioned the review of governance we have done; to really give effect to the lesson learned and the need for integration we now have Network Rail and DFTO embedded at every level of our programme governance, up to and including the East West Rail board. For example Ellie Burrows, the regional managing director of eastern region now attends the East West Rail board. There is complete integration from my team right the way up to the East West Rail board, to make sure we are looking at this as one system.

Chair: Okay. Scott, has your question more or less been answered?

  1.        Dr Arthur: I think we have covered HS2 and lessons learned, unless any of the others have anything to add on that?

Rosemary Hopkins: The only thing I would pick up from what we have just been saying about the collaborative working with Network Rail and East West Rail Co picks up one of the lessons from HS2 lessons learned as well, which is clarity of accountability. In addition to the governance arrangements, we have been very clear about the accountability that David and the East West Rail Co have for integration of the whole: bringing together the relationship with Network Rail and DFTO to take responsibility for delivering an end-to-end railway into operation.

David Hughes: Just very briefly on the HS2 lesson learned, I have mentioned Mark Wild already and I meet regularly with him. I would say the biggest lesson already actually embedded in the project and the biggest advantage that East West Rail has over HS2, in some ways, is we have absolute clarity of what we are trying to do, why we are here and what our purpose is. We are here to enable sustainable economic growth along the Oxford-Cambridge corridor. HS2 has suffered from the get-go about not being absolutely clear what problem it is trying to solve.

Dr Arthur: You even have a completion date, which is extraordinary, as well.

David Hughes: We are absolutely clear what we are here to do.

Chair: I do not think people would disagree with that.

  1.        Dr Arthur: What about lessons learned from East West Rail itself for other projects? David, Ben and Christian have already touched on this; Rosemary and Jodie, do you have anything to add in terms of future projects and what we can learn from East West Rail?

Rosemary Hopkins: There has been a lot of learning from HS2 that we have taken into East West Rail in the Department’s governance and oversight arrangements. Some of the things that have changed in our sponsor team around recognising the need for a dedicated SRO, rather than putting East West Rail as part of a portfolio; working on our sponsor capability and our role to specify and set the policy intent, the objectives and the outcomes, but then very much be eyes on but hands off and give the accountability to David and East West Rail Co.

Building on the experience of HS2 we have been really good at bringing together ensuring that we have really well experienced SROs across the Department leading the major projects with the capacity and the capability to do those well, but also bringing them together as a cohort, with peer support and sharing experience and lessons. I meet with my SRO colleagues of the other big infrastructure projects in the Department on a fortnightly basis to share lessons, experiences, and troubleshoot challenges we have on our projects—both technical and policy—together.

Jodie Lofthouse: Really quickly, obviously one of the latest projects that will also learn from us is NPR; we work really closely with the NPR teams across DFT and are actively sharing the lessons that we learn with them so that they are embedding them even earlier on in the process.

David Hughes: There are two specific areas I would highlight. It is definitely about sharing with NPR. First, the way we have built that strategic case because NPR has a lot of similarities in terms of building an economic case agglomeration, so sharing our thinking about how we have developed this compelling strategic case for the railway. The other clear area where we are learning lessons that we can share with future projects—not just in rail—is we are a pilot project under the Planning and Infrastructure Act. We are the first big project going through the new processes and we are learning some lessons, and we will share those with other projects.

  1.        Daniel Francis: Some local stakeholders, including councils and campaign groups, have argued the 2026 consultation process “lacked openness and professionalism” and that “insufficient information” was provided “to enable meaningful engagement”. How do you respond to those criticisms?

David Hughes: That quote might come from an organisation called Be Fair, which is a campaign group that has existed for a number of years and has campaigned for a different route choice through Bedford. That route choice was made in 2023. Actually, most of the feedback we get is that the consultation processes we run have been really effective. We get really high response rates and we have been able to demonstrate that actually we have made significant changes to our design as a result of the consultation. For example in last year’s consultation, as a consequence of the feedback we changed our tunnelling proposals around Bourn Airfield; we moved the location of Camborne station, and there are a number of other examples I could point to.

Chair: Yes, we have covered the changes.

David Hughes: We have run a really good consultation process in my view. We are the first big project through the Planning and Infrastructure Act. For the process we are going through at the moment with local authorities we have set up an East West Rail forum that brings together all the local authorities at the political leadership level. It is chaired by a former chair of this Committee, Huw Merriman. Lord Hendy dialled into that first meeting we had a few weeks ago and explained to the local authorities that it will feel different, and the leadership of the local authorities get this. We are the first project going through up to the DCO submission under the processes established under the new Act and, as it is different it will feel a bit bumpy and a bit uncomfortable at times. As I said earlier, it does not actually mean less consultation, it means doing it differently, in a more iterative way.

I do not accept the criticism that you cite. I do a lot of public events, and what I have found is that those who turn up at the public events are often there because they have concerns about the project. I cannot tell you how often I have had people say to me,, “Well, I am not a big fan of the railway, but this was a really good event.” We do it really well.

  1.        Daniel Francis: How do you reach those hard to reach groups, those people who never turn up?

David Hughes: It is the silent majority is it not? We do quite a bit of work actually because we do a little polling—

  1.        Chair: Sorry, that is not the silent majority. Daniel was actually referring to people who are impacted but do not generally pick up on public consultations.

David Hughes: We mailshot within a boundary around the railway; I have already mentioned we are out every week, Bedford last night, and Lidlington tomorrow. We get a good response to our consultation.

  1.        Chair: Do you assess them for things such as protected characteristics, homeowners, not homeowners, all of that?

David Hughes: We assess them for all of that.

  1.        Chair: Do you include SMEs?

David Hughes: Yes, and we can provide a huge amount of detail on all that. We work really hard to engage with everyone along the line of route. The criticism that you quote is driven by a frustration from some who are opposed to the scheme. When we came out to consult earlier this year we were very clear we were not consulting at this stage in the process on route choice: whether we are turning left or right, whether we are going north into Cambridge or south into Cambridge. Those decisions were made some years ago.

We were very clear that the purpose of the consultation in the spring was about refining the detail of the design along the chosen route. For those who fundamentally oppose that route choice that is not a message they wanted to hear. That drives some of the criticism that you may have heard, or you quote, around the nature of the consultation. It is because people wanted to relitigate decisions that actually Government took in 2023, that were confirmed by the new Government in 2024. My instructions from Government were very clear: to develop a design based on the route choices that had been made at that time.

  1.        Chair: That is partly a lesson learned from HS2 as well. I just want to pick up on this one item that was mentioned at the first session. Dave Calfe from ASLEF talked about the frustration and the wisdom from his perspective of moving a maintenance depot on the route. Was it a maintenance depot?

Ben Rule: It was the driver depot, was it not?

Christian Irwin: He was talking about driver depot.

  1.        Chair: I do apologise; it was a driver depot. Did you want to pick up on that?

Jodie Lofthouse: Yes, I can start off and then Ben might want to add to it. In the first phase—as part of working up the design—there was always an intention to have a depot in Bletchley. That was part of the proposal for East West Rail specifically. When we brought the operator on board we obviously looked at that from a wider operational perspective. At that point we had advice and proposals from our operator and the rest of industry to ensure we found the right solution. Ministers confirmed that Bletchley was the right solution.

  1.        Chair: Did they confirm the specific site at Bletchley because you talked about one that was already there?

Jodie Lofthouse: There is an existing Bletchley site and that was always within the scope of the options that we had. While that was being set up some of the drivers that were being recruited and brought in would have gone to Chiltern’s home depot. It was always then agreed that eventually all the staff for the line would be in Bletchley.

Chair: Dave had some concern about whether that was right or not.

Jodie Lofthouse: It evolved, but Bletchley was always part of the scope.

  1.        Chair: Just in case, was there anything that was said in the first session that any of you wanted to pick up on?

Jodie Lofthouse: Maybe just on the depot strategy.

Ben Rule: I would simply add that Dave’s point is a valid one, that it is important that you consider those things early. Jodie has talked about the fact that there was a consideration. I made the point earlier on that it is critically important that people who know how to operate the railway have a sufficiently strong voice sufficiently early in the programme. If you do that you go a long way to minimising the risk that those issues become the blocker later. Hard to say they go away completely, but the earlier you think about them, the more likely you are to be able to avoid them.

David Hughes: The only point to pick up from the first session is that David Calfe from ASLEF was very critical about the set-up of East West Rail. I just want to stress that that is the change we have made in terms of our accountability. What he is being critical of is what was in place that has led us to where we are today. We have made changes, as I have said, specifically to ensure we are not there again in the future.

  1.        Chair: Okay, thank you. What steps are each of your organisations going to make over the coming weeks to ensure passenger services are up and running on the first phase as soon as possible?

David Hughes: That is an easy one for us because we are not actually involved in those discussions.

Chair: It's not us, gov.

Jodie Lofthouse: I just reiterate what I said in the last panel, and it is probably what Rosemary will say as well. It is about continuing to work with Chiltern, which is leading the negotiation, and support it to get the agreement we need to get those final few things done and get a confident entry into service date for people.

Rosemary Hopkins: We share the frustration of the panel and the public around not running services on CS1. It is certainly the Department’s ambition and intention to unlock that with Chiltern and the union as soon as we can. We have also talked a lot here about learning from the experience we have there to ensure that the process works more smoothly on subsequent phases.

Chair: Our colleagues in this place whose constituents live along the route are equally frustrated.

Christian Irwin: There are a few key steps for us to take over the next few weeks. Tony made reference to the fact that the station lease was about to be signed for Winslow, that is being sorted this week. We are working with West Midlands Trains to just issue the contracts for seven new staff that will staff the platform 7 and 8 at Bletchley, so they will go out later on this week as well. The final stage for us really is to submit our final evidence to our internal systems review panel to allow both stations to come into full use.

Whatever date we set as the go-live date for passenger services we obviously have to publish the timetable and start enabling tickets to be available for sale at that point in time. Once we get over this morning’s discussion, get a way forward and set a date, we have a very clear path in terms of what we need to deliver.

  1.        Chair: That is the go-live date, what about the completion dates? Can we be any more specific than mid to late 2030s?

Christian Irwin: No, not at this stage.

Chair: Okay. Thank you very much for your evidence and the time you spent preparing for today. Again, if there is anything you did not have a chance to cover or want to add more detail, please feel free to write to us. That concludes today’s meeting. The evidence we have received today, it being a one off session, will inform future deliberations, particularly when we discuss these issues further with the Rail Minister when he next appears before us in December. Thank you very much.