Public Accounts Committee
Oral evidence: Defence equipment plan 2023-33, HC 451
Monday 22 January 2024
Ordered by the House of Commons to be published on 22 January 2024.
Members present: Dame Meg Hillier (Chair); Sir Geoffrey Clifton-Brown; Mr Jonathan Djanogly; Mrs Flick Drummond; Mr Mark Francois; Sarah Owen; Gary Sambrook.
Gareth Davies, Comptroller and Auditor General, National Audit Office, Rebecca Sheeran, NAO Executive Director, National Audit Office, and Marius Gallaher, Alternate Treasury Officer of Accounts, HM Treasury, were in attendance.
Questions 1 - 138
Witnesses
I: David Williams CB, Permanent Secretary, MoD; Tom Wipperman, Director of Strategic Finance and Investment Approvals, MoD; Andy Start, Chief Executive, Defence Equipment and Support, MoD; Lt General Sir Robert Magowan CB CBE, Deputy Chief of the Defence Staff (Financial and Military Capability), MoD.
Report by the Comptroller and Auditor General
The equipment plan 2023-2033 (HC 315)
Examination of witnesses
Witnesses: David Williams, Tom Wipperman, Andy Start and Sir Robert Magowan.
Q1 Chair: Welcome to the Public Accounts Committee on Monday 22 January 2024. Today, we are looking at the defence equipment plan, which is something that the Ministry of Defence publishes every year. It sets out the spending and the capability requirements of the Ministry of Defence over the next decade that our Armed Forces need to operate. This latest plan is £16.9 billion over budget over that 10-year period. That is the largest deficit since the MoD first published the plan. It is a big difference from last year’s plan, with costs having risen by nearly £66 billion.
For a lot of us, it feels a bit like groundhog day as we come back and look at this challenge every year. It is quite right that we look at it over a 10-year period, but it is, nevertheless, a somewhat depressing picture. Some of the reasons for that, which we will go into, are around inflation and other costs, but we need to get to the bottom of what is happening and how the Ministry of Defence will work to bridge that gap.
I am delighted to welcome our witnesses. We have David Williams, Permanent Secretary at the Ministry of Defence; Tom Wipperman, director of strategic finance and investment approvals at the Ministry of Defence; Andy Start, chief executive of defence equipment and support, often referred to as DE&S; and Lieutenant General Robert Magowan, Deputy Chief of the Defence Staff, who is responsible for financial and military capability. A very warm welcome to you all.
Before we go into our main session, we have just a couple of quick questions about other matters that might affect defence.
Q2 Sarah Owen: Good afternoon, everyone. Mr Williams, I am going to ask a question about the Port Talbot steel closures and what assessment you have made of the possible impact that this will have on defence manufacturing going forward.
David Williams: I have not yet reviewed any impact from the recent announcement. We do, however, take the security and sustainability of our supply chain seriously, including access to raw materials. As the Committee knows, the Department intervened just over a year ago to support Sheffield Forgemasters, so it is an area in which we are interested. To the extent that there are wider Government conversations on a response to the announcement, I would expect the Ministry of Defence to be engaged as an interested party, but I have not been involved in that.
Q3 Sarah Owen: Are there any projects or specific programmes that are likely to be affected? What will happen with the shortfall of materials that is going to be needed? What are the possible options available to us with the closure of Port Talbot steelworks?
David Williams: Mr Start may want to come in on this. The supply of steel is, in the first instance, a matter for our prime contractors who are producing equipment for us. I have not had any specific impacts from the Tata announcement flagged to me yet, but I am happy to take that away and write to the Committee, if that would be helpful.
Q4 Sarah Owen: That would be great. Tata Steel UK currently provides high-tech steel to UK defence for engine and gearbox components on fixed-wing and rotary aircraft, and for hatch covers on armoured personnel carriers and nuclear submarines, so it would be great if we could get the specifics on those.
David Williams: I am happy to follow up on that.
Q5 Mr Francois: Good afternoon. That is a smart tie, Mr Start. Mr Williams, on Saturday, Larisa Brown, the excellent defence editor of The Times, had a front-page splash entitled, “Army numbers to drop below 70,000 ‘in two years’”. This is germane to an examination of the equipment plan, because, as you well know, unless you have suitably qualified and experienced personnel—SQEP, as the military calls them—to maintain your kit and keep it working, you can spend all the money that you want on very expensive equipment, and some of it in this plan is incredibly expensive, but, if you cannot maintain it, it is no good to anybody. It could be a ship left on the harbour wall, a tank in the tank park, or an aircraft that is a hangar queen. What are you doing to stop the absolute haemorrhaging of people leaving the Armed Forces?
David Williams: The projection in that article is one from recent trends rather than our plan. It is an issue that all three services and the Department are taking seriously. Our approach is a combination of a range of short-term measures to increase attraction and retention. Some of that involves proposals around financial incentives, for example, as well as longer-term initiatives, including recommendations from the Haythornthwaite review from last summer about how we think about patterns of service and zigzag careers, and make sure that we are accessing the skills that we need.
Q6 Chair: When you say “zigzag careers”, do you mean people coming in and out?
David Williams: People coming in and out of service, yes.
Q7 Mr Francois: Mr Williams, I am sorry to cut across you, but, as you are well aware, there is never enough time in these sessions, so apologies for keeping this tightly focused. At the moment, across all three services, people are leaving the Armed Forces at a ratio of three people leaving for every one who joins. I deliberately use the analogy of the National Health Service, where my wife works, but that is the equivalent of the patient bleeding out on the operating table. You cannot maintain that for long. If you do, you will have operational failure, because you will not have enough skilled personnel to make it work. What you have said is all very well, but I and the Committee detect no sense of urgency. They are leaving at a rate that you cannot sustain. What are you doing to stop the bleed?
David Williams: I do not immediately recognise the one-to-three ratio.
Q8 Mr Francois: That came directly from the fifth floor, privately.
David Williams: On our most recent published statistics—and I accept that those are from the—
Chair: General Magowan is busily looking through his paperwork. We will come to you in a moment.
David Williams: You are right that outflow is higher than inflow. On any numbers, that is the situation. I can assure the Committee that it is being taken very seriously. There is lots of ministerial interest in how the services are addressing this issue. It is probably the number one risk that we are routinely engaging with in senior management fora in the Department. There is a set of individual initiatives that each service is taking, as well as us, in thinking through those broader pay, attraction and retention measures.
Q9 Mr Francois: For brevity, I will have one more go and then hand back. The Army is one example, but it is not just the Army. According to policy, it is going to reduce to 72,500 within the next couple of years. According to this article, it will be at 70,000 in two years. If you extrapolate the trend at which they are leaving, David, by the end of 2026, it will be at 68,000. If you extrapolate the line forward to a decade’s time, it will be at 52,000, meaning that, as a graphic example, you could fit the entire regular British army in the Etihad stadium. Some of them are Man U supporters who will not like that. This really is a crisis. Is the Secretary of State going to make an oral statement to Parliament to flesh out what he is doing to stop the bleeding?
David Williams: Just to be precise, we are aiming for 73,000. There is an additional 500 from the National Cyber Force.
Q10 Mr Francois: At the rate at which they are leaving, that is an academic point.
David Williams: I get that. The numbers that you set out for where the trained strength of the Army would be by those dates is not our plan. I acknowledge that our current plan is not working in the way that we want. I am happy to pass your request about a statement back to Ministers. All I would say is that—and I am trying to think whether I have said this to this Committee before or to your sister Defence Select Committee—if I think about the risks that keep me awake in defence, the number one risk to delivering our programme is access now and over time to the right number of people in and not in uniform, with the skills that we need.
Mr Francois: In fairness, your Secretary of State is an intelligent man. He is now well aware of the problem. The question is whether he could come to Parliament and tell us what he is going to do about it. You have the point. I will leave it there.
Q11 Chair: General Magowan, you were looking for the figures there, and I wondered whether you had any update.
Lt General Sir Robert Magowan: Our figures are five to eight rather than one to three, but that is by the bye. We accept the problem. As the Permanent Secretary has said, probably one of the top three of those critical problems is military capability, and people are part of that. We are not being complacent at all and we have the measures in place that the Permanent Secretary has just mentioned.
The only thing that I would add is that trends change, and can do so quite quickly, particularly around strategic events, which can be either a positive or a negative for recruiting, so I will leave it at that. Trends change in somebody’s head tomorrow morning, so we can extrapolate, but we need to be ready for changes.
Q12 Chair: This is something that we look at in other sessions as well, as does our sister Committee. We want to look at the equipment plan and the affordability of it, and the simple question, Mr Williams, is this. After all this time that I and this Committee have been looking at it, we have a gap, which has significantly deteriorated since last year. Why?
David Williams: As you set out, Chair, the excess on our current assumptions over budget over the 10-year period is just under £17 billion. Just to put that in context, that is around a 6% overall excess on a baseline budget assumption of just under £290 billion. There are two principal drivers of that change. One is the impact of adverse economic conditions, particularly the impact of extraordinary inflation, which has added around £11 billion to the cost of the programme as we previously envisaged that to be. Together with movement on foreign exchange rates of a couple of billion pounds, that is the bulk of the net increase.
We have also taken a decision linked to the context of the dangerous world in which we find ourselves, consistent with the integrated review and with the defence command paper, to seriously de-risk the nuclear enterprise in defence by ensuring that it is fully funded and de-risked, and so there has been a substantial increase in the cost of the nuclear enterprise over that period as well.
As we may come on to, I would describe this equipment plan as, effectively, a work in progress. We drew a line under it at the end of March 2023. There is more to be done on ensuring not only that the programme is affordable but that there is clarity on assumptions around budget, around the costs and around the content of the programme.
Q13 Chair: At the moment, the spending review is scheduled for November of this year, but we will come to that later, because there are a number of uncertainties around that. You have this shortfall of nearly £17 billion. As you say, some of those pressures such as inflation and forex are difficult to control, but you are going to have to manage that shortfall nevertheless, so it is a balance between capability or efficiencies. How are you going to approach that? We stress that it is over a 10-year period, so there is front-loading and back-loading that you can do, but we have seen problems before when you have just moved issues to the right. Can you assure us that you are not going to do that, and what are you going to do to try to shrink the gap?
David Williams: Let me say this in as reassuring a way as I can. One of the uncertainties that we are dealing with is the timing of the Government’s commitment to increase defence spending to 2.5% of GDP. On Monday last week, the Prime Minister said in the House that the timing and trajectory would be a matter for the next spending review. We are keen not to cut, defer or de-scope capability programmes unnecessarily in advance of clarity around that budget. That is one of the reasons why, in the material that we set out to the Committee, we talk about an upside and downside budget scenario.
As inflation changes, the forward costs over a 10-year programme will change as well. Inflation is coming down, so some of the assumptions about the costs of the programme in the later years will reduce.
Q14 Chair: You still have the increase that you have had in recent years.
David Williams: We still have the increase that we have had in recent years, and we are currently in the middle of a force design process, looking at the capabilities that we want to commit to. Some of those will be from the programme of record that we already have, as set out in this document, but we also want to reflect some of the new challenges and the learning set out in our defence command paper last summer, partly through lessons from Ukraine and partly around the pace of technological change.
Q15 Chair: We are going to touch on capabilities in more detail in a moment. You have the gap in the equipment plan. You are saying you are going to wait until the spending review before making decisions about the 2.5%. Whether or not that happens, you are waiting. In the meantime, there are no real plans to cut projects and, if there are any that are not really going to deliver, they are going to keep costing money. Even if everything else is benign—you get an increase in defence spending, inflation decreases and a few other things work in your favour—there will still be a shortfall. Is there any realistic work going on about cutting or reducing a programme?
David Williams: There is work underway right now, which is really looking at this problem in two parts. First, what are we going to do for the financial year 2024-25, maybe into 2025-26, and, secondly, what are our capability priorities across the 10-year period overall? Those are two somewhat different questions. It may well be that we need to take measures against existing programmes to manage through the first couple of years of that pressure. We have more choice when it comes to the decisions that we make over the 10-year period in terms of contractual commitment, although it starts higher and then tails off. Over the 10-year period, we are currently only about 25% on contract, so there is quite a lot of choice in the later years of the 10-year planning horizon about where we want to invest.
Q16 Chair: So you are deferring the choices about making hard decisions.
David Williams: We are deferring some choices where there are no-regrets decisions. For example, one of the key lessons from Ukraine is that we need to invest more in our munitions stockpiles. We will get on with that in advance of the next spending review. We are doing that already and, no doubt, we can talk a bit about that in this session.
The point is about not stopping things unnecessarily over the next 12 to 18 months, if it turns out that we are going to have funding headroom for it. What that means is quite an important focus on commitment control. As we are going through the approvals and putting new programmes on to contract, there is then a decision about being confident that we want those in the forward programme, come what may, given the budgetary and costing scenarios that we face. If not, we then take a decision on a case-by-case basis about whether it makes most sense to defer that programme.
Q17 Chair: We are going to get into a long answer here. There are lots of words, but we are going to drill down on some of the capability issues a little later. A colleague will be picking up on those. One of the things about this report is that, when it came out, the Department’s public statement did not sound like it agreed with the National Audit Office’s take on this, which is well worked up. Can you just be clear that it is an agreed report?
David Williams: It is an agreed report, and it is based on data that we shared with the National Audit Office. We worked closely with it on the production of the report. The distinction—and it is not a criticism of the NAO work but almost having set it an impossible task—is that we did not publish our own equipment plan this year, because of the uncertainty of how we would deal with inflation and the opportunity to think about new capabilities that we want in light of the defence command plan. That is why I described it as a work in progress. There are a set of issues that we still need to work through.
The NAO analysis is not very different to the approach taken every year. It is a view based on a set of data, which, for us, is still interim. That is really all that I mean. There is more to come.
Q18 Sir Geoffrey Clifton-Brown: I am going to drill down a little further on the Chair’s questioning. You are holding everything in this 10-year defence plan, knowing that it is unaffordable. Is this a deliberate ploy to put pressure on the Treasury to give you that 2.5% more quickly than it would otherwise wish to?
David Williams: No, not directly. The point is simply that, if you are looking to plan with a degree of precision over a 10-year period, it is helpful to know what your budget is. I have certainty about my budget only for the next 15 months before we are into the next spending review, so it is based on a set of assumptions.
Q19 Chair: Was “the next 15 months” a slip of the tongue? The spending review is scheduled for November of this year, we believe.
David Williams: I have budget certainty until the end of March 2025.
Chair: Then the new spending review will kick in. Forgive me. You are right.
David Williams: There will then be a debate for 2025-26. My point is that the Government’s stated position is that, as economic and fiscal circumstances allow, the defence budget is going to increase. The core assumption here does not factor that in. My colleagues may correct me, but the upper scenario for our defence budget assumes growth towards 2.5% from 2027 through to 2032, but that is just an assumption from us.
Q20 Sir Geoffrey Clifton-Brown: The point that the Chair was trying to make is that, without prejudging whether the Chancellor is going to give you that 2.5%, the content of this defence plan is unaffordable. Therefore, the responsible thing to do—and, indeed, any budget holder in any other Department would be widely criticised if they did not do this—would, surely, be to make a priority list and take out those items that were not an absolute priority. Otherwise, you are holding items in there, spending money, planning staff, working out budgets and everything else. You might then have to cancel them much later in the day, which would lead to very poor value for money for some of the other matters that remained in. You would get better value for money if you took out those that were not priorities, would you not?
David Williams: First, depending on the timing of a move to 2.5% of GDP, the plan could well be affordable as currently set out. That definitely does not mean that we are being complacent about managing inflationary pressure where we can. We are going through that process, and General Magowan is leading the process at the moment to review our priorities against not only affordability but the kinds of capability lessons from Ukraine and the ambition that we set out in the defence command paper refresh last summer. We are doing that and, where there is a no-regrets move to either fund or stop, my expectation is that we would enact that quickly. Where it is something that makes sense to view in the round alongside a spending review process, those are decisions that we will take when we get into that cross-Government resource allocation event.
Q21 Sir Geoffrey Clifton-Brown: I am going to switch to you, Mr Wipperman. Good afternoon. We have limited time, so shortish answers would be really helpful. I want to talk about two aspects of the plan. It says in the NAO report that you are planning to move quite substantially to inflation-linked contracts because of the recent spike in inflation, which is now coming down. What incentive does that give to your defence contractors to keep their costs down if you do that?
Tom Wipperman: The reason why we have moved towards that policy is that, going into this period of high inflation, around 25% of our contracts were firm price, and so the suppliers were taking the inflation risk. As we have moved into very high levels of inflation and very volatile movements in inflation, the cost to us of trying to put that risk on to suppliers has been too great. The value-for-money judgment is that we get better value for money by linking to the appropriate indices—and I am happy to talk about indices in a second—that mean that suppliers are not fully exposed to that risk and that we are doing some risk sharing. Which indices we might use for any particular contract will depend on the nature of what we are buying and the materials that go towards a product.
Q22 Sir Geoffrey Clifton-Brown: One of my colleagues is going to ask about that. On the specific issue of contracts, you did not answer the second bit of my question about what incentive there is on your suppliers to keep their costs down, if you give them a full inflation-linked contract. It puts me in mind—and I am old enough to remember this—of the old cost‑plus contracts, where the MoD was well and truly ripped off by its suppliers because they knew that they could immediately pass every single increase in costs back to the taxpayer.
Tom Wipperman: Mr Start may want to comment on the details of the contracts, because he would be closer than I, but the indices that we would use will set out a set of costs and be independent of any particular behaviours. The indices are to do with market prices and the way that things are moving. Linking it to the contract, whether it is CPI, clothing and textile indices, or RPI, will be an escalator within the contract that we would have agreed.
Q23 Sir Geoffrey Clifton-Brown: Surely, it is in all of our interests to try to keep inflation down. One way to do that is to put pressure on your suppliers, and one way to do that is by an incentivised contract rather than full inflation-linked contract.
Andy Start: If I may, there is a value trade-off to be had around inflation volatility. If the inflation volatility is very high—
Sir Geoffrey Clifton-Brown: It has peaked and is coming down.
Andy Start: It is, but it is still really quite volatile. At this point, that volatility means that, at the moment, on balance, we are better off using indices rather than fixed prices. Once it is stabilised, we will probably wish to go back to fixed prices. It depends on the nature of the individual contract as to the level of incentive to the supplier within the contract. If you are on a target cost incentive fee style contract, there becomes a strong incentive for the contractor to try to keep the cost down. If you are on a more straightforward single-source contract, there is less incentive within the contract.
Conversely, industry knows that the more it spends on a particular contract, the less there is to spend on other things. Its supply chain is not where it wants to spend the money. It wants to spend the money on generating more profit. Driving costs down and making the products that it has more exportable is more attractive, so there is an export incentive, although I would like that incentive to be stronger. That is the other dynamic that sits in this frame. It is not perfect, and every dynamic has a trade-off, but, at the moment, it is very clear to us that, if we try to cost in inflation with the level of volatility, we are just not getting good-value-for-money offers back.
Q24 Sir Geoffrey Clifton-Brown: General, good afternoon. Can I come to you, please, on a completely different aspect? This is on how your top-level budget holders approach their budgets. Some approach it on a completely different basis to others. For example, the RAF and the Navy have unaffordable plans, because they include full predictive costs for the capabilities that Government expect them to deliver, while others, such as the Army and the strategic programmes directorate, have developed affordable plans by accepting greater risks that their capabilities will not meet Government’s objectives. Does that make any sense? Surely, they should all do their budgets on the same basis. Otherwise, you cannot compare apples with apples. You are comparing apples with pears.
Lt General Sir Robert Magowan: On the financial machinery, I will hand to Mr Wipperman. From the perspective of capability and the risk that we carry, it does not make any difference to me, because I can see what capabilities we need in each domain or across domains—multidomain, as we say—and whether that is costed in the programme. I compare that against the risk register that I hold, so how they report it and whether it is within or without their costed programme is not going to deflect me from understanding where the operational risk is. The machinery of the process is more in Mr Wipperman’s space.
Sir Geoffrey Clifton-Brown: I probably asked the question to the wrong person. I apologise.
Tom Wipperman: To build on what the general said, the first thing that we would really want to be clear on is that we are not saying to TLBs that they can go off and do whatever they want in terms of the way they build up their budgets and plan. Through the planning round, we set them a clear set of instructions about what they need to do. We set them clear parameters—for example, the inflation, forex or pay rates that they need to use. They have to build that within their equipment plan and the rest of their budget to make sure that there is consistency.
Where we see a difference is between the TLBs that put the cost of some projects that are within policy or within ambition in their plan and those that do not. Going back to what the Permanent Secretary said a short while ago, the plan represents a snapshot of a period in time and the capabilities that the Army knows it needs to develop came out through the DCPR work, which was undertaken after this plan closed on 31 March. Through the early part of this financial year, as we finalise the DCPR, we are now working through how we bring some of those capabilities and choices into the plan and the sorts of trade-offs that we might need to make elsewhere.
Q25 Sir Geoffrey Clifton-Brown: Does it really? If they are doing it on a different basis, some are including the risks and some are not. How can that be fair? If I were CDS, I would be pretty miffed that others were doing it on a different basis to me and I would say, “If they are doing it on a different basis, I am going to do it on a different basis”.
Tom Wipperman: As the general said, we see clearly in their plans, which come back to us, the balance of financial and capability risk that they take. They are able to make different judgments within their own budgets and plans of the extent to which they want to balance those. We do not just accept what comes back to us. We are working closely with the general’s teams to say, “Are we comfortable that that balance of risk between each TLB is correct?” In some places, we might say that we want them to take less capability risk. In others, we might want them to take financial risk. It depends on the nature of the suppliers and of the contracts that they run, and whether they have flexibility.
Q26 Chair: Could you give a precise example of each of the scenarios—one where there is more capability risk and one where there is more financial risk? We have really puzzled over why this was. When I first saw this last autumn, I could not understand it, and I still do not.
Lt General Sir Robert Magowan: I will leave the machinery to Mr Wipperman. To your point, Chair, about examples, one would be between the Navy and the Army. There are elements in the plan—and we can go through those—with regard to the shipbuilding pipeline into the 2030s that are not funded and so are a pressure within the Navy. As I have discussed at various Committees, the so-called four plus one, which we can go into, sits above the line in the Army as something that is not funded, but it is outside their EP.
When I look at that, there is no advantage to the Navy or the Army as to whether it is above or below the line. I know that we have to commit more to our shipbuilding pipeline into the 2030s, and we know that we have to treat some of these operational risks that we are learning from Ukraine and the so-called four plus one in the Army. The deliberation of where we are going to make decisions and where we are going to hold operational risk is not manifest in terms of the decisions that we make.
David Williams: For me, it is partly a function of timing. As Mr Wipperman said, quite a lot of the conversations about the Army increases were discussions that we worked through after we drew a line under this equipment plan in the context of our offering into the new NATO force model—what our contribution was going to be to the strategic reserve, rapid reaction forces, regional plans and so on. There is a debate now to be had about whether the Army is funding them from within its existing programme or whether that will be money allocated to it by us.
The challenge here is partly that it is about a set of risk judgments as to where you hold the balance of capability, financial and, indeed, delivery risk in a delegated system. That is something that we are looking at as part of our review of procurement and of the operating model. It is partly about the extent to which, in that delegated model, frontline commands in particular have the authority to make changes, or whether they need to refer back to us through processes that General Rob runs.
I have absolutely no problem in accepting the recommendation from the NAO that we should try to make this more consistent. Although we can see the line, it is an additional challenge for us, which, all things being equal, I would rather we did not have, and it does make it quite difficult for you to hold us to account.
Q27 Sir Geoffrey Clifton-Brown: You have anticipated my next question. As professionals, you may well understand why it is done on a different basis, but, in terms of transparency to the general public, surely it ought to be done on a consistent basis.
David Williams: It would clearly make our equipment plan easier to interpret. As we think about how we reshape publication of equipment plan data for the future, views not only from the NAO but from this Committee will be most welcome. There is a question for us, notwithstanding where, formally, the numbers come out at the end of a planning round, as to whether we want to present it on a standardised basis, even if we would have to think about how we work our internal data with the NAO.
Q28 Sir Geoffrey Clifton-Brown: That is long answer but you have given us a good hint for a recommendation.
David Williams: I think it is a yes.
Q29 Chair: It is just worth pointing out that paragraph 1.12 on page 19 in the NAO report highlights the Army’s approach. This why I was and still am puzzled, and I am heartened that you are saying that it would be good to get the same baseline. If that approach was taken, the estimate is that it would be around £12 billion more to fully provide the capabilities, which is potentially an added shortfall.
David Williams: Some of that includes investment in ammunition stocks, for which we have said in the DCP that we will allocate another £2.5 billion. It is not all for the Army, but quite a lot of it will go in that direction. Some of it will be programmes that the Army will want to fund by prioritising new investment over old.
Q30 Chair: To be fair, ammunitions are to be delivered in the short term.
David Williams: We want to get to the situation of an always-on production line on munitions, so that we can surge when we need to.
Q31 Chair: My point is that it is quicker to deliver munitions than a new aircraft carrier.
Lt General Sir Robert Magowan: Not necessarily. The whole point of munitions is not what you just said, Chair, if I may say. It is about a long-term commitment to industry. We are learning, through operational lessons and not just from Ukraine, that we need a stronger industrial base. Some, but not all, of those areas will need some time to get to a level of production that is suitable for the ability to deter state-on-state conflict.
Q32 Chair: So we are not talking about just a few years; we are talking about a decade.
Lt General Sir Robert Magowan: In some cases, we can go quite quickly. Mr Start is much more of an expert than I am in facing industry. For others, it is going to take a period of time, but that is the business that we are in. We are in long-term commitment, long-term resilience and long-term deterrence.
Chair: We are beginning to get flesh on the bones of the picture.
Q33 Mr Francois: Mr Williams, I have a general question that is very germane to this. The Secretary of State recently gave evidence to the Defence Committee, where he presaged a major announcement within the next few months on big changes to the way that we procure military equipment. As you know, you and the Defence Committee have had certain discussions on this. Can you give us a date for when that announcement is likely to be made? Can you promise us that it will be made to Parliament first and that we will not read about it on the newswires, not least because the Speaker is at about the limits of his tolerance on this? When can we expect this major new announcement about procurement reform? If you cannot answer that, maybe Mr Start can.
David Williams: There is always a set of grid and parliamentary business processes to work through. As you know, normally when I give the Committee dates, they turn out not to be right. We are targeting an announcement before Easter.
Chair: We recognise that it is not entirely in your hands. We do understand that.
Q34 Mr Francois: That is good, because the House rises on 26 March and is due back a little after that, but then we are in April and in purdah for the elections and all the rest of it. If it is not by then, you are probably talking about mid-May, realistically. We understand grid management. Can you just give us your commitment—and we respect you, David—that you will do your very best, subject to those extraneous factors, to have it made before we rise for the Easter recess on 26 March?
David Williams: We are collectively being driven by the defence ministerial team for the work to be ready in that kind of timeframe.
Q35 Mr Francois: That is as far as we can ask you to go. That is very good. Thank you very much. Moving on to some programme specifics, let us look at the Royal Navy. There have been many press reports that Type 23 frigates HMS Westminster and HMS Argyll, which have gone into refit, will not come back out, which would take us down to 15 available frigates and destroyers as opposed to the current number of 17 and what was, for very many years, a number of 19. Will Westminster and Argyll come back into active service from refit?
Lt General Sir Robert Magowan: The Secretary of State has not yet decided on those two particular vessels. We are in negotiation with the Navy so that we can provide the advice to the Secretary of State. He has not yet announced what is going to happen to Westminster and Argyll.
Q36 Mr Francois: But you cannot tell us for definite that they are coming back. It is subject to final approval, one way or another, by the Secretary of State. It is, metaphorically, on his desk.
Lt General Sir Robert Magowan: Yes, exactly what you have just said, Mr Francois.
Q37 Mr Francois: We know what that means, so we are down to 15. For the Type 31 programme and the Venturer class, is initial operating capability still late 2027?
Lt General Sir Robert Magowan: Yes, 2027.
Q38 Mr Francois: For the Type 26 and HMS Glasgow, initial operating capability is still October 2028.
Lt General Sir Robert Magowan: That is correct.
Q39 Mr Francois: So we are going to have to run the gauntlet of this gap for the best part of another three years, nearly four, when, even on a good day, we may have only 15 escorts available when you knock off the ones that are in refit or deep maintenance. In the Defence Committee’s public session, we asked the First Sea Lord, “How many escorts, including those already on active service, could you put to sea to fight tonight?” He said eight and a half. As he is the First Sea Lord, I presume that you agree with that figure.
Lt General Sir Robert Magowan: I will agree. On your first point, you made an assumption about Westminster and Argyll, and we will have to wait and see what the Secretary of State’s decision is on those two.
Q40 Mr Francois: I understand that, but what I am saying is that you have not contradicted me, so we will make that the working assumption for this afternoon. That is eight and a half escorts that the Royal Navy could put to sea. How on earth can we deter Vladimir Putin with eight and a half escorts, when the destroyers’ power packs do not work very well and the Type 23 frigates are so old that they keep failing their MOT? Who are we kidding here?
Lt General Sir Robert Magowan: First of all, the high watermark of 13 Type 23 and six Type 45 does not translate to 19 escorts at what we call readiness level 0. You know, Mr Francois, that the system does not work like that.
Q41 Mr Francois: Yes. Would that it did.
Lt General Sir Robert Magowan: That is the first point. Secondly, the United Kingdom is not facing down the Russian navy by itself. It is there to deter our adversaries along with an alliance called NATO. Thirdly, we accept that the Type 23s are coming to the end of their life, although some of them will be in service through to the 2030s, which is precisely why you have just given the dates.
Q42 Mr Francois: How has this situation been allowed to develop? The Type 26 has slipped again and again. The cost of that one-year extension in time to the taxpayer is nearly £250 million. How old the Type 23s are is not a state secret. It is like that car that you keep putting through for an MOT and, every year, it gets more expensive. Why have we allowed the Type 26 programme to slip to the point where it takes 11 years to build a frigate, when some other nations can build the equivalent in three? How did that happen?
Andy Start: First, we have to be careful with comparisons. I think that the example you are picking is Japan, which has got down to a three-year build cycle, but we should get down to a three-year build cycle with Type 31 as we come to the back end of the Type 31 build process. Type 26 is an absolutely top-end capability. It is pushing the boundaries of what has been done before in order to provide us with an asset that is as capable as possible to make it. That has had real technical issues in developing the ship.
The good news on Type 26 is that we now appear to have a stable programme. They are making decent progress. I am pleased to see the investment in the build hall. I was up there just before Christmas, and progress on the first ship is starting to really come on. It is disappointing that it takes that long, but the comparisons are not exactly like for like and, as I said, when we get to the back end of the Type 31 programme, we should be at that three-to-four-year build time.
Q43 Mr Francois: To save time, the Type 26 is a world beater. We have exported it to Australia and Canada. In terms of the prosperity agenda, this is fantastic. The ship is so good that we are anxious to get it into service sooner rather than later. That is why we are beating you up about it a bit: we do not want to wait any longer than we have to for a world beating ship.
Let us move on to Fort Victoria. If the carrier sails, it needs a support ship to carry some of its stores. The last one we have that can do that is Fort Victoria, which is nearly 30 years old. We have a competition to build some new ones. That has been delayed and delayed, so they are years away. If the carrier now sails without Fort Victoria, we have to beg, steal and borrow a support ship from another ally. We have spent £10 billion, including the aircraft, on a “sovereign” carrier capability that now hangs on borrowing a support ship from another nation. Why did Fort Victoria not sail? Was it because she is not technically ready to put to sea, or you cannot crew her?
Lt General Sir Robert Magowan: Fort Victoria is going through a scheduled maintenance period. We have the Tide class. They are oilers, but they have the capacity to support a carrier task group in addition to providing it with fuel across the range of logistics support that a carrier task group needs. That is why we are accelerating the FSS programme. You are right that it has had some difficulties, but we are on schedule.
Q44 Mr Francois: What is the IOC for that?
Lt General Sir Robert Magowan: It is 2029 for the first phase.
Q45 Mr Francois: Very quickly, yet again, General, we have a situation where we have a critical and very expensive capability—for the record, my father was in the Royal Navy and I am as pro carrier as you are going to find—that hangs on some extremely old warships, because the new warships to replace them are running years late. There is definitely a pattern here, is there not?
Lt General Sir Robert Magowan: I agree.
Q46 Mr Francois: So why not do something about it?
Lt General Sir Robert Magowan: We are. That is why we have commissioned Type 31, Type 26 and FSS. That is why we are commissioning MRSS. We know that many, although not all, of our current maritime platform capabilities are coming to the end of their life. You are articulating the recapitalisation programme of our fleet. That is precisely why we are doing it. Are there some delays in some of those programmes? Yes, there are. We accept that, and that is why we are doing all that we can.
Q47 Mr Francois: Forgive me, but we do not accept that. That is why we are here. I have two more quick questions and then I will come back to the Chair. For the LPDs or amphibious assault ships, the out-of-service date for Albion and Bulwark is 2034.
Lt General Sir Robert Magowan: It is 2032.
Mr Francois: It was 2034 in the PQ that I got the other day, but, if I am wrong, I will buy you a drink. I thought that it was 2034. We will argue about that later.
Chair: We will take the general’s date.
Q48 Mr Francois: Is the reason that they now seem to be in play because they are old—they still have nearly the best part of a decade left, whichever one of the two of us you believe—or is it because you cannot crew them?
Lt General Sir Robert Magowan: If we go back to the Westminster/Argyll conversation, the Secretary of State has not made a decision about the future of Albion and Bulwark at the moment.
Q49 Mr Francois: My question is why it is even an issue.
Lt General Sir Robert Magowan: At the very start of this Committee conversation, we accepted that we have workforce issues across the Armed Forces. Therefore, we need to look at the totality of those pressures when we look to start to crew some of these new capabilities that you have talked about.
Q50 Mr Francois: So it is workforce issues and crewing.
Lt General Sir Robert Magowan: Crewing is definitely an issue within the Royal Navy. We accept that. As to whether that is the driver for whatever decision the Secretary of State makes with regards to the two LPDs, there are a range of issues associated with that.
Q51 Mr Francois: I realise that you are sitting here in lovat green, so it is a difficult question, but thank you. Lastly, on SSNs or attack submarines, we will not talk about the deterrent in open session, but it is widely known and reported on all sorts of websites that, a few months ago, we did not have a single attack submarine at sea, because they were spotted all tied up either in Faslane or in Devonport. That has not happened for, crikey, half a century. Why did we not have a single attack submarine at sea?
Lt General Sir Robert Magowan: I am not going to get into the detail of the operational readiness of our SSN fleet.
Q52 Mr Francois: Just give us a rough idea.
Lt General Sir Robert Magowan: We are quite clear on the numbers. We have one Trafalgar class left, and we have four at sea, with a fifth Astute class soon.
Q53 Mr Francois: With respect, there was no operational readiness. That is the point. They were all tied up.
Lt General Sir Robert Magowan: The operational availability of these platforms and, in fact, the totality of their capability change on a weekly, monthly and yearly basis, depending on what the operational tasking is. I do not think that you would expect me to sit here and give a detailed account of the operational readiness of our SSNs.
Q54 Mr Francois: General, I am very proud to have had a father at D-Day on a minesweeper. Across the Navy, it is the most godawful mess at the moment, is it not? We have just been through class by class. It is a mess, is it not?
Lt General Sir Robert Magowan: I would disagree. There is no doubt that we have we have workforce pressures, as the Permanent Secretary has said, including in the Navy, but, as the Secretary of State made clear yesterday and in his speech last week, we are about to launch Steadfast Defender, which sees something like 40% of the total commitment of that exercise across the alliance coming from United Kingdom Armed Forces, including the Royal Navy and a carrier task group.
Mr Francois: I will meet you halfway. You said, “We have workforce pressures”, which comes right back to where we started. They are leaving at three times the rate that we can replace them. The workforce pressures are more important than any programmatic that I have just mentioned. If there is no crew, no ship goes to sea.
Q55 Mr Djanogly: Inflation has been covered, but we have also been talking about costing uncertainty. I am looking at paragraph 1.27 in the NAO Report, which says, “The MoD reflects this uncertainty by recording and monitoring two levels of risk”. The first is “risk inside cost (RIC), which is risk that the MoD judges will probably occur and so includes it in its forecast costs”. It then goes on to say, “RIC has increased from £13.2 billion in last year’s plan (5% of forecast costs) to £22.8 billion this year (8% of forecast costs)”. Mr Wipperman, what proportion of the RIC is inflation?
Tom Wipperman: I would not be able to say explicitly how much of that risk increase is just to do with inflation. The risk inside costing is available to projects within their specific budget to deal with problems or challenges that might emerge as they go through their programme. Some will reflect inflation for those projects that see that as a risk. Some will be other risks. The reason why it has gone up is partly a reflection, as the NAO points out, that we have a growing budget—and you would expect it to grow—but it is also a recognition by us and by projects that we have been in a more volatile economic context. As a result, the level of provision available to projects should go up. That is why you see an increase. As I said, some of it will be for inflation, and some for other risks and issues that we are dealing with.
Q56 Mr Djanogly: But you cannot break those figures down.
Andy Start: I cannot. I can break down inflation overall and where we are seeing inflation rises. We are seeing inflation in the equipment plan of about £11 billion. On top of that, we have about £2 billion of fuel and forex. While that does not directly translate into the risk, that is additional cost pressure that we are seeing through the plan. Outside the equipment plan, we have about another £5 billion of inflation forecast risk, which is to do with utilities and energy costs, and the cost of maintenance in the estate, as well as about £6 billion to do with the consequences of the consolidated pay awards. In big handfuls, it is equipment and materials, infrastructure, utilities and energy costs, forex and pay.
Q57 Mr Djanogly: That is helpful. That is what I wanted. You said that it has gone up. It has gone up by 63%, which is rather significant. Do you currently expect a similar increase this year, given that inflation is coming down?
Tom Wipperman: We are in the process right now of putting together the planning round for this year. We are analysing returns from TLBs to see how costs are playing through to them. In this plan in front of you, on top of that risk provision, we are holding £4 billion of contingency available across the plan as a whole, which is not allocated to any project and is available to us to deploy, should further issues occur.
Q58 Mr Djanogly: What do you mean when you say that you are working it out again at the moment?
Tom Wipperman: That is for this year’s plan.
Q59 Mr Djanogly: At what point do you draw sticks on the inflation figure?
Tom Wipperman: Probably towards mid-February, given the way our planning works, we will need to take a snapshot and say that that is the point at which we take a view. We do that for other variables as well, such as forex.
Q60 Sarah Owen: General Magowan, what are the capability consequences for our Armed Forces of the plan being unaffordable?
Lt General Sir Robert Magowan: As I have said to Committees before, it is about balancing the risk against the budget that we are given.
Q61 Sarah Owen: What is that risk?
Lt General Sir Robert Magowan: The financial risk?
Sarah Owen: No, your capability risk.
Lt General Sir Robert Magowan: I have mentioned the operational capability risks publicly before. Those areas where, if I gave you my top four or five, we know that we need to invest more are lessons from not just Ukraine but operations that we are seeing unfolding around the world.
If I were allowed to say only one thing, it would be straight lethality, which the Permanent Secretary has already mentioned. You cannot deter major state-on-state conflict if you cannot prove that you can close with and kill the enemy. To do, that you need lethality, so we need greater munitions stockpiles. Related to that, we need a strong industrial base to be able to produce that, which is a sovereign capability. That would probably be my number one.
If I were allowed another two or three in answering your question—but we are balancing these—it is clear that the battlespace of today and tomorrow is such that there are a lot of things flying through the air and trying to do us harm. Therefore, we need the ability to deliver what we call IAMD—or integrated air missile defence. We have a missile defence capability within the UK Armed Forces and within NATO, but we all agree across NATO that it needs to be deeper and broader.
Q62 Sarah Owen: How confident are you that those three priorities that you have set out are going to be included in what Mr Williams puts forward to Ministers and what will actually be delivered?
Lt General Sir Robert Magowan: This is a fundamental question. The point here is that we must demonstrate that the programme of record—and both Mr Wipperman and the Permanent Secretary have made it clear that there are uncommitted elements within the programme of record out to 10 years—is not fixed from now until 2034 as far as our budget is concerned. Therefore, we have to be flexible in identifying those areas that are uncommitted and whether they are a higher or lower priority than the areas that I have just articulated, and there are probably a couple of others.
As I have said here before, from a military capability perspective, we will have to make hard-edged decisions about deleting, de-scoping or potentially deferring—we will see—to ensure that there is headroom to get after the things that we have just been talking about, and we will do that.
Q63 Sarah Owen: Given the international developments that you just alluded to in North Korea, Ukraine, China and the Middle East, do the Armed Forces currently have what they need to meet those demands?
Lt General Sir Robert Magowan: Yes. This is state-on-state deterrence. We are part of a broad alliance, and my firm judgment and those of my seniors is that we are deterring state-on-state conflict. NATO is not at war. It is deterring state-on-state conflict, and we are part of that. Does that mean that we are not carrying any operational risk? Does that mean that we not do not need to adjust the programme of record to meet those operational risks? No, absolutely not. There are things that we are going to need to invest in. Are we deterring today? Yes, we are. If we need to go to war tonight, we can.
Q64 Sarah Owen: Earlier in the Committee, you said that we need to be ready for changes. Are we ready for those changes? Do we have enough resilience built into the system currently to deal with those international developments that we just spoke about?
Lt General Sir Robert Magowan: Yes, we do, and that is our challenge.
Q65 Sarah Owen: In terms of the plan, as you had alluded to, we said that not all of the cost pressures that are developed into the new capabilities are costed. Mr Williams, why do you not know how much it would cost to deliver all the capabilities set out in the refreshed defence command paper?
David Williams: I think that you are referring to a list at table 5 in the report. Some of the items on that list generally refer to areas where there are choices about what we might do. We have not yet decided, for instance, whether we go for a midlife upgrade of the Meteor long-range air-to-air missile and precisely what that means. The scope of any work is still a decision that we need to make. There are examples where there are decisions still to come.
There are examples where we have funded early-stage feasibility and development work, but are still to make a decision on the scale and timing of production. There are programmes where we are working with international partners, so the level of funding that they might bring to a programme is still in negotiation.
To the general point earlier—I will probably make the same offer as I did to Sir Geoffrey Clifton-Brown—in our internal view of the programme, we have a good sense of those kinds of decisions that are coming down the track. Over a 10-year period, we expect to have more headroom and choice in the budget in the back end of the programme, so we are thinking about how we can bring those in at the appropriate time, but I accept that it is not necessarily the most transparent part of our planning process in the documentation or the data that we set out.
Q66 Sarah Owen: No, I would say it is as clear as mud. In terms of the 2.5% increase in defence spending, what happens if that gamble of yours does not pay off and you do not receive that before you need it to complete some of these programmes? Coming back to one of the points that you made earlier, you said, “How do we set a programme without knowing how much money we have?” Why do you not help the people setting the budget by telling them what your priorities are?
David Williams: It is not a gamble. It is stated Government policy to increase the defence budget to 2.5% of GDP as economic conditions allow.
Q67 Sarah Owen: That is like when I ask my mum, “When is dinner going to be ready?” and she says, “How long is a piece of string?” If you cannot give us a guaranteed time, or at least a timescale, for this increase in budget, how can you be certain that you are going to be able to deliver the programmes that you need to deliver?
David Williams: To use your analogy, in quite a lot of the conversations that we have with the Treasury, as you might imagine, we are explaining that we are quite hungry now. In the end, it is a matter for the Prime Minister and for the Chancellor, and those are decisions about spending priorities for Government that are properly made in a spending review. Were the Government to change that and to come off 2.5% as their funding ambition, there would need to be conversations about the level of capability that we could buy for the budget that they then agree.
Q68 Sarah Owen: How much wriggle room do you have if the spending review were to be delayed, say, for a general election?
David Williams: We are working through some short-term pressure, as I said at the beginning. Last week in the House, the Prime Minister suggested that the spending review might be in 2025 rather than in late 2024, but we are talking about six months or so here or there.
Q69 Chair: Just to be clear for people who might be tuning in, if there were a general election in the autumn, there could not be a spending review at that point. If whatever Government were elected would like to have a budget shortly after a general election, the next spending review is typically around six months after a budget. Is that the sort of thinking that you are going through in the Ministry of Defence?
David Williams: There needs to be a local government financial settlement by December of each year.
Q70 Chair: There have been previous examples not that long ago of rolling over an existing spending review by just carrying it on.
David Williams: What I am particularly interested in is when we get to the point of a multi-year settlement, and that may well be at a period of time after a general election.
Q71 Chair: So you are expecting to get to a multi-year settlement.
David Williams: We had a multi-year settlement at the last spending review and, for defence, that makes sense.
Q72 Chair: Just to be clear, you are planning on that basis.
David Williams: Yes.
Lt General Sir Robert Magowan: Our overall priorities are articulated in the defence command paper refresh. We have said that, and we now need to go into a level of detail beneath that, but we have articulated those. From a military capability perspective, we need a long-term settlement. We need a five-year settlement to give us the confidence, particularly with industry, to get after that long-term deterrence that I have been talking about. We cannot live year on year.
Q73 Sarah Owen: Absolutely, I completely understand that, but what you are asking for is completely unfunded at the moment.
David Williams: It is not that it is completely unfunded, because we make a set of reasonable assumptions about how the budget might develop beyond the spending review period. Even on a multi-year settlement, there are going to be two or maybe three spending reviews over the period that we are looking at. In the separate information that I sent to the Committee, we set out a central assumption around the overall budget, a downside assumption and an upside assumption. They are simply that—assumptions. We are not looking for a completely blank sheet of paper, but the precise settlement is to be decided.
Q74 Sarah Owen: But there is a blank space of £12 billion within that.
David Williams: It depends very heavily on assumptions about the budget and the content of the programme, what that programme costs and how we need to deliver it.
Chair: That is a long way of saying that, at the moment, you want to do more than you have money for, which is why we are here today.
Q75 Mrs Drummond: You said that you wanted a five-year contract so that you could give security to suppliers for the programmes, but should they not be taking the risk, rather than the Government?
David Williams: Mr Start may want to come in on that, and maybe I will come back.
Andy Start: Companies can reasonably take risk when they have a reasonable chance of an economic return. The challenge that we have at the moment is that there is incredible volatility in the nature of the threat. In the Ukraine conflict at the moment, we are seeing technological changes within a 90-day period. That means that, for the equipment that we think we need, we make our best guess now, but we need to be very adaptable and change it. The risk of that becomes a military rather than a commercial one.
If you are sitting in industry, you can take sensible risk-based decisions around skills. We are seeing that with very substantial investment in skills by the likes of BAE Systems, Babcock and others in terms of building underlying capability, but it is very hard to make firm decisions around production capacity or particular products.
That is exacerbated by the fact that, in the defence market, which is not a regular consumer market but one that is heavily influenced by Government policies in different countries, you can sell only when there is aligned Government support for the products that you need in terms of exports. It is not a natural market, and making a strategic investment choice is extremely difficult for industry to do without Government giving it very clear signals.
In the UK, we try to publish as much of the defence pipeline as we can, and we have been increasingly doing a better job of that. We try to do that by engaging industry early in terms of the requirements, and General Rob has been doing groundbreaking work in terms of involving industry at high levels of classification, so it has a better insight than it would have otherwise. In the NATO context, we are trying to do that through the Conference of National Armaments Directors.
Without Government giving it appropriate guidelines, the industry cannot make long-term commitments, because the chances of it developing something that does not get sold is high.
Q76 Mrs Drummond: Why are we not buying off-the-shelf products from other countries that have already taken this risk, particularly if you need it quickly—as you said, a 90-day one?
Andy Start: All countries have the same underlying dynamic problem. Together with our allies, we have to paint as clear a picture as we can of the future need. Wherever possible, we, as Governments, benefit from having interoperable and interchangeable products with other allies. We benefit from when we develop products together, as we are doing with things like GCAP.
Just buying off the shelf leaves you in a situation where you might benefit in the very short term, but, over the longer term, you do not have the level of sovereign ability to adapt and change the military need. In times of conflict, if you do not have national capability, it is very difficult to adapt at speed.
Our overall acquisition strategy has to be a blend of having onshore capability, so that we have that sovereign independence, economic growth and jobs, but, also for security reasons, a mixture of international partnerships and some things that we would buy off the shelf because it is much more economic to do.
Chair: We will touch more on the industrial strategy side of this shortly.
Q77 Sir Geoffrey Clifton-Brown: Mr Start, I cannot help pondering the answer that you gave to the last question. I might refer you to Ajax, where you would have had a vehicle fully in operation by now if you had bought off the shelf, but we are not going to go there.
Mr Williams, going back to my earlier question, we have been over and over the nuclear enterprise funding gap in the budget of £7.9 billion and the total budget gap of £16.9 billion. How are we going to close that gap?
David Williams: Yes, so £7.9 billion of the £16.9 billion is currently showing against the nuclear enterprise. Our initial experience within the nuclear ringfence that we have been operating this year is that our first set of cost estimations have been about right. We will deliver within that budget without deliberately having had to slow programmes down.
Part of the way in which we manage that cost pressure will be through the exceptional flexibilities that we have agreed with the Treasury for the nuclear ring-fence, which will allow us both to commit spend at pace through more streamlined approvals processes and to bring money forward and backward to address risk as it begins to crystallise.
It reflects about 7% of the nuclear budget over the 10-year period. At this stage, my expectation is that that level of financial pressure will be broadly manageable.
Q78 Sir Geoffrey Clifton-Brown: I am absolutely certain that the flexibility you have gained from the Treasury is very useful, but how likely is it that in next funding reviews you are going to need to come back and ask for more money for the nuclear enterprise?
David Williams: I cannot rule it out, but part of the reason for the particular increase in this planning round is that we deliberately asked our colleagues working in the nuclear enterprise to make sure that they were being comprehensive and risk-aware in the numbers that they put in.
There are always adjustments up and down, but, in comparison to previous planning rounds, this is a much less financially risky position and a more comprehensive view not only within the Defence Nuclear Organisation but in allied top-level budget areas. Nuclear costs within the Royal Navy and Strategic Command have been included within that ring-fence.
There has been quite a lot of de-risking in this planning round. It is often in the nature of nuclear costs that they can move around, but this is a much healthier position than we have been in for a number of years, in my view.
Q79 Sir Geoffrey Clifton-Brown: “We are in a much healthier position than we have been in for a number of years”. That is a really interesting statement.
Mr Wipperman, given that the nuclear enterprise budget is consuming such a large proportion of the total budget, how likely is it that, in order to fund it, you are going to have to further cut conventional weapons over the next 10 years?
Tom Wipperman: The answer to that partly goes back to what the Permanent Secretary has been saying about potential future funding scenarios. The letter that the Permanent Secretary sent to the Committee set out some of those scenarios. In one of those scenarios, the funding for nuclear that we receive from the Treasury continues. That leaves you with this £7.9 billion, which, as we have set out, we think is manageable over a £100 billion 10-year budget.
Q80 Sir Geoffrey Clifton-Brown: That is predicated on, as Ms Owen says, the Treasury granting you this extra 2.5% of GDP. If you do not get that, does that answer still stand?
Tom Wipperman: I was going to go on to say that in the lower-bound scenarios that we set out, where we have a lower budget than we might currently forecast, we would have to work with Ministers about the sorts of choices available to them and where they would want to balance capabilities.
David Williams: Just to be clear, in the central budget scenario, which generates the £7.9 billion, we have made no assumption about progress to the 2.5% as a policy choice. That is in our upside budget scenario.
Tom Wipperman: Yes.
Q81 Sir Geoffrey Clifton-Brown: It does assume that £7.9 billion.
David Williams: Yes.
Tom Wipperman: Yes, it does.
Q82 Sir Geoffrey Clifton-Brown: Otherwise you will be left with a scenario where you will have to cut conventional spending, if you do not get that 2.5% of GDP expenditure.
David Williams: Yes, if the nuclear enterprise is unable to manage the costs within the funding envelope that we expect to give it, and if at that point we choose to find savings in the non-nuclear side of the programme rather than deliver nuclear within the ring-fence. There are some variables there.
Q83 Sir Geoffrey Clifton-Brown: That is understood. Mr Wipperman, very briefly because time is moving on, what capacity did the delivery agency and industry have to deliver the nuclear programme more quickly and therefore help save costs?
Tom Wipperman: Mr Start might be better placed on some of the industry, but, in terms of how we put together the plan, the forecast is based on the defence nuclear enterprise, the Defence Nuclear Organisation and the associated elements giving their judgment working with industry about its ability to deliver.
At the spring Budget this time, in March 2023, we received an extra £3 billion spend for nuclear, £1 billion for this year and £2 billion for next. We currently forecast that we are on track to spend that extra funding and to get that out through the supply chain. We did a lot of work with the DNO to get an assessment of realistic spend profiles. Currently, we think we will be able to deliver, but Mr Start may be better placed to talk about it more broadly.
David Williams: If I can come in first, last year Ministers announced a nuclear skills taskforce looking at both defence and civil nuclear skills requirements in the round. Our assumptions going into that work, based on some earlier internal reviews, have been that across the defence nuclear enterprise over the course of around a 10-year period we will probably need an extra 10,000 or so apprentices, graduate engineers and so on to deliver on the totality of the defence nuclear ambition.
That skills taskforce made good progress over the back end of last year. A report will shortly be with Ministers for them to consider. The announcement on that will get to the heart of your question.
Q84 Sir Geoffrey Clifton-Brown: This question is either to you, Mr Williams, or to Mr Start. We have talked about speeding up the defence nuclear enterprise to save money. Does the same argument still apply to the conventional weapons budget—that, if you could speed up some of the programmes, you would be able to save money and make the programme more affordable?
David Williams: Yes. Both in hearings here and in the Defence Sub-Committee that Mr Francois chaired, there was a renewed and welcome emphasis on pace. That will be a key feature of the announcements by Ministers around our new procurement model. In a world of high inflation, delivering more quickly, or at least delivering on time, avoids inflationary cost pressures.
In the kind of uncertain world that we are in—we have talked in the defence command paper about sprinting to a 70% or 80% capability and then spiralling—getting usable capability into the hands of the warfighter more quickly is the capability ambition. That is the most important piece. It has the advantage of probably allowing you to deliver it more cheaply.
Q85 Sir Geoffrey Clifton-Brown: Can you give us an exemplar—it will probably be one of those green projects in the GMPP—of a project that is well ahead of schedule at the moment and that you are proud of?
David Williams: We only have one green project in the GMPP. No, we have two. I do not know whether General Rob wants to comment.
Lt General Sir Robert Magowan: Can I take it from the other angle? We accept the challenge that, with all the programmes here, in quarter 3, 11 of them are at red. Half of those are in the areas that you have just been talking about, so complex weapons or the nuclear enterprise.
To support what the Permanent Secretary said, there are a range of reasons for that.
Q86 Sir Geoffrey Clifton-Brown: I was not really going into those. I just wanted one exemplar of which you are proud that it is being delivered on time or even ahead of budget.
Lt General Sir Robert Magowan: A number of the Air Force programmes are developing well. We have had F-35B success.
Q87 Sir Geoffrey Clifton-Brown: That was a conventionally established programme.
Lt General Sir Robert Magowan: Yes, but you are asking for a major programme, a cat A programme, that is delivering to cost and time. We are rolling that out. We now have the second squadron up and running. We will have 48 F-35Bs certainly delivered from 2025. We are looking to grow that to 74. There is an example of a programme that is delivering operational capability today.
Andy Start: Sir Geoffrey, if you look at some of the things we have done for Ukraine, we have tried to take these opportunities around acceleration that we are trying to build into the longer-term system. We have then been able to be very successful in delivering a lot of capability very quickly.
An example is the acquisition of Archer, where we replenished using an existing off-the-shelf capability at real speed. A second example is the way that we have introduced the use of both armed and unarmed drones, taking technology from concept through to operation in weeks and months rather than years and decades. There are some really exciting opportunities that we have demonstrated in that space.
We are trying to roll out that kind of approach, where we take more operational risk, get our capabilities out more quickly and then spiral up. We are doing that in the conventional weapons space, in particular in munitions. In the munitions space, we rolled out capabilities to protect our warships, equipping Lynx with a capability early for both FASGW-light and FASGW-heavy. Those are Martlet and Sea Venom, off the top of my head.
Lt General Sir Robert Magowan: It is Wildcat.
Andy Start: In both cases, we got a capability out quickly and then we spiralled that capability up by increasing its capability over time. That is the approach that we need to use much more widely.
We are also trying to take approaches that are more modular. Within the Boxer programme, similar to the concept of the Type 31 programme, we get out the basic capability that is the underlying platform, and then we can enhance that platform with mission modules and enhanced capabilities over time. That gives us a solid basis but allows us to be flexible and spiral in capabilities more quickly.
Sir Geoffrey Clifton-Brown: We are used to asking critical questions in this Committee, but congratulations. The UK is recognised around the world as having got those capabilities out very quickly.
Q88 Chair: Can I just go back to F-35, General Magowan? We have been following this for some time. We had the aircraft carriers without the aircraft, but we still have issues about the number that we need to have full capability. We are still quite far short of what we need to do. It is a programme that is beginning to deliver, but it is still behind where it ideally ought to be, given that we need those to make the carrier group operate fully and effectively. We also need the crew. That is another area that we have looked at, along with the training for pilots.
Lt General Sir Robert Magowan: Yes, for engineers, rather than pilots.
Q89 Chair: There were also some pilot training issues.
Lt General Sir Robert Magowan: The extra 168 engineers has been the pinch point, which we have now funded. We are now growing those 168.
Q90 Chair: When you say you are growing them, are you training them from within the service?
Lt General Sir Robert Magowan: Yes, so the headmark for us is two squadrons operationally deployed on Carrier Strike Group 25.
Q91 Chair: With two squadrons, if you have any number of aircraft out of commission, you are struggling. You really need three, do you not, to make sure that you have full capability?
Lt General Sir Robert Magowan: The programme of record at the moment is designed to deliver three squadrons. We are rewriting the routine operating model at the moment. It is going to the Secretary of State in the next few weeks and months. There will be a ramp-up from what we originally said back in 2017. Either way, the headmark is for three operational squadrons by the early 2030s, but in the short to medium term there will be two squadrons operationally deployed with a training unit, an OCU, by 2025.
Chair: We are on schedule for that.
Lt General Sir Robert Magowan: Yes, we are.
Q92 Mr Francois: Mr Start, for the record, when the Defence Sub-Committee looked at DNS, as you know, we were critical in a number of areas, but, on the principle of credit where it is due, we gave your organisation a lot of credit for everything you have done for the Ukrainians. Today, by the same token, for the record, it is worth recording in public session that, because your teams worked unbelievably hard, although we cannot quantify the number of Ukrainian lives you have saved, it will probably be in the thousands. Perhaps you will be kind enough to carry back the compliments of this Committee to all of your people at DE&S who pulled out all the stops to do that.
Andy Start: Thank you, Mr Francois. It is much appreciated.
Q93 Mr Francois: That was the good bit. Mr Williams, can I just check something that you said earlier just to make sure we understood what you said?
You have a problem. This is a 10-year plan, but you only know how much public spending that you have going forward three years. That is always a challenge. Am I right that you said from 2027, so the back end of this plan, the second half really, you were using more optimistic financial assumptions—i.e. that by then we will be spending about 2.5% of GDP on defence? Did I understand you correctly?
David Williams: All of the analysis is based on data that we have shared with the NAO. That 16.9% budgetary pressure is based on a central assumption. I have made no assumptions in that about a trajectory to 2.5% of GDP at all.
Mr Francois: You have not.
David Williams: We have an upside budget scenario. This is not based on any agreement with the Treasury. It is a set of assumptions that looks at what a growth of 2.5% of GDP by the end of the 10-year planning period, starting at the end of the next spending review period—let us say 2027-28—would look like.
Q94 Mr Francois: If you get the “optimistic” outcome from your point of view, and mine too by the way, does that deficit disappear?
David Williams: Yes, except that there is obviously a mismatch of profile because that gives you more money in the last five years of the plan.
Q95 Mr Francois: It all fits, though.
David Williams: It fits across the 10-year period.
Q96 Mr Francois: I have one more, very quickly, and then I will go into some specifics. With the £17 billion deficit, what proportion of GDP are we spending on defence in that scenario? In your central assumption, what is your percentage assumption?
Chair: This is to fill the gap.
Mr Francois: Is it 2.2%, 2.25% or 2.3%?
Tom Wipperman: On the current assumptions that are built in this, based on the latest OBR forecast from November, by the end of the decade it will be about 2.1% of GDP.
Q97 Mr Francois: This plan with the £17 billion “black hole”, to use media language, is based on us spending 2.1% of GDP on defence, plus Ukraine.
Tom Wipperman: No, it makes no assumption about the future of Ukraine. This financial year, we are forecasting 2.25% including Ukraine. Next year, we are forecasting 2.26% including Ukraine. We have no agreed funding for Ukraine.
Q98 Mr Francois: All right, I have got that. When the agreed funding runs out, it is based on 2.1%.
Tom Wipperman: No, it will reach 2.1% in year 10 of this plan. It will be a downward trajectory year on year on that current forecast, but you would get to 2.1%, starting at 2.26%. It will be 2.26% in year 2 and 2.1% in year 10.
Q99 Mr Francois: If it were to be 2.5% in an ideal world, that black hole disappears. I have got it. That is very clear.
David Williams: Just taking this year, the difference between 2.25% and 2.5% of GDP is about £6 billion or £7 billion.
Q100 Mr Francois: We get the point that many of the costs are frontloaded. We have got that. That is very helpful. Let us come on to the RAG ratings, the colours, very quickly.
For the benefit of our thousands of viewers abroad, the National Audit Office, which prepared this Report, is Parliament’s auditor, not the Government’s. The Government, since 2012, have had their own auditor called the Infrastructure Projects Authority, or IPA for short, nothing to do with a particular brand of beer. It goes through all the major Government infrastructure programmes, including in defence, and the biggest is Dreadnought. Then it assigns a RAG rating, red, amber or green, to each programme.
We have got into muddles in the past about which colours to use because sometimes you use slightly different colours. We are using the IPA colours, for the avoidance of doubt. It is page 37, paragraph 211. Of the 52 that it looked at, six were classified and so have not been rated, so 46 of the 52 had a rating. Five were red; 35 were amber; and two, only two, were green. Green is defined as, “Successful delivery on time, budget and quality appears highly likely”. By my maths, of the 52, that is barely 4%. That is awful, is it not, Mr Williams?
David Williams: As we have discussed previously, we are absolutely not complacent about the number that are amber. There are a range of technical, commercial and delivery challenges in getting our most major and complex programmes delivered.
The proportion of red, amber and green is not materially out of kilter with the IPA’s reviews of more conventional programmes in terms of infrastructure and construction, Government transformation and IT delivery.
Q101 Mr Francois: Mr Williams, forgive me. We understand that, but we are not going to deter Vladimir Putin with HS2, whether we have the extra leg or not.
Let us come back to this point. The definition of amber—most of them are amber—is, “Delivery appears feasible but significant issues already exist, requiring management attention”. That is still something to worry about. Red, for the record, means, “Successful delivery appears to be unachievable”.
The red projects include the future combat air system, GCAP, Tempest, which is embarrassing, the core production capability for nuclear submarine reactors, which is embarrassing, MODNet Evolve—okay, that is still embarrassing—the Brimstone 3 air-to-surface weapon and the SPEAR cap 3 air-to-air weapon.
We have just signed a treaty with the Japanese and the Italians for the future combat air system, and yet the Government’s own auditor says the programme is red.
Chair: We should just be clear. The IPA is not quite an auditor. I know you are using shorthand, Mr Francois.
David Williams: They are the programme delivery experts in Government.
Mr Francois: Red means, “Successful delivery appears to be unachievable”. We just signed an international treaty with two other nations. That is a bit embarrassing, is it not?
David Williams: Colleagues may want to come in on the detail, particularly General Rob on GCAP. This is about the degree of difficulty in delivering against the planned 2035 in-service date.
There are examples—you will ask me now to give you one, and I will probably have to write to you—of programmes that are rated red, which, as a result of intervention, re-scoping or throwing additional resource at them, you can recover from red to amber.
Q102 Mr Francois: David, I am sorry. I will save you a letter. F-35 was red last year, from memory.
David Williams: Thank you, yes.
Mr Francois: It is now amber. That is right, is it not? There is still a long way to go, as Dame Meg was saying, but F-35 is slowly going in the right direction and not the wrong direction, is it not, General?
Lt General Sir Robert Magowan: Yes, absolutely.
Mr Francois: That is just to prove we were listening to you.
Lt General Sir Robert Magowan: Yes, it does not look good. It is very difficult to talk generically, though. There are 52 programmes in there and there are a range of reasons. We do have to get into the specifics of the programmes, which we can do. I have it all here.
There are some general trends, and the Permanent Secretary has already alluded to one of them, which is SQEP—you used the expression—suitably qualified and experienced personnel. That is true particularly across the nuclear space—there are a number of nuclear reds—and the technical spaces associated with defence, digital and complex weapons.
Some of these are difficult international negotiations, which involve political conversations. That can lead to deliberation. Those would be my top three.
Q103 Mr Francois: General Rob, you have said that it is difficult to generalise, but these have all been examined in great detail by the IPA. It has not generalised; it has scrutinised all of them individually and then given them a RAG rating. In that sense, they are not generalisations.
Even if you take out the classified programmes, there are only two green out of 46, one of which, ironically, is the fleet solid support ship. By my maths, that is still less than 5%. In pub English, barely one in 20 of these procurement programmes is running to time and cost. That is appalling, is it not?
David Williams: They are the 50 most complex things that we are trying to do, so it does not surprise me that at various points in project lives they are not really—
Q104 Mr Francois: Mr Williams, the taxpayer employs you people on a lot more than we are getting in order to make these complex things go right, do they not?
Lt General Sir Robert Magowan: That complexity is the reason why we think P50 is an unsafe assumption.
Chair: Just explain P50. We understand it.
Lt General Sir Robert Magowan: As the Permanent Secretary says, these are the most complex projects. The nuclear ones are probably at the top of the list. We plan on the probability of us hitting our milestones being 50%, on a normal bell curve. Because of the complexity of the nuclear enterprise, and we are trying to get to a point where we are trying to be more realistic, we have now determined that it is better to be at P70.
Q105 Mr Francois: That is good. We wanted P75.
Lt General Sir Robert Magowan: It is P70 for the nuclear enterprise.
Mr Francois: The problem with P50, again in pub English, is that you have half as much chance of being wrong as you have of being right. If I went to buy a car, I would not say to the car dealer, “Is there a P50 chance that it might start when I turn the key?” I would not buy the car.
Q106 Chair: Mr Francois, you have quoted what amber is. Just to be clear, I will give the full definition so that we can get an answer from the witnesses about what they are doing in this respect. The definition of an amber project is, “Successful delivery appears feasible but significant issues already exist, requiring management attention” and then, crucially, “These appear resolvable at this stage and, if addressed promptly, should not present a cost/schedule overrun”. It might be helpful if you could pluck a couple of amber examples and tell us what you are doing to address them promptly so they do not cause a cost or schedule overrun.
Mr Francois: That is footnote 12 on page 37.
Chair: Yes, indeed. Mr Start, perhaps you would respond.
Andy Start: I would be delighted to do so. If I may, I will speak to red briefly. What is helpful about this system is that it allows us as delivery agents to focus on where really senior management attention is needed.
In the case of the couple of reds that are within my portfolio, one of them is red because the supplier has some really difficult technical issues that it is wrestling with. That is making it late. It will get there, but that is making it late. I could take that particular capability to war, if I had to, but I would be doing so with increased risk. I do not want to do that unless I have to. That is red in terms of meeting the obligations that we have set on it, but I can fight with it if I need to.
The other one is red because I am waiting for a capability from an ally that I need to integrate that platform on to. I do not have a date from them yet because they are working on some other things. As a consequence, it is red because we just do not know a critical dependency. That makes it red. When we have resolved that, it will come off red. It is flagged as red because it is not within our control.
If I could take some amber ones, in general, we set pretty aggressive targets on our teams to deliver capability because our military wants capability as quickly as possible and within a timeframe. The targets that we set on the teams themselves are quite aggressive, and therefore I would expect most project managers to say they are struggling to hold the aggressive times that we give them.
The Defence Sub-Committee chaired by Mr Francois made the recommendation that, while we might still task the project teams that way, we should be holding reserves at a higher level and, in particular, doing so on schedule. We have accepted that recommendation and are implementing that across the board. We are moving to hold more contingency in terms of the overall schedules, but we will still drive the teams aggressively because we want to get the capability into the hands of users.
Q107 Chair: You are in charge of that contingency. You are not giving it away easily.
Andy Start: Yes, indeed. That is the key dynamic. If I may, why do we have so many?
Q108 Chair: We asked for examples. Can you give us some examples?
Andy Start: Let me take the example of Boxer. Boxer is currently amber. This is the MIV programme. On the Boxer programme, we are currently just holding the IOC—initial operating capability—dates that we have committed to, but they are under pressure. They are under pressure, as are most of the programmes here, because of issues with supply chain componentry. That is true in the land, sea and air domain and all of my international counterparts are having the same issues.
As we came out of Covid, as industry bounced back, the car industry, the commercial aviation industry and others sucked out a lot of the component capacity as they started to rebuild their industries. Suddenly, we went from a situation where our suppliers were assuming they could buy components in two weeks off the factor market and some of them have gone out to over two years.
That means they are suddenly under real pressure to maintain the schedule because they cannot get the components in the timeframe. That is starting to wash out at the component level and is now sitting at the subsystem and assembly level. Across our suppliers, we are seeing real issues in that space.
The second common issue that is driving all of them to feel pressure at the moment is skills. We have a very hot market globally for these engineering skills. Getting those skills into the defence industry is a real challenge. We need to work that skills issue in nuclear. My predecessor Sir Simon Bollom is working on that in the nuclear space. Through the Defence Suppliers Forum, we are also working with industry to try to get more apprenticeships and with higher education to pull more STEM resources into the defence industry.
Q109 Mr Francois: You made the point about holding that reserve. Presumably, we will hear more about that and you will flesh that out in the statement, hopefully before 26 March.
David Williams: Yes.
Q110 Mr Francois: That is very helpful. My last one is about programmatics. Some of us have tabled a number of parliamentary questions about how many contracts your Department holds with Fujitsu. You have come back and said that that is commercial in confidence, which I have to say is an incredibly weak reply.
If you will not publish how many of those contracts you have—you were also asked about their duration and their contract value—as this is the Public Accounts Committee, would you give an undertaking to provide that information to the Committee in confidence?
David Williams: Yes, in principle. I would need to check that.
Chair: We have previously had access to the entire strategic suppliers information. Admittedly, that was under a humble address of the House.
Mr Francois: You could save us going to all that trouble.
Chair: We may simply approach the Cabinet Office for the whole list.
Q111 Mr Francois: Your in-principle answer is yes.
David Williams: Yes.
Mr Francois: That will do. Thank you very much.
David Williams: I know what the answer is and I do not particularly see any problem with sharing it with you.
Mr Francois: That is very good.
David Williams: Finally, before we move on, having now read last year’s report again, I have one final point. As well as the F-35, five other programmes moved from red to amber in the latest published IPA review.
In terms of what we are doing on internal governance, the Minister for Defence Procurement has now started a regular GMPP review meeting with a particular focus on the reds and ambers trending down. At the delivery end in DE&S there is a programme of project review meetings led by non-executive directors on Mr Start’s board. We have followed up on some of the Sheldon recommendations about ensuring that senior responsible owners have a direct route into me or senior sponsors in head office where they are concerned about progress. We are taking the delivery governance seriously.
Lt General Sir Robert Magowan: Can I just add one extra thing to what Mr Start said, just to bring it to life further? You gave credit to DNS staff under Mr Start for what they have done in Ukraine.
Mr Francois: Yes, absolutely right.
Lt General Sir Robert Magowan: I can name three programmes in the DMPP that are red, which would go green tomorrow morning if we were going to war tomorrow night. We would be able to deliver FASGW-heavy, Brimstone 3 and SPEAR cap 3, if we needed to, but we are not prepared to take the level of risk that we are taking in Ukraine. We just need to ensure that we are comparing apples with apples.
Mr Francois: Can we take a bit more risk, then?
Chair: Let us not digress into other topics.
Q112 Mr Djanogly: I will move on to supply chain constraints. I am going to start off with paragraph 2.5 of the NAO Report. It says, “The MoD is also facing supply chain risks and industry capacity constraints, mainly due to skills gaps, shortages of key components and an increased demand for defence equipment in other countries in response to the war in Ukraine”.
It then gives a series of examples, one of which is that the Army has said the lead time for the delivery of semiconductors has increased from one to three weeks to more than 50 weeks. Mr Williams, from your point of view, has the NAO report got it right? Are there these supply constraints that it is talking about? What impact are they having on delivery of equipment plan projects?
David Williams: Yes, they have got it right. That specific example around the Army experience and access to semiconductors is directly relevant to the Boxer example that Mr Start talked about.
We have put in place a number of processes to give us better visibility below the prime contractor level of our supply chain, including up to around 700 companies that are active in the UK defence supply chain. We have been developing a measure of supply chain fragility or vulnerability. Given your role on the Defence Suppliers Forum, Mr Start, I wonder whether you might want to expand on that.
Andy Start: This is a very different world to the one that we lived in five years ago. There is no doubt significantly more pressure on raw materials and raw material access. Because of the war in Ukraine, there is incredible demand for existing products and equipment. That is pressuring down through the supply chain.
As a consequence of that, we have been having to work with the large primes within the Defence Suppliers Forum. The DSF covers about 80 companies directly and then the whole of the supply chain through the trade associations. We have been working with the large companies to make sure their supply chain teams are discussing supply chain fragility.
We have also changed the defence conditions or DEFCONs. Within contracts, the primes now have to provide us with visibility of the supply chain at least four levels down. We have created a supply chain visibility toolset, which now allows us to map this very complex web of interrelated suppliers both onshore and offshore. We can now see where things map.
Q113 Chair: That goes four tiers down.
Andy Start: Yes. For the most critical products we have also started to place investment in the supply chain where there have been weaknesses and issues, particularly in things like munitions.
Within the Government’s commitment to £560 million over two years in terms of improving defence resilience, we have been spending that money on not only enhancing production capacity but also working down through the supply chain particularly around chemicals, chemical supply and so on.
Q114 Mr Djanogly: I will come back to the foreign aspect, which we have not really covered yet, but to what extent are you reliant on delays that result in short-term savings but long-term overall cost increases? In the NAO Report, the Type 23 frigate, where repair costs have increased by £23 million to £100 million, is given as an example. To what extent are you using short-term savings but, as a result of that, then being hit for much larger costs down the line?
Andy Start: We have to balance the budget in any particular year. That always creates pressures on spend-to-save things that we would like to do but just cannot. That is a dynamic of defence. We have to make those decisions. We try to prioritise the things that will give us the greatest benefit.
The other dynamic we are facing at the moment is that we are seeing a very high operational tempo of our use of military assets. That means a number of assets that should be in for scheduled maintenance are not because they are out on operational deployment. We are building up something of a maintenance debt that we are going to have to work through as well. There are a few of those dynamics.
David Williams: It is reflected in our equipment plan, if you look at paragraphs 1.21 and 1.22 in the report. The phrase we use is “management adjustment for realism”.
In putting the plans together, frontline commands, in conjunction with Mr Start’s delivery teams or delivery teams elsewhere, will make an assessment of the realism of being able to deliver the programme in totality. Because we do not want to underspend—we want to get as much capability as we can for the budget—that is being factored in particularly within the early years of the programme.
It is not particularly a deliberate slowing down of any one programme but an assumption that the totality of the programme overall will probably arrive later than we have programmed.
Q115 Mr Djanogly: It is certainly not deliberate in terms of the operational aspects you mentioned and things being used. General, what are the capability implications of equipment being used and therefore not being replaced?
Lt General Sir Robert Magowan: That is why we have a replenishment programme for Ukraine. Mr Start and the team have got at that, particularly with regards to some of our missile defence systems but more broadly as well. We know we have to either replenish or take operational risk. That is why we have been given additional funding to do that twice, in both the autumn statement and the spring statement.
Q116 Mr Djanogly: Last week, on 15 January, as part of the “Defending the UK and Allies” statement, our colleague Jack Lopresti asked the Prime Minister, “Is it not time that we upscaled our industrial defence capacity so that we can continue to support our friends in Ukraine and replenish our own stocks?”
The Prime Minister’s reply was, “That is an excellent point. In a word, yes. That is why we have invested £2.5 billion in rebuilding our stockpiles. Beyond the money, we do need to build our defence industrial capability. That is a challenge shared across NATO that I have discussed extensively with partners, including the NATO Secretary-General. Of course, part of our agreement with Ukraine is how we can mutually help to support and grow our defence industrial complexes”.
Could someone—is it one for Mr Start?—please explain what the Prime Minister meant when he said “mutually help to support and grow our defence industrial complexes”?
Andy Start: One of my roles is to lead a programme called Project Hirst, which is our project of supporting Ukraine to build its defence industrial capability, its ability to domestically support the fight, while working in conjunction with UK industry.
Using a combination of UK funds and UK Export Finance, we are in the process of supporting UK industry to forum partnerships, joint ventures or other commercial arrangements with Ukrainian companies. Together with Ukraine, we are building industrial capacity for the fight. There are some real benefits to that.
Mr Djanogly: In Ukraine?
Andy Start: It is building capability both here and in Ukraine. I was out in Kyiv just before Christmas running the first of a series of conferences between the UK defence industry and the Ukrainian defence industry. I was pleased to be joined by the Ukrainian Defence Minister and their Minister for strategic supply, as we worked together to build up that capacity together.
I talked to you earlier on about the fact that in the fight some technologies are evolving every 90 days. The benefit that our industry gets from working with the Ukrainian industry is that real operational feedback into how its products are working and how it needs to adapt over time. That will make us more competitive in export as well as ensuring that our products adapt and remain relevant in the fight against Russia and others.
Q117 Mr Djanogly: I totally get that in terms of the cutting edge, but not all of it is cutting edge, like NLAWs or 155-millimetre shells. I understand that the Ukraine provision is being paid for from a separate pot, in effect. However, it is still coming from the same factories. Is there enough to go around, even if we can pay for it?
Andy Start: There is no question that industrial capacity across Europe is stretched, particularly in some areas like 155-millimetre munitions. Over the last 12 months, as part of the Ukraine Defense Contact Group, I have been working with my national armament director colleagues to build that capacity in both physical continental Europe and the US to increase industrial capacity.
An example of that in the UK was our investment in increasing the capacity of our 155-millimetre munition manufacturing capability with BAE Systems, under our long-term partnering agreement with BAE Systems. We have increased that capacity eightfold by investing in its underlying manufacturing capacity to support both our need and the need for Ukraine.
Q118 Mr Djanogly: As things stand, can the British public be satisfied that, if there was a war tomorrow, we would have enough 155-millimetre shells?
Andy Start: In conjunction with our allies—we have pooled capacity in those critical munitions with allies—we have enough capability to fight, if we needed to.
It is important to recognise that one of the reasons for that is that the adversary that is identified as our highest threat is currently engaged in a war with Ukraine. That is attritting its capability. Anything that we do to support Ukraine degrades our greatest potential adversary.
Mr Djanogly: General Magowan, would you like to add to that?
Lt General Sir Robert Magowan: Yes, a couple of things. First of all, we would have to have a closed session, understandably, on where we hold risk in the so-called TSR—the total stockpile requirement—against the state-on-state threat that Mr Start has been talking about. We are very happy to do that. Clearly, we would not want to do that in public.
The second point I would make is that I hate to predict the future, but I do not think NATO would be fighting in the way that the Ukrainians, unfortunately, are having to fight against the Russians in their own country. It would be a different fight. There would be a different demand on 155. That is all I would say at this point.
My role in Mr Start’s plan is to ensure that, as much as possible, there is a commonality of operational requirements between our requirements and Ukraine’s because that adds to industrial resilience.
Lastly, to answer your point directly about whether the British public should be confident that we can produce these stockpiles, we should think of an exponential curve going that way. It is going to take some time to ramp up from where we were five years ago to where we need to be. It is accelerating, but it is going to take a number of years, in certain cases, to get to the level that we need to reach against the total stockpile requirement for full warfighting.
Q119 Mr Djanogly: Looking at it from the other side of the coin, from the manufacturers’ point of view, they also need confidence that, if they are going to build new plants, those are going to be used. From your conversations with them, Mr Start, are they feeling confident about increasing their capability?
Andy Start: As per my conversation earlier on with Mrs Drummond, the industry is looking for a long-term commitment from Government to help it underpin its investment strategy. Together with industry, we have developed a munitions strategy that allows it to get the visibility that it needs. Our intent is to underwrite that in the long-term plan, which then creates the ability for it to scale up capability to meet the UK need.
To meet the Ukrainian need, we are working with it to provide as much visibility as we can about what Ukraine needs and sharing that with our other allies to help create the stimulus where they can invest. Certainly, in my conversations with chief execs, they are keen to invest, if we can give them enough clarity and certainty, and we are working hard to do that.
Lt General Sir Robert Magowan: The munitions strategy that Mr Start just mentioned was co-written between us and industry.
Q120 Mr Djanogly: Does it become easier if, as the Prime Minister said, we are going to be working across NATO?
Andy Start: It is absolutely easier if we do it across NATO. We are doing that as far as is possible within the current commitments under the Conference of National Armaments Directors, on which I sit.
We are keen to see the nations continue to work together to give a clear signal around their long-term commitment to Ukraine over the next five years or so. The stronger we can make those commitments, the easier it is for industry to make the investments it needs and to ramp up the capacity that we would all like to see.
Q121 Gary Sambrook: Permanent Secretary, if I may take you back to recruitment and retention, it is clearly a big problem at the moment. You must be looking at different assessments and at the way in which you can review what is going on and what the problems are at the core in the Department at the moment.
There are significant numbers of people leaving. When you are walking around the Department, you must be looking at people and thinking, “Why are they leaving?”
David Williams: There are a range of issues. I do not have with me the annual survey, AFCAS, but as part of that we ask a series of questions about which aspects of service life are retention-positive and which are retention-negative. We get quite a good feel from across the service population about the factors of their experience and, within the Armed Forces, what drives people to stay or to go. That is published. I would be happy to share it with the Committee, but I do not have it with me today.
There is a question around the wider economic situation. This is not an excuse, but we saw exit levels drop off quite markedly during Covid. More people were staying than is usual. Some of the effect that we are seeing is a correction of that period, but it is now stabilising at a level that is higher than the historic norm.
Q122 Gary Sambrook: From the answers we have been given today, a lot of the problems that people have been focusing on are caused by issues of retention and recruitment. The findings of that report should probably be imprinted at the forefront of your mind when walking around, making decisions and informing Ministers.
How far is your work to improve the number of senior responsible owners undermined by the inability to provide them with supporting teams?
David Williams: It is important to get the right support for SROs in terms of both the direct support that they get from programme directors in their immediate teams and the wider support that they get from delivery teams in Mr Start’s organisation as well. That is part of the issue there.
As part of our work on the broader procurement model, the broader operating model, there are other challenges for SROs around their direct control of projects in their programmes, which does not sit neatly with the way in which money flows around the organisation in our current setup, and the range of influence they have across all of the lines of development that go to make successful programme delivery. That is one factor but only one factor.
We have made good progress over the past year in increasing the proportion of SRO time that is spent on delivering programmes. We are now up at the 90% mark for SROs who are spending at least 50% of their time on major programmes. Where it is lower, they will be dealing with programmes that are allied or related capabilities. We are supporting them through training and accreditation, including of their programme directors. It is a live issue, but one that we are taking steps to address.
Q123 Gary Sambrook: Last week we learned that the Royal Navy’s support arm was being forced to use Serco to recruit deckhands. This is the first time in history that the Royal Fleet Auxiliary is not going to be directly employing people on Navy and Royal Marines vessels. This is going to cost you more money and it is not particularly conducive to keeping a good workforce in order either. This is not sustainable, is it?
David Williams: My understanding of that particular case is that we have a contract with Serco for certain port and dockside capabilities. I do not think that job advert is indicative of the health of recruiting potential in the RFA.
Q124 Chair: Just to be clear, Mr Williams, you are saying that the story was not accurate.
David Williams: Yes, I think that is what I am saying.
Q125 Chair: Let us call a spade a spade. Let us be clear that we are not asking private companies to provide people to serve on Royal Fleet Auxiliary ships.
Lt General Sir Robert Magowan: Again, the Permanent Secretary referred to this at the beginning. One of the major recruitment challenges is that we need to invoke greater flexibility in Armed Forces careers. We are in a different environment to when I joined the Royal Marines, 525 years ago.
We are in a position where we have to offer zig-zag careers or whatever it might be. Again, we do not have the report here, but quite often the reason people give for leaving is “inability to manage my own life”. That answer is more prevalent now than it was decades ago. We are getting after that. That is what the Haythornthwaite review identified.
Q126 Gary Sambrook: General, we are not alone in this challenge. There are reports of similar challenges with recruitment in the US. You want the best of the best. You want to be able to serve alongside the best of the best. In recent years, has there been too much emphasis on equality of output rather than equality of opportunity in terms of recruitment?
Chair: Do you want to explain what you mean by that?
Gary Sambrook: We have been looking at a more diverse range of people to go into the forces in particular, which is on one hand a good thing. When that becomes the sole focus of a recruitment campaign, that does not necessarily always yield results.
Lt General Sir Robert Magowan: Let me bring it home to the Royal Marines. About four or five years ago, the Royal Marines, along with the other frontline capability in the Armed Forces, welcomed women to join. Our view in the Royal Marines is that a diverse team is a stronger team. There is quite a lot of evidence that a narrow team can develop groupthink. Greater diversity, whatever it might be, whether it be gender or race, delivers a stronger and more challenging team.
I would refute that it is a distraction. It is something we should absolutely be getting after. History shows that it is a strength.
Q127 Gary Sambrook: Finally, Mr Start, the report states that you have identified 20 roles where you do not have the number of skilled staff you need, which included project managers, commercial staff, data scientists, business analysts and engineers. These are all highly competitive roles. Why can we not keep them or even recruit them?
Andy Start: We are able to recruit them. If we are focusing on the Civil Service, we are able to recruit them, but we do have a slow and steady attrition of this skillset. Why do we have a slow and steady attrition? It is because these are very attractive skills that are wanted in many industries that are currently vibrant. There are very low levels of unemployment. There is a lot of competition for these kinds of jobs. Fundamentally, we need more, coming out of our colleges and universities, to meet the national demand. It is an overall supply and demand issue.
What are we doing about it? We are trying to be clear that, while other people may pay more in some circumstances, we offer a competitive package that is a mixture of a good salary, a good pension and, most importantly, work that is genuinely meaningful, rewarding and enjoyable. We are hoping that message attracts more and more not just to DNS but to the wider defence industry, which is desperately in need of more skills.
Q128 Sarah Owen: Mr Start, General Magowan said earlier that we need a much stronger industrial base and you have said there is an assembly issue with some projects. We are seeing a decline in the UK manufacturing base as a whole. We have heard the news about Port Talbot steelworks closing. What is the MoD doing to secure the defence manufacturing sector in the future, particularly around bringing in skilled workers, such as apprentices, welders and platers, to secure the supply chain in the future?
Andy Start: Defence overall has an underlying industrial strategy that articulates its aspiration and then breaks that down into sector strategies covering each of the major areas of defence. In the shipbuilding space, for example, we have the National Shipbuilding Office, which is trying to blend the needs of UK military with the private sector.
We have done pretty well in shipbuilding. If you go back a decade, we had one plant that was actively manufacturing defence warships for the nation. We now have three. Each of those is building in more skills with skills academies that underpin them. Within that sector, there has been a really good story.
There are challenges. For example, there are not enough master welders to teach the apprentices. That creates a challenge for us. There is a rite of passage that you have to go through and learning takes time, but we are trying to work that as actively as we can with industry to help stimulate it. Where appropriate, Government have been doing their best to support them.
Q129 Chair: You say “stimulate”. If it is a question of time, you cannot just rush people through the training to become a master welder.
Andy Start: Yes. The dynamic is about working with them to create the academies, to encourage as many master welders into the system as we can and to be flexible where necessary to bring capabilities from partners and allies. For example, when we have managed to sell our design to an overseas shipyard, we work collaboratively with that shipyard but also encourage them to bring skills and capabilities into the UK and enhance our capabilities. That is what we have been doing in the maritime domain, which has been quite strong.
In the land sector, we have the land industrial strategy. To be honest, we have seen a renaissance in our capability from almost nothing in the UK, where we had seen it wither on the vine, to a capability where we are now very active with the building of Boxer. There are multiple manufacturing plants working on the Boxer programme. The Challenger 3 programme is very active and so on.
We are seeing good efforts. We are trying to work with industry through both our industrial strategy and the Defence Suppliers Forum in order to have a coherent plan with industry. It is a big job of work. The truth of the matter is that it is a challenging global environment. That is going to drive overall increased spending in this sector, and therefore we have to build industrial capacity.
Sarah Owen: I know time is tight, but I would really welcome if you could write to the Committee and explain some of those challenges, particularly the shortfalls around master welders and the very high-skilled jobs in defence manufacturing that we are looking at, and how we are going to get through that.
Chair: It is an important pillar of defence strategy to have an industrial strategy. When you talked about volatility earlier, Mr Start, there is volatility, but some of this is about long-term planning and pipelines, which is of concern to us.
Q130 Sir Geoffrey Clifton-Brown: I have two very brief things to mop up. Mr Wipperman, on figure 14, further to the questions by Mr Djanogly and Ms Owen on building manufacturing capacity, is that £5.01 billion a commitment in the budget? The NAO Report says that the MoD “intends” to invest. Which is it? Is it a commitment or an intention?
Tom Wipperman: On figure 14, the £560 million is agreed funding from the Treasury. The £1.95 billion is agreed funding from the Treasury. The £2.5 billion is a commitment that was made in the defence command paper refresh in July, which we will invest into the future. That does not represent new funding; it represents how we will reprioritise within the existing budget.
Q131 Sir Geoffrey Clifton-Brown: It will come out of the budget in due course.
Tom Wipperman: Yes, that is right.
Q132 Sir Geoffrey Clifton-Brown: Over what timeframe?
Tom Wipperman: We are already getting after munitions generally. We are working through that now and we would start to see it in future plans. It might be next year; it might be the year after.
Andy Start: Just to put that in context, against that £560 million, over £400 million of it is already on contract. Against the wider number, we have already spent over £1 billion on replenishment, which is already on contract. A lot of this is underway and there is more to come.
Q133 Sir Geoffrey Clifton-Brown: I have another question for you, Mr Start. In the dreaded GMPP list of red projects—I am asking this question carefully and no doubt you will want to answer it carefully—is there a problem with complex digital communication systems across a range of defence equipment?
Andy Start: I am going to carefully answer the question by saying that is delivered within Defence Digital and it would be unfair for me to comment. I will let David take the wider question.
David Williams: There are a range of challenges, and we have had hearings before this Committee before on the digital programme.
Chair: We had a whole set of sessions.
David Williams: Some of the programmes that are particularly challenging are, in my view, at the more basic end of our IT and digital infrastructure.
Q134 Sir Geoffrey Clifton-Brown: The basic end?
David Williams: Let me take the example of the MODNet Evolve programme. We bent out of shape in order to support hybrid and working from home during Covid. It is a programme that includes the delivery of laptops, for instance. We did a really good job in supporting that.
As a result, some of the other elements of the programme around the management of printed services and moving some of the secret domain to the cloud are taking longer than originally thought. This is not the most technical end, but it is fundamental underpinning infrastructure that has been disrupted through real-world events.
Q135 Sir Geoffrey Clifton-Brown: I wonder whether you are putting a bit of a gloss on that. Let me give you another example. Morpheus does involve complex digital communications. It is not the only one. There are others with complex digital communications.
David Williams: On digital transformation programmes generally, we are not alone in Government in this.
Chair: We have covered this. Just to be clear, we have done a separate report on this. You can keep your answer brief. We do not need to revisit it.
David Williams: Yes, there is a challenge. Some of the ones that are red are not at the most challenging end of the spectrum. That is all I meant.
Sir Geoffrey Clifton-Brown: They are not the most challenging.
David Williams: Not all of them, no.
Q136 Chair: We have an interesting challenge here, if I can put it politely, with the equipment plan. If we look back to last year, there was a £4.3 billion contingency in the plan and the worst-case deficit was just over £7 billion. If you add those two together, it does not even hit the size of £17 billion. It is not enough to close the gap, yet you have been quite buoyant today, as a team. Mr Williams, why are you so buoyant that you can manage this?
David Williams: The Defence Secretary gave a speech this time last week around the challenges in the international environment. I am loath to feel buoyant about that. Those are very real and present threats.
Against the Government’s commitment—although the timeframe is to be decided—that defence spending should increase over time, and against the headmark in capability terms around the exploitation of technology and the changes to our procurement system that we have pointed the way for in the defence command paper refresh last summer, we have a pretty clear idea of where we need to get to and a reasonable chance of having the wherewithal to get there.
Is it a challenging environment? Yes, absolutely. Based on the set of assumptions that we had when this snapshot plan was produced last year, there are a range of affordability challenges that we need to deal with, but we have work in hand to think about our priorities. We are making the case for our budget.
Q137 Chair: I just need to pick up on that. You are making a case, but you are waiting for the spending review as a major part of achieving this, and there is this assumption that you are going to get 2.5% of GDP for defence spending. You sound very optimistic that those two elements will be part of it, but yet we have not really had any discussion about reducing capability in order to meet the demands of the overall programme.
David Williams: We are working through what we need to do next year and maybe the year after to get us to the spending review. My point is simply that deliberately taking things out of the programme against an expectation and a Government policy that the budget will go up is not good value for money or a sensible set of decisions to take from a capability perspective. It is about managing that uncertainty over the next 18 months.
Q138 Chair: If you do not get the money, you are going to have to take capability out, are you not?
David Williams: Yes, but then a spending review is the proper process by which to have conversations with the Prime Minister and the Chancellor about how much is being invested in defence and what they get back for that investment.
Chair: We can go round and round on this. As I said at the beginning, it is a bit like groundhog day. The capability needs and the budget never seem to balance. We have gone over it a lot. We will revisit it again next year, whatever iteration of this Committee there is at that point. If it is in a year’s time, there will have been a general election in between. We know that for sure, by today’s date.
Thank you very much indeed for your time. The transcript of this session will be available on the website uncorrected in the next couple of days and we will be producing a Report before the Easter recess. Thank you very much indeed.